Key Takeaways
- Revenue and margin miss, but the cause is mix, not loss of work: FY23 revenue grew only 10% against a 20–25% guide because over half the order book sat in early-stage construction where cost recognition outruns revenue booking, and no large project reached completion.
- The order book is at an all-time high: FY23 brought in ₹3,421 crore of new orders (90% growth YoY), and the company is now eligible to bid for single projects up to ₹2,500 crore.
- FY24 guidance is reaffirmed with a learning pledge: Management holds its ₹2,600 crore revenue and 11–13% EBITDA margin targets, stating it has learned from the miss and will only commit to what is achievable.
- Precast is emerging as a second engine: Captive precast revenue was ₹75–80 crore in FY23, but infrastructure demand is pulling the facility beyond its original building-and-warehousing purpose, and the board has approved an expansion.
- What to watch next quarter: Whether the UP medical college projects complete on schedule by October 2023, the pace of debtor-day normalization to 30–35 days, and any conversion from the ₹6,000 crore bid pipeline.
FY23 Performance: The Mix-Driven Miss
- Revenue growth fell short because more than 50% of the order book was at initial stages (core and shell, excavation, civil work) where cost incurred is higher relative to revenue booked, and no EPC or large projects were completed during the year.
- Q4 revenue reached ₹723–727 crore against a commitment of near ₹900 crore, with the UP project (₹1,600 crore, 7 projects, 14 sites) causing execution and management difficulties, compounded by inconsistent labour availability and delays in government approval of materials on lump-sum projects.
- EBITDA margin contracted from 14.67% in FY22 to 11.68% in FY23 because FY22 revenue included major projects (Surat Diamond Bourse, Kashi Vishwanath, Bombay Stock Exchange) at finishing stages with higher profit margins, while no such major projects completed in FY23.
- Employee expenses rose as headcount increased from 1,345 to 1,833, and finance costs increased due to higher utilisation of fund-based limits, rising interest rates, and issuance of bank guarantees for newly awarded projects.
- Cash flow from operations weakened compared to the previous year because of an increase in receivables, other assets (amount due from customers, retention money), and inventories, driven by starting roughly ₹3,000 crore of new orders during the year and high infrastructure expenses for new projects.
- Two slow-moving projects removed: Pandharpur and Bhiwandi, worth ₹727.31 crore, were taken out of the order book this quarter. On Pandharpur, the client accepted delay on their part and asked PSP to resume work, but PSP refused to restart until outstanding dues are received.
P. S. Patel: "During this year, more than 50% of our order book was at the initial stages of construction and none of the EPC or large projects were getting completed during the year which has largely led to lower-than-expected revenue growth and margin contraction during the quarter and full year."
Order Book & Bid Pipeline
- Highest ever order inflow: FY23 recorded ₹3,421 crore excluding GST, a 90% growth over FY22, and post-FY23 orders worth ₹758 crore have already been received.
- Bidding eligibility upgraded: The company can now bid for single projects up to ₹2,500 crore, and the virtual completion certificate for Surat Diamond Bourse enables qualification to bid for Central Vista projects.
- Bid pipeline stands at approximately ₹6,000 crore, split 67% private and roughly 20% from Gujarat; margins on this pipeline are expected to be in line with what the company has been doing until now.
- Key FY23 wins include a high-rise office building for Surat Municipal Corporation, a corporate office building for a leading MNC, three of the tallest residential projects in Ahmedabad and Gandhinagar, Ahmedabad Airport development, a repeat industrial order for Phase II and III of a noodle and chocolate factory by an MNC, an institutional campus in Ahmedabad, and a precast order for the National High-Speed Project from L&T.
- Gujarat Tourism project (L1, roughly ₹350 crore) has been converted into an order.
- High-rise residential inquiry is picking up because permission for 30-plus storey buildings in Gujarat was granted only last year, and PSP is the only player that has carried out work of 30 storeys plus in GIFT City.
- Central Vista: The company can bid for packages up to ₹2,500 crore but may not qualify for packages beyond ₹3,000 crore; margins are expected to be similar to the overall 11–13% guidance.
P. S. Patel: "See what has happened, the permission for 30 storeys plus up to 35 storey has been given in the state of Ahmedabad or in state of Gujarat last year only. So, any developer who wanting to go for a high-rise building of plus of 30 storeys, we are the only player that has carried out work of 30 storey plus in gift city."
UP Medical College Projects: The Execution Reset
- Seven projects, 14 sites worth ₹1,600 crore caused execution and management difficulties that drove the Q4 revenue miss, but the projects have been back on track for the last 8–9 months and the delay was only at the initial land handover stage.
- Structure of buildings is getting completed; MEP and interior work has started simultaneously in some projects, and execution is expected to ramp up during H1FY24.
- Completion timeline: Five projects expected by October 2023, Sultanpur by December 2023, and Sonbhadra by March 2024. Sultanpur and Sonbhadra are lagging because land possession for hospital buildings was given later than the other five projects.
- Revenue from delayed UP projects is expected to come in the first two quarters of FY24. All projects except the Sonbhadra hospital building will be completed in FY24; Sonbhadra may go beyond FY24 but not much revenue will be left.
Precast: From Captive to Growth Engine
- Captive precast revenue was ₹75–80 crore in FY23. The facility was originally created for buildings, industries, and warehousing, but demand is now coming from infrastructure (data ducts, electric ducts for the L&T bullet train, storm water drainage).
