Key Takeaways
- Strong quarter, guidance held flat: Revenue grew 70% YoY to Rs.607 crore, yet management declined to raise the full-year Rs.2,600 crore target, sticking to its original view.
- Margin uplift from UP project close-out: EBITDA margin improved to 12.2% (from 10.83% YoY) as revenues previously on hold at near-complete UP projects converted into bills.
- Balance sheet stretched by execution: Short-term borrowings jumped to Rs.377 crore and operating cash flow turned negative for H1, driven by unbilled revenue build-up and a drop in unearned revenue.
- Order book dipped, but pipeline is full: The order book declined 4% YoY to Rs.6,500 crore on fast execution; management expects Rs.3,000 crore of inflows for the year, with over Rs.1,000 crore converting by December.
- What to watch next quarter: Whether the Rs.1,000 crore order inflow converts by December, whether the two delayed unbilled revenue claims finally close, and whether the Delhi Railway Station JV bid proceeds.
Revenue & Margin Performance
- Top-line jump: Revenue hit Rs.607 crore, a 70% YoY rise, driven by higher execution across ongoing projects and UP projects reaching an advanced stage of completion.
- Margin mechanics: EBITDA margin rose to 12.2% from 10.83% a year ago because the majority of UP projects are near completion, so revenues that were on hold got converted into bills. Other expenses also fell significantly due to a reduction in consultancy expense with no special reason cited.
- Finance costs doubled: Finance cost rose from Rs.7 crore in Q1 to Rs.12 crore in Q2, mainly due to an increase in short-term borrowings during the quarter. Depreciation also climbed from Rs.9 crore to Rs.14 crore on Rs.79 crore of fixed asset additions.
- H2 skew intact: Management noted the first two quarters are always a little less than the last two for construction companies and confirmed the company is on track for the full-year Rs.2,600 crore revenue target.
P. S. Patel: "This year's margin is a little bit better because majority of the UP projects are near to completion, so some of the revenues which were on hold got converted into bills, so that way you see better margin this quarter."
Balance Sheet & Working Capital
- Short-term borrowings surge: Short-term borrowings increased from Rs.107 crore in March 2023 to Rs.377 crore in September 2023, attributable to higher inventories, capex payments, and other financial assets.
- Cash flow turned negative: Operating cash flow was negative for H1 due to a reduction in unearned revenue (from Rs.60 crore to Rs.20 crore) and other liability items. Total cash including FDs stands at around Rs.285 crore.
- Unbilled revenue is the lock-up: The increase in current assets mainly reflects unbilled revenue, including carry-forward amounts from earlier years that have not yet been converted to GST bills. Two projects, Surat Diamond Bourse and Kashi, are delayed in finalization due to difficult escalation discussions post-Corona and pending issues on the lump-sum contract at Kashi that need top-level discussion.
- Collection catalyst ahead: Management expects the unbilled revenue issue to be concluded by Q3 FY24, which should reduce short-term borrowings by Rs.50-100 crore once those amounts convert into cash flow. Cash conversion days, currently at 42-43 days, are expected to improve to 30-35 days as UP projects near completion and due payments convert.
- Debt level anchor: Combined debt will be on the lower side compared to this quarter once UP projects are over and funds are received; debt is expected to be fixed at around Rs.300 crore, not reduced by Rs.200 crore.
P. S. Patel: "That is only because of these two projects we are getting delayed because of finalization. Otherwise, generally, the bills do not get delayed to such an extent."
Order Book & Bid Pipeline
- Order book dipped on fast execution: The order book stands at Rs.6,500 crore (excluding Delhi), a marginal 4% YoY decline, because execution and completion of ongoing projects outpaced order inflow. It contains a few projects of scale around Rs.1,000 crore each: Rewari AIIMS, a Museum project in MP, and a University project in Vadodara at Rs.775 crore.
- Inflow target maintained: Management maintains its guidance of nearly Rs.3,000 crore in order inflow for FY24, citing a robust bid book. Bids worth more than Rs.2,500 crore are already submitted and awaiting conversion, with over Rs.1,000 crore expected to convert by December.
- Delhi Railway Station is the next big swing: The company will bid for the Delhi Railway Station project (Rs.4,800 crore), which is not included in the current Rs.6,500 crore bid book. The bid must be via a JV because the project requires bridge experience that PSP does not have in-house; the bid submission is due by end of November 2023, possibly extended 10-15 days for Diwali.
- Ahmedabad station lost: The Ahmedabad railway station tender went to DR Agrawal as the lowest bidder; PSP stood 3rd or 4th among six bidders and it is no longer part of the bid pipeline.
- Closing book expectation: The order book is expected to close FY24 in the range of Rs.5,500 crore to Rs.6,000 crore.
