Key Takeaways
- Record quarter, conservative guide: Q4 presales hit INR6,957 crores (up 48% YoY), but FY26 guidance of INR25,000-27,000 crores is deliberately conservative, with management preferring to "under-promise and over-deliver."
- Mumbai overtakes Bangalore: For the first time, Mumbai contributed more to quarterly sales than Bangalore, validating the geographic diversification strategy and the growing weight of non-South markets.
- Realizations surge on mix and pricing: Average realization jumped 36% YoY to INR14,113/sq ft, driven by premium launches and strong pricing power, even as full-year sales volumes dipped on deferred launches.
- Cash flow profile softens: Free cash flow profile slipped from 48 to 44-45, pressured by launch-stage project shifts, design revisions inflating upcoming project estimates, and collections timing.
- What to watch next quarter: Whether the INR12,000-13,000 crore Q1 presales target materializes, the pace of NCR land acquisitions, and any movement on the stalled Noida Bougainvillea Gardens and Mira Road approvals.
Sales Performance & Geographic Shift
- Q4 surge: Presales of INR6,957 crores were driven by a robust launch pipeline and strong customer response to premium offerings.
- Full-year drag: FY25 sales of INR17,023 crores fell 19% YoY, largely because launches were deferred, though pricing power partly offset the volume shortfall.
- Realization leap: Average residential, villa and commercial realization rose 36% YoY to INR14,113/sq ft, while plotted development saw a 50% YoY increase.
- Mumbai milestone: Mumbai sales overtook Bangalore for the first time in a single quarter, underlining the success of geographic diversification.
- FY25 mix shift: Bangalore contributed 45% of FY25 sales, Mumbai 30%, Hyderabad 23%, with the rest from other cities, a clear shift from earlier years.
- Collections lag sales: FY25 collections were flat at INR12,084 crores despite INR17,023 crores in sales, because Southern Star and Spring Heights launched just 2 and 7 days before March 31, pushing those collections into FY26.
- Demand steady: Management sees no red flags: if the product is right, absorption remains very strong across Bangalore, Mumbai, Hyderabad and Indirapuram.
Irfan Razack: "This time, we want to be conservative. We've got also INR20,000 crores worth of inventory. So the strategy is I'd rather under-promise and over-deliver."
Launch Pipeline & FY26 Outlook
- FY26 presales target: Management guided to INR25,000-27,000 crores, with Q1 alone expected to deliver INR12,000-13,000 crores.
- Launch ammunition: INR42,000 crores of launch pipeline is locked with "absolute certainty," plus another INR10,000-15,000 crores if pushed, and INR20,000 crores of ready inventory already in hand.
- Q1 FY26 headliner: The Prestige City Indirapuram, a marquee NCR township with a GDV of INR9,000 crores, has already sold over INR6,500 crores and will launch in Q1.
- Chennai and Bangalore: A Chennai launch is planned for June, pending RERA approval expected in the first week of June; Gardenia Estate in Bangalore launched and delivered roughly INR800-1,000 crores of revenue.
- Hyderabad additions: Prestige Rock Cliff and Prestige Imperial Park are slated for FY26, alongside a land deal for plotted development and a tie-up for roughly 0.9 crore sq ft of residential.
- Evergreen and Falcon City Luxe: These projects should launch in the next 2 or 3 quarters.
- Pallavaram, Chennai: Expected this quarter.
NCR Expansion & Market Entry
- Indirapuram breaks the ice: The Prestige City Indirapuram has validated the NCR entry, with management noting the market "really welcomed us" and confirming huge potential.
- Scale ambitions: Management expects NCR to eventually contribute as much as Bangalore does; there is no volume mass-market product there yet, but big acquisitions are being evaluated in Ghaziabad, Tier 2 NCR markets, Gurgaon and Noida.
- KG Marg: A small land parcel on KG Marg will come to market very soon.
