Key Takeaways
- Revenue surged, margins collapsed: Q2 revenue grew 82% YoY to ₹120 crores, but EBITDA fell 17% YoY as the company executed low-margin orders and third-party product billing, with elevated input, freight, forex, employee and overhead costs.
- The BESS bet is now operational but unproven: The 1.2 GWh Jhajjar facility and Bakrol UPS plant commenced operations in September 2026, yet management expects only 25–30% utilization next year and peak utilization in three years.
- Order book is shifting toward private-sector, high-value work: Excluding the ₹856 crores BESS developer order, 70%+ of the remaining order book is now private, and the company has stopped bidding for government tenders below ₹5 crores bidding amount.
- Cash flow is deeply negative as inventory strategy bites: Operating cash flow was negative ~₹17 crores at September-end, driven by capex and a deliberate inventory build to ₹120 crores, with management arguing "whoever has stock is the king."
- What to watch next quarter: Whether the down-sell of the two BESS developer projects actually closes, whether the export sample wins approval and generates orders, and whether H2 margin pressure moderates as promised.
The Margin Trade-Off: Billing Continuity Over Profitability
- Deliberate compression: EBITDA margin fell to 7.83% in Q2 and 8.06% in H1 because management prioritized regular billing and market continuity over margin, executing low-margin orders and third-party product billing that carried thin spreads.
- Cost stack under pressure: Freight costs nearly doubled YoY, foreign exchange fluctuations hit fixed-price tariff contracts, and elevated input costs all compounded the margin squeeze.
- Factory overhead not yet absorbed: The Jhajjar and Bakrol facilities have started but all overhead costs cannot be recovered during the settling period, putting additional load on existing numbers.
- PAT margin percentage dropped in H1 because the dollar/rate "behaved very rudely" and customers were targeting minimum-to-minimum pricing.
Ram Agarwal: "Future is not dark at all. Future is very good. So, that was more important was the continuity to be there in the market with order and with execution. ... Our focus was on delivering number. Even if the margin is on the lower side, important was to have the regular billing done on the books."
BESS: The Core Growth Engine, Now Facing Headwinds
- Manufacturing capacity now live: A 1.2 GWh BESS assembly facility in Jhajjar (scalable to 3 GWh with three shifts) and a UPS assembly plant in Bakrol (3,000 pieces per day capacity) commenced operations on September 25, 2026.
- New orders flowing, but modest: ₹54 crores of new BESS orders were taken for execution in the current fiscal year, with ₹36 crores of BESS orders already built in the current financial year, plus an additional 33 MWh from a portfolio of reputed customers.
- Developer projects are underwater: The two large BESS developer projects face cost increases in lithium, DC blocks, and the dollar versus when they were priced, creating margin depletion risk on any down-sell.
- Industry commoditization is real: 90% of BESS players are "in doldrums" because unknown new entrants crashed prices while China simultaneously increased its prices.
- Down-sell discussions active with around 6 or 7 industry players for the two developer projects, and could close "any moment — this quarter, next quarter, any moment," though margin on any sale is uncertain given cost escalation.
- Export pathway opened: A sample home energy storage system (around 16 kilowatt) was shipped to an international customer in October 2026, with good export volume expected in FY28 if the sample is approved, though the country was not disclosed.
Management: "Whatever BESS project has been taken, it's not facing a good north wind, rather it's a south wind, in terms of execution and the project cost. So that, it's a headwind right now. But market is very big."
Order Book & Strategy Pivot
- Private-sector shift underway: If the ₹856 crores BESS developer order is removed, over 70% of the remaining order book is private, and in H1 the majority of billing came from private customers.
- Government bidding curtailed: The company has stopped bidding for government tenders up to ₹5 crores, focusing instead on selective, high-value tenders where few companies qualify, and has appointed an MD to route billing through partner channels rather than direct government bidding.
- Strategy effect lag: The pivot to private-sector and partner-channel bidding has been underway for six months, and this you will see a very big effect in the next financial year.
- Manufacturing identity reinforced: Management explicitly wants to remain a manufacturer, OEM, and solution provider, not a typical EPC where "top line is big and bottom line is very minimal," and expects local domestic content to be a differentiating factor if import restrictions extend to batteries as they did with solar.
Management: "We have not built any kind of a developer or EPC. We want to remain focused as a manufacturer, OEM and a solution provider. So, we don't want to call ourselves as a typical EPC where the top line is big and bottom line is very minimal."
Working Capital & Cash Flow Strain
- Working capital days rose from 185 in FY26 to 192 in H1 FY27, driven by three factors: higher inventory (₹120 crores vs ₹76–77 crores earlier), increased government deposits from higher GST input credit (₹18.5–19 crores), and supplier advances.
