Key Takeaways
- Revenue hit by labour, not demand: Revenue fell 16% YoY to ₹513 crore as a 37% labour shortfall in April-May choked execution, not because orders dried up. The shortfall has since narrowed to 19%.
- Adani pipeline is the story: Management is in talks for ₹8,000-9,000 crore of Adani Group projects, with ₹7,500-8,000 crore of inflow possible this year. That would more than double the existing ₹4,500 crore order book.
- Margins promised, not yet delivered: EBITDA margin guidance held at 8-9%, with a recovery expected from Q2 or Q3. Q1 saw employee costs spike to 6.8% of revenue and a ₹4.5 crore charge on a UP project.
- Balance sheet stretched before the advance arrives: Debt rose ~₹100 crore QoQ on capex and working capital. Management expects Adani mobilization advances of minimum ₹750 crore to drastically reduce fund-based working capital by end-Q3.
- What to watch next quarter: Whether the Adani order inflow actually converts from discussion to signed contracts, whether labour availability normalises enough to execute, and whether the promised margin recovery to 8-9% shows up in Q2.
Labour: The Quarter's Binding Constraint
- 37% shortfall at the worst point: April-May 2025 saw labour availability drop by over a third, driven by seasonal factors: Holi, marriage season, and two Eids within 15-20 days. Workers who had returned to villages after projects concluded in March did not come back in time for new starts.
- Not a wage or facility problem: Management explicitly stated the shortfall was not because PSP's facilities, salaries or infrastructure lag peers. It was purely seasonal timing around new project starts.
- New projects hit hardest: The majority of newly awarded projects worth ₹1,600 crore started after March 2025 and are at the foundation stage, where labour deployment is highest. That is exactly where the shortage bit.
- Shortfall easing but not over: The gap narrowed to 19% by the call date, and management is confident it will reduce further from August. A minor impact of both labour shortage and monsoon will still be felt in Q2.
- Structural response underway: The company is investing in advanced formwork technology (Peri table forms that cast 50 sqm slabs in one go), training unskilled labour from Odisha and West Bengal, and targeting a 30-40% reduction in labour requirement versus prior years.
Patel: "We are purely understanding the labor situation is not going to help the organization, and this will continue throughout the year. And day by day, the country's economy is growing fast. So we are very much serious to work on that part also."
The Adani Order Book: Scale and Terms
- Pipeline of ₹8,000-9,000 crore under discussion: Management is in active talks with Adani Group for projects of this scale, with ₹7,500-8,000 crore expected to convert to order inflow this fiscal year.
- Mobilisation advances change the working-capital math: Adani Group contracts carry 5% mobilisation advance upfront and another 5% after mobilisation. On ₹7,500 crore of inflow, that implies minimum ₹750 crore of advances, which management expects will drastically reduce fund-based working capital from banks by end-Q3.
- Open-price contracts, not fixed-price: Almost all group projects use item-rate or open-price contracts where cement has a base rate and any major material price difference is reimbursed. This limits commodity risk on the incoming order book.
- Margins comparable to non-Adani work: Management stated Adani Group margins are the same as non-Adani projects, with blended expectations of 9-10% for non-Adani and 8-9% overall.
- First-priority positioning: If PSP proves it can execute on the ground, management believes it will be given first priority on most Adani projects. A small Mumbai office has been opened and key people appointed to manage projects directly.
Patel: "If we can prove on ground and we are able to handle them, most of the projects, we will be given the first priority always."
Project-Level Execution: What Moved and What Stalled
- Eight projects completed in Q1: These included Project Aster at Adani Shantigram, Nestle Phase II at Sanand, precast supply to L&T and Kutch Copper, and a school building in Jodhpur.
- Fintech Building at GIFT City: Client-side delays are now resolved; the revenue shortfall in Q1 was purely due to labour availability.
- Science City: No work happened in Q1 because of a deliberate technology switch from conventional formwork to a modular jump-form system.
- GMC and Dharoi Dam: Both remain on hold due to land acquisition delays.
- SMC: Considerable delay in receiving drawings from the client; finishing work has not started. Facade is now approved and materials ordered; management expects to be in a better position to work on MEP, civil, finish, interior and facade by end-Q2 or early Q3. The project cannot go beyond FY27.
- Palladium Mall, Surat and Gati Shakti Vidyalaya: Both started last year and suffered monsoon delays and some April-May disruption this year. Palladium has all drawings in place and should move regularly from August; Gati Shakti buildings are out of the basement at first/second floor level with finishing and MEP to gear up.
- Dharavi: Sheet piling for basement excavation is in process. The project has a 36-month timeline; management expects to answer detailed questions by October-November once basement work has started.
Margins: The Bridge from Here to 8-9%
- Employee cost spike to 6.8%: Normal range is 4-5% of revenue. The jump reflects hiring at various levels for new Adani order wins, layered on a quarter where revenue itself contracted 16% YoY.
- UP project added ₹4.5 crore of one-off cost: Projects in the handover phase are seeing additional expense because hospitals are not yet operating, the department is not maintaining efficiently, and the contractor is being taken advantage of. Management is not sure the additional cost will stay under ₹5 crore; some may spill into Q2.
