Key Takeaways
- A record year, but a weak finish: FY24 revenue grew 28% YoY to a record INR 2,462 crore, yet Q4 revenue fell 11% YoY as cost overruns on a large UP government project crushed margins.
- The UP project is the margin story: The INR 741 crore UP hospital project, with margins of ~5% per an analyst's math, single-handedly dragged FY24 EBITDA margin to 10.62%. With only INR 40-50 crore of revenue left, that drag largely ends in Q1 FY25.
- Guidance reset reflects scars, not just prudence: Management guided FY25 revenue growth of 15% and EBITDA margins of 10-11%, both below what the ex-UP business already delivers, citing higher overheads and a deliberately cautious view of execution pace.
- The balance sheet is healing: A QIP raised INR 244 crore, the Surat Diamond Bourse dispute was settled for INR 170 crore above certified value, and management expects to become a net cash company by end-FY25.
- What to watch next quarter: Whether the remaining UP project handover proceeds smoothly, the pace of SDB cash collection, and any sign that the bid pipeline of INR 5,746 crore converts fast enough to lift the 15% growth floor.
The UP Project: The Margin Drag That Explains Everything
- A dispersed, speed-driven project: The UP project was spread across 14 hospital sites, requiring heavy infrastructure build-out and fast execution. MEP materials delivered after March 2021 were hit by post-Covid cost increases, and the maximum margin impact landed in the last two quarters as projects neared completion.
- Margin erosion quantified: Initial margin estimates were 10-11%, but overall impact was 4-5% due to cost overruns. Management insists no loss was made, but overall margin went down materially. The remaining impact at completion will not be major.
- Ex-UP, the business looks healthier: Excluding the UP project, FY24 margins were ~13.5% per an analyst's math. The remaining UP revenue of INR 40-50 crore will only affect Q1 FY25, after which the drag disappears.
- Three hospitals remain: Three hospitals are to be handed over by June end, closing out the project.
P. S. Patel: "Of course, the tendering process will still remain on the range of 12% and 13%. But the guideline has to be a little bit lower side. That's the reason I am saying. And that's what we have experienced in the last few years. Little bit of crisis."
Order Book & Bid Pipeline
- Record order book, but low coverage: Outstanding order book reached a highest-ever INR 6,049 crore, up 20% YoY, with record order inflow of INR 3,498 crore. However, the order book is only ~2x revenue, versus peers at 3-4x, which management cites as a structural limit on near-term growth pace.
- Bid pipeline disclosed at INR 5,746 crore: 16 named projects are in the pipeline, including a INR 2,000 crore commercial project in Noida and AIIMS New Delhi at INR 445 crore. Management expects FY25 order inflow of nearly INR 3,500 crore.
- Government mix has swung sharply: Government share in the order book has risen to ~70% from a historical 85% private, because private investment is lower and the company is not working on the developer side. Margins are not inherently dependent on client type, management says, because private projects carry different cost requirements.
- Large-ticket ambition, with a caveat: The company is confident to gradually move up the value chain to larger projects, but strict timelines of up to 30 months on large jobs can extend overheads and reduce profit, offsetting the benefit of higher monthly revenue.
Margins: Why the Recovery Is Guided Below Potential
- Overhead costs have structurally risen: Staff and labour cost increases have pushed overheads from 3.5-4% to 5%, which is the primary reason FY25 EBITDA margin is guided at 10-11% even though the UP drag ends. Tendering still targets 12-13%, but guidance is set lower based on recent experience.
- Recency bias acknowledged: When an analyst asked whether the cautious margin guidance reflected recency bias, management replied, "Yes, you can say that."
- Q4 margin breakdown: Q4FY24 EBITDA margin fell to 7.98% from 10.67% YoY, driven by higher employee benefit expenses and other expenses. PAT margin fell to 2.3% from 6.3%, with additional pressure from higher finance costs on increased borrowings and depreciation from additional capex.
- Precast: a margin tailwind, but unproven: Precast revenue was ~INR 200 crore in FY24. Management sees 14-15% margins possible in future as the technology gains acceptance and industrial inquiries grow, but the business is still in an investment phase and margins are not separately disclosed.
Balance Sheet & Cash Flow Repair
- QIP completed: In April 2024, the company raised INR 244 crore via QIP, placed with marquee domestic mutual funds and FIIs. INR 188 crore of debt has already been repaid.
- SDB settlement removes an overhang: An out-of-court settlement was reached on May 15, 2024, with Surat Diamond Bourse. SDB agreed to pay INR 170 crore over and above INR 1,790 crore already certified, bringing total approved project value to INR 1,960 crore excluding GST. The resolution also clears the way to bid for Gem and Jewellery Export Promotion Council projects.