- Receivables skewed by September billing: ₹90+ crores of billing occurred in September 2026 alone, inflating the quarter-end receivables position, with additional big collections expected from two major parties by December.
- Operating cash flow negative ~₹17 crores at September-end, improved from ~₹49 crores negative at March 2026, but management is only "trying best" to make it positive by FY27-end given ongoing capex and inventory needs.
- Inventory strategy is deliberate: Management views high inventory as a competitive advantage, stating "today, whoever has stock is the king," and expects absolute inventory levels to rise further with expansion even if days decline.
- Debt will increase to support stock inventory and BESS facility working capital requirements.
Management: "Today, whoever has stock is the king."
BESS Industry Dynamics & Competitive Positioning
- Commoditization pressure: The BESS sector has become "commodity more than the technical product or solution," with new unknown players crashing prices while China increased its prices, putting 90% of the industry in distress over the last year.
- C&I margin opportunity: Commercial and industrial BESS margins are "big," and if the company can do good BESS volume, that would comfortably deliver good margin, though utility-sector pressure will take more time to moderate.
- Policy tailwinds uncertain in timing: The government is "about to launch" a VGF scheme of INR 14,500 crores with 30 GWh for BESS, and is reportedly considering a ban on export of second-hand lithium so recycling can be done in India, though management is "not very sure" on the latter.
- Capacity ramp is gradual: BESS capacity utilization is expected at only 25–30% next year, with the facility taking shape over the next 2–3 years and peak utilization expected in three years, though the second year will also see good growth.
- BESS will be the majority contributor to incremental revenue growth next year, with manufactured solutions and BESS segments expected to go up while solar EPC volume may not continue at current levels without high-value orders.
Management: "As you correctly said, this has become commodity more than the technical product or solution. And that's why the whole industry is in trouble, because all the new player, unknown player has just jumped in and they have crashed their prices and in opposite, China's increased their prices. So, 90% of beta in last one year, all are in doldrums."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue | Around ₹500 crores, based on ₹260–266 cr order in hand plus ₹25–30 cr from channel | FY27 full year |
| FY27 EBITDA margin | Above 11% | FY27 full year |
| FY27 PAT growth | Positive in absolute terms | FY27 full year |
| FY28 revenue growth | Minimum 25% | FY28 full year |
| FY28 EBITDA margin | Return to 12–13% level | FY28 full year |
| FY28 PAT margin | 8.5% to 9% | FY28 full year |
| BESS capacity utilization | 25–30% next year, peak in 3 years | FY28 / FY30 |
| Down-sell of BESS developer projects | Could close any moment; active discussions with 6–7 players | This quarter or next |
| Export volume from energy storage | Good volume expected if sample is approved | FY28 |
| Operating cash flow | Trying to make positive by FY27-end, but capex and inventory are headwinds | FY27 year-end |
| Big collections | Expected from two major parties | By December 2026 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue from operations | ₹120 crores, +82% YoY |
| H1 FY27 revenue from operations | ₹196 crores, +62% YoY |
| EBITDA | ₹9 crores, -17% YoY |
| EBITDA margin | 7.83%, vs 8.06% in H1 FY27 |
| PAT | ₹6 crores, -27% YoY |
| PAT margin | 5.08%, vs 5.46% in H1 FY27 |
| FY27 revenue guidance | ~₹500 crores, with order in hand of ₹260–266 crores plus channel revenue of ₹25–30 crores |
| FY27 EBITDA margin guidance | Above 11% |
| FY28 revenue growth guidance | Minimum 25% |
| FY28 EBITDA margin guidance | 12% to 13% |
| FY28 PAT margin guidance | 8.5% to 9% |
| Order book | ₹1,121 crores, across 97 ongoing projects |
| BESS, EPC and developer projects in order book | ₹909 crores, 81% of total order book |
| BESS developer order | ₹854 crores, carrying annual rental of ₹62 crores over 12 years |
| Working capital cycle | 192 days as of H1 FY27, vs 185 days in FY26 |
| Inventory level | ~₹120 crores, vs ~₹76–77 crores earlier |
| Receivables | ₹201 crores in October 2026, down from ₹257 crores at H1 end |
| Operating cash flow | Negative ₹17 crores at September 2026 end, improved from negative ₹49 crores at March 2026 end |
| Jhajjar BESS facility capacity | 1.2 GWh under single shift, scalable to 3 GWh under three shifts |
| Bakrol UPS facility capacity | 3,000 pieces per day, revenue potential of ₹500–600 crores per year |
| BESS capacity utilization expected next year | 25% to 30% |
| BESS developer project equity IRR | More than 12% to 13% |