Key Takeaways
- Revenue surged, but monsoon masked the run-rate: Revenue grew 35% QoQ and 20% YoY, yet management says heavy monsoon through September cost ~Rs. 100 crores in lost revenue, without which EBITDA margin would have exceeded 7.5%.
- Adani Group now dominates the order book: Order inflow of Rs. 4,011 crores in Q2, mostly from Adani, pushed Adani's share of the outstanding order book to 56%. Mobilization across these projects has begun, setting up H2 for sustained execution.
- Working capital stretched, but relief is promised: Debtor days rose ~20 days as Q2 sales concentrated in September; management expects stabilization in Q3 as Adani Group advances flow in under favorable payment terms.
- Margin recovery is the core H2 bet: EBITDA margin of 6.93% was depressed by monsoon and fixed costs on lower sales; management targets 8%+ in H2 and eventual stabilization at 8-9% as project revenues ramp.
- What to watch next quarter: Whether the promised Q3 working capital stabilization materializes, the pace of margin recovery toward 8%, and any concrete progress on the Rs. 7,000 crores bid pipeline that must convert to hit the Rs. 11,000 crores FY26 order inflow target.
Order Book & Client Concentration
- Adani Group now 56% of the outstanding order book, up sharply after a quarter in which the majority of Rs. 4,011 crores in new orders came from Adani entities. The concentration is deliberate: management is prioritizing Adani Group projects and expects the relationship to drive order book toward Rs. 16,000 crores by March 2026.
- Q2 order wins were granular but Adani-heavy: Key additions included Navbharat Mahim (Rs. 1,303 crores), Skilled Workers' Accommodation Mundra (Rs. 813 crores), Tower C Shantigram precast (Rs. 406 crores), ACP Corporate House interior (Rs. 160 crores), and Leadership Guest House Shantigram (Rs. 90 crores), plus other miscellaneous orders.
- Disclosure policy changed without clear rationale: The company will now disclose orders only with quarterly results, not via separate exchange announcements. When pressed on why, management called it a "company policy decision" and noted it is not a SEBI requirement, deflecting the question about the change in practice.
- The Rs. 7,000 crores pipeline is the FY26 swing factor: With Rs. 4,000 crores already won, management expects to convert most of this pipeline to hit the Rs. 11,000 crores full-year inflow target. Whether these are competitively bid or negotiated Adani nominations remains unclear: management said "usually it is always a bid or sometimes depending on the situation... it can be negotiation also."
- FY27 revenue ambition rests on order book conversion: With an expected outstanding order book of Rs. 14,000-15,000 crores by March 2026, management is confident of exceeding Rs. 4,000 crores in FY27 revenue, implying 25%+ growth.
Prahaladbhai Patel: "You're absolutely right - with a large order book, we should ideally be able to deliver stronger performance. However, at present, many of our projects, especially in Mumbai, are facing delays due to the nature of work."
Margin Trajectory & Monsoon Impact
- Monsoon stole ~100 bps of margin in Q2: EBITDA margin came in at 6.93% (vs 6.72% YoY). Management stated that with an additional Rs. 100 crores of revenue lost to heavy monsoon, margin would have exceeded 7.5%, since fixed expenses remained unchanged despite lower sales.
- H2 margin target is 8%: Management called this "achievable" as revenue scales, with eventual stabilization at 8-9% once project revenues begin flowing from each site after foundation work completes. The path depends on execution volume absorbing fixed costs.
- Labor availability has normalized, removing a Q1 headwind: Q1 had a 37% labor deficit; from July onward labor was fully available, though heavy monsoon in Gujarat through August-September then became the binding constraint. Currently a ~10-12% Diwali-related shortfall exists, but full strength is expected for Q3.
- Precast capacity is a margin lever, but underutilized: Infrastructure is ready for five projects, but L&T orders end by February, freeing capacity. Only machinery CAPEX would be needed if new precast demand materializes, likely next financial year. Four Adani precast projects in Shantigram are starting soon, with one next month and three more by December.
Prahaladbhai Patel: "This quarter also if you see it is 7% and due to heavy monsoon, we could have made till about 100 crores more revenue and if that revenue could have been done we should have landed more than 7.5% but just because of heavy monsoon and continued monsoon till October you must have seen in Navratri also it was a monsoon in Ahmedabad."
Working Capital & Receivables
- Debtor days jumped ~20 days QoQ because the majority of Q2 sales were booked in September, post-mid-August, after monsoon and labor shortages eased. By October 17th, considerable amounts had already been received, suggesting the spike is timing-related rather than structural.
- Government client payments are stretched: Receivables from Sabarmati Riverfront, Dharoi, Naranpura Sports Complex, and Surat Metro Corporation are running slow, adding to the working capital burden.
- Adani payment terms are structurally favorable: Contracts carry 10% mobilization advance, with 75% of payments approved within seven days and the remaining 25% within 30 days. Management expects this to reduce debt levels and minimize working capital pressure.
- Q3 working capital stabilization is promised: Advances from the Adani Group are expected to normalize the working capital position in the third quarter.
- ECL provision is formula-driven, not project-specific: The Rs. 3.64 crores Q2 provision follows the Ind AS expected credit loss working formula and is linked to receivables aging beyond 60/90 days, not tied to any single troubled project.
- SDB recovery remains uncertain: SDB has agreed to pay with interest but requested more time as it struggles with office sales. Management called the timeline "very difficult to predict," noting the government is trying to stabilize SDB by bringing in gold, jewellery, and textile merchants.
