Premier Energies Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/njire76zdapwu4kbna9hdia4.pdf

Key Takeaways


The Flat Quarter: What Happened and Why It Reverses

Chiranjeev Saluja: "The contracts on the order book, which we generally share with the shareholders in the market, is firm order books. We never account for any framework or orders which have a possibility of order cancellation clauses."

Cell Capacity: The 7 GW Acceleration

Chiranjeev Saluja: "We feel that many companies have announced cell manufacturing plans. Most of this new capacity will take two to three years to come online and ramping up. So, with the demand being so strong and an attractive market opportunity to be captured in this period, we had actually gone back to the drawing board."
Chiranjeev Saluja: "Puneet, it's going to be India's single largest, single location, 7 gigawatt cell line, TOPCon line in one building."

Order Book and the Cell-vs-Module Dynamic

Chiranjeev Saluja: "The DCR portal was launched by the Government of India more for traceability rather than doing a financial analysis on sales and production."

New Businesses: Inverters, Transformers, BESS, Ingot Wafer

Vinay Rustagi: "You know, given that it is an assembly line business, the fixed asset turnover will be actually very, very high, something like between 7x to 10x. And the result of that will be that the overall return from capital will still be very attractive in line with the current business."

Margins, Costs, and the Silver Question

Vinay Rustagi: "So, I think our view is kind of very hard to say and we will have to see how things develop. But our view is generally that the prices have nearly stabilized and don't have much more room to go up from current levels."

US Expansion and the Policy Backdrop

Vinay Rustagi: "We had put our old plans on hold while all these changes were going on. But now, I think as we begin to kind of get more clarity, it does seem like, making it in the US is going to be very attractive, particularly as the IRA incentives for manufacturers will stay until almost until 2030, '31, '32."

Capital Allocation: No New Debt, Internal Accruals Fund Growth

Vinay Rustagi: "Our aim remains that we want to kind of focus on scale, on vertical integration, and adopting the latest technology. And we feel that, our business is poised to grow very strongly, given our plans for capacity expansion, backward integration, and diversification into new areas."

Guidance & Commitments

CommitmentSpecificsTimeline
New 1.2 GW TOPCon cell line ramp-upReach full utilizationDecember 2025
4.8 GW cell line commissioningLine comes onlineJune 2026 (implied Q4 FY26 / early FY27)
7 GW cell line commissioningIndia's largest single-location cell lineSeptember 2026
Total cell capacity target10.6 GWSeptember 2026 (advanced from FY28)
BESS first phase completion6 GWh line capable of ~4 GWh end productsJune 2026
BESS FY27 production2 to 3 GWh, ~INR 1,000 crores+ revenueFY27
Transformer capacity expansion2.5 GVA to 16.75 GVAApril 2026
Ingot wafer Phase 1 commissioning5 GWDecember 2027
Ingot wafer Phase 1 stabilizationFour to six months post line build-outFirst half calendar year 2028
KSolare revenue scale-upTreble current top lineNext 2 to 3 years
New businesses revenue contribution~30% of total revenueOver time (no date)
Debt postureNo new debt; become debt-free graduallyOver time (no date)

Key Metrics

MetricQ2 FY26
Revenue₹440 cr (per analyst observation), up from ~₹420 cr QoQ
Order wins₹6,511 cr in the quarter
Order book duration12 to 18 months
Cell realizationMarginally increased QoQ, no reduction in selling prices
Gross marginMarginally increased QoQ, driven by higher cell sales proportion and operating leverage
New TOPCon cell line target efficiencyAbove 25.2%, targeting 25.2–25.4%
Cell capacity expansion (4.8 GW to 7 GW) incremental capex₹502 cr, with 23% saving per GW versus greenfield
Cell and module expansion capex (7 GW cell, 5.6 GW module)~₹4,000 cr over next 12 months
Inventory build-up~₹300 cr incremental, due to shipment delays from rains and GST rate reduction
KSolare revenue (FY25)₹143 cr
KSolare target revenue at 0.1 crore inverters~₹1,500 cr, translating to ~3 GW capacity
Transcon capacity expansion2.5 GVA to 16.75 GVA by April 2026
Transcon EBITDA (last year)~₹30 cr
BESS first-phase capacity6 GWh line, capable of ~4 GWh end products, completion by June 2026
BESS expected FY27 production2 to 3 GWh, with realizations of ₹60–65 lakh per unit
BESS expected FY27 revenue~₹1,000 cr plus
Silver paste cost~$1.4 to $1.45 per watt, up from ~$0.01 a year ago
Forex gain driverINR depreciated from 85.7 to ~88 during the quarter
India cell capacity (current)~27 GW, production run rate 16–17 GW per annum
India cell capacity expectation by end-2027~80 GW
Solar capacity auctioned and allocated (utility scale)More than 100 GW
ALMM-2 cost impact on powerIncrease of ~₹0.10 per unit
Solar plus BESS tariffsLess than ₹3 per unit
Cell sales mix (external vs internal)~50:50 expected