- ECL provision of ₹8.68 crore: Includes ~₹4 crore for the Pandharpur project, whose entire ₹17 crore receivable is now fully provided for. Both Bhiwandi and Pandharpur projects are over. Some additional provision is possible in Q2 depending on receivables.
- Material cost ratio swung 800 bps YoY to 38.51%: This is a mix effect, not inflation. MEP work carries 80-90% material component, core-and-shell civil 45-50%, and finishing 70%. The ratio depends entirely on which activities dominated the quarter.
- Capex will stay at 3-4% of revenue: For large Adani Group projects, it could move 0.5% plus or minus. FY26 and FY27 are expected in the same range.
Patel: "Since the closure of the project has not happened, they are taking undue advantage of the contactor, and that's how it has happened."
Order Book Composition and Non-Adani Opportunities
- Order book stood at ~₹4,500 crore after one project was short-closed, reducing the executed amount and creating a ~₹300 crore QoQ difference.
- Non-Adani bidding will be selective: PSP will bid for prestigious projects like the Ambaji Corridor development (earlier tender rejected as a single tender, expected to be reissued). But management was clear: "mostly orders will be from Adani."
- Revenue visibility for next year: With the existing ₹4,500 crore order book and new orders expected at 2x to 3x that, management believes it can easily deliver ₹4,500 crore of revenue next year.
- Revenue guidance deferred: Management will only give revenue guidance after Q2, because Adani Group projects will start in Q2 or Q3. New orders coming in Q2 will see work start in Q3, with basement work only from Q4.
- Precast ambition: Within 1-1.5 years, PSP expects to generate precast revenue of up to ₹500 crore. The business previously supplied ₹300 crore worth of precast elements to the bullet train project and has now initiated four buildings of 60-70m height, which may limit capacity for outside orders.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Labour shortfall reduction | Shortfall to reduce further; minor impact remains in Q2 | Starting August 2025 |
| Order inflow from Adani Group | ₹7,500-8,000 crore from projects under discussion | FY26 |
| EBITDA margin recovery | 8-9% range | Q2 or Q3 FY26, probably Q2 |
| Revenue guidance | Will provide after seeing first two quarters | After Q2 FY26 |
| Working capital / debt improvement | Fund-based WC from banks to reduce drastically via Adani mobilisation advances (min. ₹750 crore) | By end-Q3 FY26 |
| SMC project completion | On track; cannot go beyond FY27 | FY27 |
| UP project additional cost | Not more than ₹5 crore total, some possible in Q2 | Q1-Q2 FY26 |
| Capex as % of revenue | 3-4% range, ±0.5% for large Adani projects | FY26 and FY27 |
| Precast revenue scale-up | Up to ₹500 crore | Within 1-1.5 years |
| Dharavi project | 36-month timeline; detailed update possible once basement excavation underway | October-November 2025 |
Key Metrics
| Metric | Q1 FY26 |
|---|---|
| Revenue from operations | ₹513 cr, decreased 16% YoY from ₹612 cr |
| EBITDA | ₹24 cr, decreased 67% YoY from ₹73 cr |
| EBITDA margin | 4.77%, vs 12% in Q1 FY25 |
| Net profit | ₹13 lacs, reduced 100% YoY from ₹34 cr |
| Employee cost as % of revenue | 6.8%, vs typical range of 4% to 5% |
| Additional expense on UP projects | ₹4.5 cr, booked in Q1 FY26; up to ₹5 cr possible in Q2 |
| ECL provision | ₹8.68 cr, vs ₹4 cr in Q1 FY25; includes ₹4 cr for Pandharpur project |
| Order book (work on hand) | ₹6,514 cr as on June 30, 2025, 11% YoY growth; Adani projects 27% |
| Order inflow | ₹107 cr excluding GST in Q1 FY26 |
| FY26 order inflow guidance (Adani) | ₹7,000 cr to ₹8,000 cr, projects under discussion |
| FY26 EBITDA margin guidance | 8% to 9%, maintained; expected from Q2 or Q3 |
| Labor shortfall | 37% during April-May 2025, reduced to 19% at present |
| Net unbilled revenue | ₹556 cr as on June 30, 2025 |
| Receivables | ₹525 cr as on June 30, 2025 |
| Short-term borrowings | ₹338 cr excluding short-term maturities of ₹25 cr |
| Mobilisation advance | ₹326 cr as on June 30, 2025 |
| Capex incurred | ₹32 cr in Q1 FY26, mainly plant and machinery, formwork, cranes |
| FY26 capex guidance | 3% to 4% of revenue, plus or minus 0.5% for Adani projects |
| Non-Adani margin guidance | 9% to 10% |
| FY26 revenue guidance (per an analyst's math) | ₹4,500 cr for FY27, based on order book of ₹6,514 cr and expected inflows |
| Precast facility revenue target | ₹400 cr to ₹500 cr, currently at 50%+ utilization; target within 1-1.5 years |
| Cost of material consumed as % of total expense | 38.51%, up from 30.03% in Q1 FY25, rise of over 800 bps YoY |