Prahaladbhai Patel: "The conditions of contract, the way it is decided with Adani Group, it is 10% mobilization advance and most of the payments are being approved within seven days for 75% and maximum to 30 days for first 25% is approved. So probably this will help company a lot in terms of reducing the debt level and at the same time, minimize our working capital."
Project Execution & Bottlenecks
- Five projects completed in Q2: IIM Ahmedabad New Campus (multiple buildings), Mundra Solar Manufacturing precast, Astral House Phase-3, and an EPC precast building for Mundra Petrochem Limited.
- Ahmedabad Airport cluster work has geared up strongly, with reasonable work finishing at a faster pace. GIFT City projects are executing fine post-labor improvement and monsoon, working to revised schedules.
- SMC and RVNL projects are now running smoothly, with good execution and revenue expected in H2 as finishing and MEP activities ramp. The GBRC project is progressing steadily per plan.
- Dharoi Dam is near resolution: Only two land acquisition components remain pending, expected to be finalized by November 2025. Development work, paused during monsoon, has now resumed on the available work front.
- GMC road project remains on hold due to land acquisition issues and encroachment by shop owners, with no clear resolution timeline.
- Mumbai projects face inherent delays: Sheet piling and excavation take considerable time; Dharavi projects that began ~4 months ago have not yet started excavation, creating challenges at the substructure stage. This structural delay tempers the near-term revenue conversion from the Mumbai order book.
- World record pour demonstrates execution capability: The company completed a continuous concrete pour of 24,000 cubic meters in 54 hours for the Vishv Umiya Dham Temple foundation, generating Rs. 37 crores in Q2 revenue for work that would normally have taken three months.
Bid Pipeline & Optionality
- Commonwealth Games 2030 in Ahmedabad is a visible medium-term opportunity: designs are ready and the tender is expected after Diwali. Management intends to bid for "privileged projects" including Commonwealth, Stadium, and Temple projects (Somnath) in the Rs. 800-1,000+ crores range.
- Precast capacity creates optionality for FY27: With L&T orders ending by February and infrastructure ready for five projects, only machinery CAPEX would be needed to scale if new precast demand arises, likely next financial year.
- Bhiwandi arbitration is at the verge of hearing: If the government has funds and does not appeal further, the company should recover something, though timing and amount remain uncertain. Pandharpur arbitration is ongoing with no expectation of resolution this year.
- UP project is financially neutral: No significant cost was incurred in Q2; whatever was spent was matched by invoices raised. No further expenses are expected, so the project carries no future profitability drag.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Order book target | Rs. 16,000 crores total; Rs. 14,000-15,000 crores outstanding after H2 revenue of Rs. 2,000+ crores | March 2026 |
| Full-year FY26 revenue | ~Rs. 3,200 crores (per analyst math, confirmed by management) | FY26 |
| H2 FY26 EBITDA margin | 8% achievable | H2 FY26 |
| Steady-state EBITDA margin | Stabilize at 8% to 9% as project revenues ramp | Once revenue generation starts from each project |
| FY26 order inflow | Rs. 11,000 crores total; Rs. 4,000 crores won, Rs. 7,000 crores pipeline to convert | FY26 |
| FY27 revenue | Exceeding Rs. 4,000 crores (25%+ growth) | FY27 |
| Working capital | Stabilization expected from Adani Group advances | Q3 FY26 |
| Dharoi Dam land acquisition | Two pending components finalized | November 2025 |
| FY26 CAPEX | 3-4%, could cross to 4-4.5% due to high-value cranes for precast | FY26 |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue from operations | ₹694 cr, +20% YoY and +35% QoQ |
| H1 FY26 revenue | ₹1,206 cr, +1.38% YoY |
| EBITDA | ₹48 cr, +24% YoY |
| EBITDA margin | 6.93%, vs 6.72% in Q2 FY25; management targets 8-9% stabilization |
| Net profit | ₹15 cr, +33% YoY |
| Order inflow (Q2 FY26) | ₹4,011 cr (excluding GST), majorly from Adani Group |
| Order inflow (FY26 to date, till Oct 17) | ₹4,118 cr |
| Outstanding order book | ₹9,883 cr, +51% YoY; Adani projects 56%, non-Adani 44% |
| FY26 order inflow expectation | ~₹11,000 cr (per an analyst's math), management confirms bid book of ~₹8,500 cr plus ₹4,011 cr already received |
| FY26 revenue guidance | ~₹3,200 cr (per an analyst's math), management confirms H2 revenue of over ₹2,000 cr |
| FY27 revenue guidance | ₹4,000 cr+, more than 20% growth |
| Outstanding order book guidance (Mar 2026) | ₹14,000–15,000 cr, after potential order book reaches ~₹16,000 cr and H2 revenue of over ₹2,000 cr |
| Mobilization advance | ₹486 cr, entirely interest-free, largely from Adani Group |
| CAPEX (Q2 FY26) | ₹41 cr; H1 FY26: ₹80 cr; FY26 guidance: 3–4.5% of revenue |
| Net unbilled revenue | ₹603 cr |
| Working capital cycle | 102 days, up from 65 days last year, driven by higher receivable days from September-heavy billing |
| ECL provision (Q2 FY26) | ₹3.64 cr, vs ₹75 lakhs in Q2 FY25; accumulated ECL ~₹30 cr |
| Pending receivable from SDB | ₹90 cr, management expects payment once SDB stabilizes |