Precast & Capacity
- Precast investment nearly complete: The company is almost done with its precast investment; a new shed has been constructed for infrastructure and no major further investment is expected, though some assets may need to be bought going forward. Remaining capex is not more than Rs.10-15 crore, or 3-4% of revenue.
- Revenue potential: At optimum utilization, the precast facility is expected to generate more than Rs.200 crore to Rs.225 crore in revenue.
- Mould fungibility: Moulds made for bullet train ducts (data ducts, electrical ducts) can be utilized for road infrastructure such as drains, storm water drains, and drainage lines, offering a second life for the asset base.
- Output measured in cubic meters: Management noted it is not possible to convert precast output into square feet; it is measured majorly on the quantity of work done daily in cubic meters of concrete. When the plant moves purely into residential or commercial buildings, output can then be expressed in square feet terms.
P. S. Patel: "it is not possible to convert it into square feet output of the precast plant, but it is majorly on the quantity of work we do every day in terms of cubic meter of concrete now. When we go into purely into buildings, when you construct a totally residential building or a commercial building, then you can say it has increased from 0.1 crore to 0.3 crore."
Competitive Environment & Strategy
- Bidding discipline over volume: Management acknowledged competition is aggressive on some projects but stated the company will stick to its margins and not enter the rush. It prefers project sizes of Rs.150-200 crore and has the capacity to handle 50 projects at a time.
- Election risk seen as manageable: Management does not see any slowdown of bids from the government or private side due to the upcoming election; even if there is a disturbance of 1-1.5 months, it still expects to achieve the Rs.3,000 crore order inflow projection.
- Litigation timeline: Both ongoing arbitrations (including Pandharpur, where the Arbitral Tribunal has now been formed and a preliminary hearing will be held in coming months) are not considered complicated; management expects closure within one year, as the arbitration process per government norms must be completed within 12 months once the case starts.
P. S. Patel: "Competition is there. People are a little bit aggressive at some of the projects, but we in general, we will stick to our margins, and we will try to maintain our order inflow because we would not like to enter into that rush of market where people are much aggressive."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue | Rs.2,600 crore for FY24; on track | FY24 |
| EBITDA margin | 11% to 13% range; depends QoQ | FY24 |
| Order inflow | Nearly Rs.3,000 crore for FY24 | FY24 |
| Closing order book | Rs.5,500 crore to Rs.6,000 crore | FY24 end |
| Order inflow conversion | More than Rs.1,000 crore to be converted | By December 2023 |
| Unbilled revenue collection | Two delayed projects to be concluded | Q3 FY24 |
| Short-term borrowing reduction | Decrease of Rs.50-100 crore after unbilled revenue converts to cash | After Q3 FY24 collection |
| UP projects completion | Should be through, rest closed by March; may extend to April 2024 | March-April 2024 |
| Delhi Railway Station bid | Bid submission via JV | End of November 2023 (may extend 10-15 days) |
| Arbitration closure | Both cases to close | Within one year |
| Capex | Not more than Rs.10-15 crore remaining | Ongoing |
| Cash conversion days | Improve to 30-35 days; less than 40 days in near future | Near future |
| Sustainable revenue growth | Targeting 20%-25% growth; needs order inflow of Rs.4,000 crore | FY25-26 onwards |
Key Metrics
| Metric | Q2 FY24 |
|---|---|
| Revenue from operations | ₹607 cr, up 70% YoY |
| EBITDA | ₹74 cr, up 91% YoY |
| EBITDA margin | 12.15%, vs 10.83% in Q2 FY23 |
| Net profit | ₹39 cr, up 71% YoY |
| PAT margin | 6.4%, vs 6.3% in Q2 FY23 |
| Order inflow | ₹175 cr in Q2; ₹934 cr in H1 FY24 (excl. GST) |
| Order inflow as on date | ₹958.62 cr; L1 in additional ₹102 cr |
| Order inflow guidance for FY24 | ~₹3,000 cr |
| Outstanding order book | ₹4,898 cr, down 4% YoY; 52% govt, 48% private |
| Bid book | ~₹6,500 cr, plus Delhi Railway Station redevelopment ₹4,800 cr |
| Revenue from UP projects | ₹268 cr in Q2; cumulative ₹1,183 cr as on date |
| Net working capital days | 41 days (debtor days 69, creditor days 65, inventory days 37) |
| Current borrowings | ₹377 cr as on 30 Sep 2023, up from ₹107 cr on 31 Mar 2023 |
| Net unbilled revenue | ₹336 cr |
| Capex incurred | ₹79 cr in Q2; ₹97 cr in H1, of which ₹51 cr for precast facilities |