- Noida Bougainvillea Gardens stalled: The project is held up by a government issue; management has tied a date but treats resolution as uncertain, noting "it's a global issue for everybody."
Irfan Razack: "We were trying to test out this market and the market has really welcomed us that shows there's a huge amount of potential here... we always knew there was potential. It's only a question of we had to break the ice there, and I think we have done it and done it in style."
Mumbai Portfolio & Key Projects
- Maiden handovers: The Prestige Jasdan Classic, Siesta at The Prestige City Mulund, and Prestige Turf Tower at Mahalaxmi were handed over, marking the first Mumbai completions.
- Jijamata (The Prestige Place): A mixed-use development with hotels, office, branded residences, a shopping center and residences for sale; SOM appointed as architects; premiums paid for FAR; planning a Waldorf Astoria hotel with Waldorf Astoria branded residences. Management is not hurrying, wanting the planning to come out well.
- Mahalaxmi Tower (The Prestige Turf Tower): Not for sale; only to rehabilitate turf estate tenants; Evergreen is also moving there; the company may not have anything left over unless it buys a few units.
- BKC and Prestige projects: Pre-leasing is underway and described as "very positive," though management declined to disclose quantum or tenant names due to confidentiality; construction is at full speed.
- Mira Road (Prestige Horizon Heights): Launch is targeted for FY26 but is waiting on MOEF clearance; the environment committee in Maharashtra has been disbanded, delaying the process.
- Valor Estate JV: Acquired a 50% stake for INR504 crores; the project has 4 basements and 11 floors, with excavation able to start almost immediately and completion targeted in 3 to 3.5 years on a fast track. The INR500 crores paid stays in the SPV; only when that is exhausted will further equity or debt be needed.
Irfan Razack: "We don't want to hurry this up. We want to do it well. We want the planning to come out really, really well."
Acquisitions, Spend & Capital Allocation
- Stake consolidation: Acquired balance stakes in PPPL (increased from 60% to 74%), PGEPL and Franklin Mumbai for close to INR1,500 crores, adding roughly INR20,000 crores of GDV.
- Bangalore infill: Acquired Phase 3 of Raintree Park for close to INR400 crores.
- No further PPPL buyout: Management has no intent to acquire the remaining 24% of PPPL this financial year, citing significant outflows that would pressure cash flows and debt.
- FY26 land spend: Targeting INR4,000-4,500 crores, with an expected GDV addition of INR30,000-40,000 crores.
- Acquisition discipline: Management looks for an EBITDA margin of 30-35% on new acquisitions and takes a conservative approach to pricing, ensuring projects can fund themselves.
- Dividend: INR1.8 per share declared for FY25, unchanged from FY24; the Board may declare an interim dividend if surplus cash flow materializes, but management maintains a conservative approach to avoid needing external funding.
Zayd Noaman: "We have a very balanced approach at looking at new acquisitions, where we believe that the project should fund itself... we look at an EBITDA margin of 30% to 35%, and based on this, we look at acquiring these assets."
Financials, Cash Flow & Completions
- Revenue and profitability: FY25 revenues of INR7,735 crores were impacted by slightly lower handovers; EBITDA was nearly INR3,000 crores with a 38% margin; PAT was INR617 crores with an 8% margin.
- Construction spend: Quarterly construction spend fell QoQ because Q3 included high spend on government approvals for Nautilus and TPC Indirapuram; the normal run-rate is INR1,600-1,800 crores per quarter, and incremental FY26 launches will not significantly add to FY26 construction spend since major outflows hit in FY27.
- Cash flow profile dip: Free cash flow profile declined from 48 to 44-45, driven by launches shifting from upcoming to ongoing, collections timing (INR3,000-3,500 crores in the quarter), upward revisions in upcoming project estimates due to design-phase changes including retail allocation, and area allocation changes.
