PSP Projects Ltd Q1 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/65zv27esxebvh26gq8l1zpc0.pdf

Key Takeaways


The Q1 Labor Shock

Prahaladbhai Patel: "Because of which we were having a very big problem in terms of getting labor in April and May 2022. And that's the reason that this quarter we could not deliver to an extent of 20-25% growth compared to the Q4FY22."

Order Book & Bidding Strategy

Prahaladbhai Patel: "So as we have already reached to order book of INR 1000 Crore plus in the first quarter, I think we'll be going a little bit slowly and safely."

Project Portfolio Health

Prahaladbhai Patel: "I think there is some misunderstanding, I have never committed on the private residential sector. I always look at the project value and really, as far as developing business is concerned, we are too much cautious..."

Margins & Cost Structure

Prahaladbhai Patel: "See, if you know the benefit on the existing projects, we'll simply survive from losses. So I think that this is the benefit blessing in disguise that some of the projects are on fixed prices, which we floated in March 2021."

Precast & Capex


Guidance & Commitments

CommitmentSpecificsTimeline
Full-year order inflowApproximately ₹2,200 croreFY23
Full-year revenueMinimum ₹2,200 crore, confident of achieving with existing order book "without any fail"FY23
Incremental order inflowBroadly ₹2,000 crore minimumFY23
Maharashtra stalled project restartWork to re-start, re-allotted at slightly higher value; "minimum by Q3 something should be positive"By Q3 FY23
IIM Ahmedabad old campusCompletion expectedBy March 2023
UP medical projects (most)Completion expectedBy March 2023
UP medical projects (Sonbhadra, Khushinagar)Completion expected, sites handed over 2 months agoBy July 2024
Long-term PAT marginMaintain in 7% to 8% rangeOngoing
Long-term EBITDA marginMaintain in 11% to 13% range, quarter-to-quarter variation expectedOngoing
Precast EBITDA margin11% to 12%Ongoing

Key Metrics

MetricQ1 FY23
Revenue from operations₹345 cr, +8.8% YoY
EBITDA₹47 cr, +19.6% YoY
EBITDA margin13.64%, vs 12.42% in Q1FY22
Net profit₹28.51 cr, +13.5% YoY
PAT margin8.13%, vs 7.8% in Q1FY22
Order book₹4,613 cr, highest ever
Q1 order inflow₹550 cr, vs ₹4.89 cr in Q1FY22
FY23 order inflow till date~₹1,100 cr, 70% institutional orders
FY23 revenue guidance₹2,200 cr, ~25% growth over FY22 (management confirmed the growth percentage)
FY23 minimum incremental order inflow expected~₹2,000 cr
Bid pipeline~₹4,000 cr, 41% private, 51% from Gujarat
Employee expense growth+43.5% YoY, due to annual appraisals, increments, and higher managerial remuneration
Working capital days35 days net (debtor days 70, creditor days 54, inventory days 19)
Long-term borrowing₹50 cr, up from ₹34 cr; ₹20 cr loan at 7% for sports complex
Short-term borrowing₹67 cr, vs ₹66 cr in Mar 2022; expected range ₹60–75 cr
Fixed deposits₹317 cr, of which free deposits ₹140 cr
Unbilled revenue₹128 cr, mainly Kashi and other major projects
Government projects share of order book63% of all business verticals
EPC and turnkey projects share83% of portfolio
Ongoing projects46 projects, 43% Gujarat, 41% UP, 16% Maharashtra, 0.3% Rajasthan
UP projects Q1 revenue₹34 cr; cumulative revenue ₹182 cr
Surat Diamond Bourse Q1 revenue₹53 cr; cumulative revenue ₹1,856 cr
Precast facility Q1 revenue₹14 cr
Private residential projects order book₹694 cr
Bhiwandi and Pandharpur share of order book16% of outstanding order book, slow-moving
Interest cost sustainable annual run rate₹65–70 cr