- Board approved expansion of the existing precast facility; ₹17 crore of a planned ₹45 crore capex has been booked this year, with the rest expected in the next few quarters.
- Order execution planned for FY24 is ₹200–250 crore, related to both infrastructure and building segments.
- L&T project delay of 45–60 days occurred because imported moulds, compulsory per the agreement with L&T, were delivered one month late; management expects to recover the delay by working 24 hours and foresees no problem at the end of the project.
- Market is picking up: discussions are ongoing for three or four more orders from Godwitt, and enquiries for storm water drainage ducts are coming in. Once a precast building in Ahmedabad is completed, more enquiries on the building side are expected.
Balance Sheet & Cash Flow
- Working capital increased in inventory, trade receivables, and trade payables, in line with increased sales in Q4 FY23 and increased order inflow during the last two quarters.
- Debtor days are expected to settle down at 30–35 days within 1–2 months.
- Finance cost in Q4 (₹9 crore) was lower than the previous quarter (₹10 crore) despite higher sales (₹730 crore vs ₹500 crore) because mobilization advances from major new customers reduced utilization of funding facilities. The run rate is expected to continue at the same level (₹9.2 crore).
- Long-term debt rose from ₹17 crore to ₹38 crore mainly due to precast addition and frames/editing equipment; no further long-term debt is expected.
- Credit facility: The lead bank has approved a further extension of ₹450 crore in credit limits; the company is in the process of signing and expects to receive it in one or two months.
- SDB performance bank guarantee of ₹80 crore is expected to be released in FY24 after the defect liability period ends in June 2024.
- FY24 capex excluding precast is expected in the range of ₹70–80 crore (3–4% range).
Disputes & Arbitration
- Pandharpur project: The client accepted delay on their part and asked PSP to resume work by investing further; PSP refused as a listed company acting as contractor, not investor. If the situation continues, PSP will go into arbitration.
- Bhiwandi project: A panel of arbitrators has been appointed and necessary documents provided. The claim is based purely on land issuance issues, not technical criteria, and PSP expects to recover all booked losses. The government is pushing for arbitration completion within one year.
P. S. Patel: "But as a listed company, we are not investors into the project but are contractors. We have refused to continue by putting in more money into the project."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY24 revenue | ₹2,600 crore (20–25% YoY growth) | FY24 |
| FY24 EBITDA margin | 11% to 13% | FY24 |
| FY24 order inflow target | ₹3,000 crore | FY24 |
| UP project completion | Five projects by Oct 2023; Sultanpur by Dec 2023; Sonbhadra by Mar 2024 | H2 FY24 |
| Debtor days normalization | Settle at 30–35 days | Within 1–2 months |
| Credit limit extension | ₹450 crore sanctioned, signing in process | 1–2 months |
| SDB performance BG release | ₹80 crore after defect liability period ends | June 2024 |
| Bhiwandi arbitration | Government pushing for completion | Within one year |
| Precast order execution | ₹200–250 crore | FY24 |
| Surat Municipal Corporation revenue | ₹300–350 crore | FY24 |
Key Metrics
| Metric | Q4 FY23 |
|---|---|
| Revenue from operations | ₹727 crore, +31% YoY |
| FY23 revenue | ₹1,927 crore, +10% YoY; below guidance of 20–25% |
| EBITDA | ₹78 crore, -12% YoY |
| EBITDA margin | 10.67%, vs 15.87% in Q4 FY22 |
| Net profit | ₹46 crore, -12% YoY |
| PAT margin | 6.3%, vs 9.4% in Q4 FY22 |
| FY23 EBITDA margin | 11.68%, vs 14.67% in FY22 |
| FY23 net profit | ₹133 crore, -17% YoY |
| FY24 revenue guidance | ₹2,600 crore, implying 20–25% YoY growth |
| FY24 EBITDA margin guidance | 11% to 13% |
| FY24 order inflow target | ₹3,000 crore |
| Order inflow FY23 | ₹3,421 crore excluding GST, +90% YoY |
| Outstanding order book | ₹5,052 crore as on FY23; grew 40% over FY22 excluding two slow-moving projects |
| Order inflow YTD post-FY23 | ₹758 crore |
| Bid pipeline | ~₹6,000 crore, 67% private, ~20% from Gujarat |
| UP projects revenue in Q4 | ₹301 crore from 7 projects |
| Cumulative UP projects revenue | ₹718 crore as on 31 March 2023 |
| Employee strength | 1,833, up from 1,345 as on 31 March 2023 |
| Total net working capital days | 41 days; debtor days 82, creditor days 70, inventory days 29 |
| Net unbilled revenue | ₹257 crore |
| Mobilisation advance | ₹245 crore |
| Total credit facility utilised | ₹897 crore out of ₹1,047 crore; further ₹450 crore enhancement approved |
| Precast captive work in FY23 | ₹75–80 crore |
| Precast order execution planned for FY24 | ₹200–250 crore |
| Bhiwandi project losses booked | ~₹9.5 crore |
| FY24 capex guidance | ₹70–80 crore, 3–4% of revenue, excluding precast |
| Precast capacity expansion capex | ₹45 crore planned; ₹17.7 crore CWIP already booked |