PSP Projects Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/x62pdonxpv4vapm0npckzq28.pdf

Key Takeaways


Order Book & Client Concentration

Prahaladbhai Patel: "You're absolutely right - with a large order book, we should ideally be able to deliver stronger performance. However, at present, many of our projects, especially in Mumbai, are facing delays due to the nature of work."

Margin Trajectory & Monsoon Impact

Prahaladbhai Patel: "This quarter also if you see it is 7% and due to heavy monsoon, we could have made till about 100 crores more revenue and if that revenue could have been done we should have landed more than 7.5% but just because of heavy monsoon and continued monsoon till October you must have seen in Navratri also it was a monsoon in Ahmedabad."

Working Capital & Receivables

Prahaladbhai Patel: "The conditions of contract, the way it is decided with Adani Group, it is 10% mobilization advance and most of the payments are being approved within seven days for 75% and maximum to 30 days for first 25% is approved. So probably this will help company a lot in terms of reducing the debt level and at the same time, minimize our working capital."

Project Execution & Bottlenecks


Bid Pipeline & Optionality


Guidance & Commitments

CommitmentSpecificsTimeline
Order book targetRs. 16,000 crores total; Rs. 14,000-15,000 crores outstanding after H2 revenue of Rs. 2,000+ croresMarch 2026
Full-year FY26 revenue~Rs. 3,200 crores (per analyst math, confirmed by management)FY26
H2 FY26 EBITDA margin8% achievableH2 FY26
Steady-state EBITDA marginStabilize at 8% to 9% as project revenues rampOnce revenue generation starts from each project
FY26 order inflowRs. 11,000 crores total; Rs. 4,000 crores won, Rs. 7,000 crores pipeline to convertFY26
FY27 revenueExceeding Rs. 4,000 crores (25%+ growth)FY27
Working capitalStabilization expected from Adani Group advancesQ3 FY26
Dharoi Dam land acquisitionTwo pending components finalizedNovember 2025
FY26 CAPEX3-4%, could cross to 4-4.5% due to high-value cranes for precastFY26

Key Metrics

MetricQ2 FY26
Revenue from operations₹694 cr, +20% YoY and +35% QoQ
H1 FY26 revenue₹1,206 cr, +1.38% YoY
EBITDA₹48 cr, +24% YoY
EBITDA margin6.93%, vs 6.72% in Q2 FY25; management targets 8-9% stabilization
Net profit₹15 cr, +33% YoY
Order inflow (Q2 FY26)₹4,011 cr (excluding GST), majorly from Adani Group
Order inflow (FY26 to date, till Oct 17)₹4,118 cr
Outstanding order book₹9,883 cr, +51% YoY; Adani projects 56%, non-Adani 44%
FY26 order inflow expectation~₹11,000 cr (per an analyst's math), management confirms bid book of ~₹8,500 cr plus ₹4,011 cr already received
FY26 revenue guidance~₹3,200 cr (per an analyst's math), management confirms H2 revenue of over ₹2,000 cr
FY27 revenue guidance₹4,000 cr+, more than 20% growth
Outstanding order book guidance (Mar 2026)₹14,000–15,000 cr, after potential order book reaches ~₹16,000 cr and H2 revenue of over ₹2,000 cr
Mobilization advance₹486 cr, entirely interest-free, largely from Adani Group
CAPEX (Q2 FY26)₹41 cr; H1 FY26: ₹80 cr; FY26 guidance: 3–4.5% of revenue
Net unbilled revenue₹603 cr
Working capital cycle102 days, up from 65 days last year, driven by higher receivable days from September-heavy billing
ECL provision (Q2 FY26)₹3.64 cr, vs ₹75 lakhs in Q2 FY25; accumulated ECL ~₹30 cr
Pending receivable from SDB₹90 cr, management expects payment once SDB stabilizes