- FY26 completions: Projects with INR17,000 crores of GDV are expected to complete in FY26; management estimates 70-80% can be handed over depending on the completion quarter, with EBITDA margins in the 25-30% range.
- Retail capex increase: An INR1,100 crore increase was attributed to upcoming projects where design specifications led to a relook at costs.
Hospitality & Commercial Assets
- Aerocity progress: The office component of 600,000 sq ft is already committed and leased; the hotel will be ready by year-end or early next year, with 4-5 months of simulation; office handover is by year-end; the hotel starts trading in July next year.
- BKC completion: Targeted for fiscal 2028.
- The Prestige (Mahalaxmi) completion: Calendar 2029.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 presales | INR25,000-27,000 crores | FY26 |
| Q1 FY26 presales | INR12,000-13,000 crores | Q1 FY26 |
| Launch pipeline | INR42,000 crores with certainty; INR10,000-15,000 crores stretch | FY26 |
| Land spend | INR4,000-4,500 crores, adding INR30,000-40,000 crores GDV | FY26 |
| Construction spend run-rate | INR1,600-1,800 crores/quarter | Ongoing |
| FY26 completions | INR17,000 crores GDV, 70-80% handover, 25-30% EBITDA margin | FY26 |
| No further PPPL stake buy | No acquisition of remaining 24% | FY26 |
| Aerocity hotel trading | July next year | Mid-CY26 |
| BKC completion | Fiscal 2028 | FY28 |
| The Prestige (Mahalaxmi) completion | Calendar 2029 | CY29 |
| Valor Estate completion | 3 to 3.5 years from now | ~CY28 |
Key Metrics
| Metric | Q4 FY25 / FY25 |
|---|---|
| New sales (Q4) | ₹6,957 cr, 48% YoY growth |
| New sales (full year) | ₹17,023 cr, 19% lower than FY24 |
| Area sold (Q4) | 0.45 cr sq ft across 2,301 units |
| Average realization (residential, villas, commercial) | ₹14,113 per sq ft, up 36% YoY |
| Plotted development average realization | 50% YoY increase |
| Geographic sales mix | Bangalore 45%, Mumbai 30%, Hyderabad 23%, other cities rest |
| Collections (full year) | ₹12,084 cr, up slightly from FY24 |
| Launches (Q4) | 1.4 cr sq ft across 4 cities |
| Launches (full year) | 2.56 cr sq ft with GDV of ₹26,223 cr |
| Revenue (full year) | ₹7,735 cr |
| EBITDA (full year) | nearly ₹3,000 cr |
| PAT (full year) | ₹617 cr |
| EBITDA margin (full year) | 38% |
| PAT margin (full year) | 8% |
| Office gross leasing (full year) | 0.41 cr sq ft, occupancy above 90% |
| Retail gross turnover (full year) | ₹2,264 cr, 99% occupancy, 1.8 cr footfalls |
| FY26 presales guidance | ₹25,000 cr to ₹27,000 cr |
| Q1 FY26 sales guidance | ₹12,000 cr to ₹13,000 cr |
| GDV pipeline for FY26 launches | approx. ₹42,000 cr, plus another ₹10,000-15,000 cr if pushed |
| Existing inventory stock | ₹20,000 cr |
| Land / business development spend (FY25) | approx. ₹5,680 cr, of which ~₹1,500 cr on stake acquisitions |
| GDV added via stake acquisitions (FY25) | close to ₹20,000 cr |
| GDV of projects expected to complete in FY26 | ~₹17,000 cr, 70-80% expected handover |
| EBITDA margin on FY26 completions | 25% to 30% |
| FY26 land spend target | ₹4,000 cr to ₹4,500 cr, translating to GDV of ₹30,000-40,000 cr |
| Total capex on BKC, Mahalaxmi, Delhi Aerocity | ₹7,000 cr to ₹8,000 cr |
| Dividend per share (FY25) | ₹1.8, up from ₹1.5 in FY24 |