- SDB cash inflow timeline: 50% of the due payment is expected within 30 days, with the balance in quarterly tranches, maximum within FY25.
- Net cash target: With INR 250 crore of combined cash inflow from SDB and UP projects, management expects to become a net cash company by end-FY25.
- Negative operating cash flow in FY24: Operating cash flow was negative INR 226 crore, driven by increased inventories, a rise in unbilled revenue from INR 257 crore to INR 442 crore, and a decrease in mobilization advances from INR 245 crore to INR 135 crore.
P. S. Patel: "That is an individual call wherein the overall we have claimed, we have received INR103 crores out of which we were expecting INR100 crores more. But as we wanted to get out of this issue because that was giving a bad impression to the company also."
Revenue Growth: A Calculated 15% Floor
- 15% is a minimum, not a forecast: Management calls the 15% revenue growth guidance a "calculated decision" based on two years of experience where execution pace is not 100% due to multiple factors. If significant order inflow arrives in the first two quarters, growth can exceed 15%; if orders land in the last two quarters, the scenario is different.
- The 2x order book constraint: Management explicitly ties faster growth to order book coverage: if order inflow improves to 2-3x revenue, growth of 20-25% becomes possible. The current ~2x coverage caps near-term execution pace.
- Execution uncertainties remain: Management declined to confirm higher execution in FY26, saying projections about execution are not 100% possible due to uncertainties, and that the key variable is whether the order book multiples expand.
- Key projects in early stages: Newly awarded major projects including the SMC High Rise Building, Sabarmati Riverfront, Dharoi dam development, Gati Shakti University, and a Fintech building at GIFT City are in initial construction phases, contributing only marginally to Q4FY24 revenue.
P. S. Patel: "I can't say it's conservative, but it's a calculated decision that I've made over the past two years where the execution pace is not 100% of the company because there are many other factors that affect our growth."
Precast & Other Business Developments
- Precast gaining traction: Demand is coming from Nestle, Tata, and Coca-Cola. Three warehouses were completed this quarter, and 12 lakh sq ft of warehousing has been completed in total. The company recently received a precast order from Adani and is bidding for a INR 150 crore purely precast project from the same client.
- Precast growth ambition: Management sees precast revenue growing from INR 200 crore to INR 250-300 crore and potentially INR 400 crore over the next three years, with 25-30% minimum YoY growth. The technology helps address labour shortages and seasonal issues.
- SMC Surat project progressing: The four-basement project has reached the first floor; once the podium is reached, the RCC structure can be completed this year, with total completion expected within 36 months.
- Arbitration updates: Bhiwandi arbitration is in cross-examination, with final conclusion expected in 2-3 months. Pandharpur arbitration cross-examination is yet to start, with conclusion likely ~6 months from now.
- Kashi Vishwanath Dham payment: Expected to move in the next two months, post-election.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | Minimum 15% YoY; can be revised upward if significant orders arrive in first two quarters | FY25 |
| EBITDA margin | 10-11% range | FY25 |
| Order inflow | Nearly INR 3,500 crore | FY25 |
| UP project handover | Three remaining hospitals handed over | By June end 2024 |
| SDB cash receipt | 50% of due payment within 30 days; balance in quarterly tranches | Max within FY25 |
| Net cash company | Achieved provided receipt of INR 50-80 cr from UP and INR 225 cr from SDB | By end-FY25 |
| SMC Surat project completion | RCC structure this year; total completion within 36 months | ~FY27 |
| Bhiwandi arbitration conclusion | Final conclusion after cross-examination completes | 2-3 months |
| Pandharpur arbitration conclusion | Cross-examination yet to start | ~6 months |
Key Metrics
| Metric | Q4 FY24 |
|---|---|
| Revenue | ₹649 cr, -11% YoY |
| EBITDA | ₹52 cr, -33% YoY |
| EBITDA margin | 7.98%, vs 10.67% in Q4 FY23; impacted by higher employee and other expenses |
| Net profit | ₹15 cr, -67% YoY |
| PAT margin | 2.3%, vs 6.3% in Q4 FY23 |
| FY24 revenue | ₹2,462 cr, +28% YoY |
| FY24 EBITDA margin | 10.62%, vs 11.68% in FY23; UP projects impacted margins |
| FY24 net profit | ₹124 cr, -7% YoY |
| Order book | ₹6,049 cr, +20% YoY, highest ever |
| FY24 order inflow | ₹3,498 cr (excluding GST), highest ever |
| FY25 order inflow guidance | ~₹3,500 cr |
| FY25 revenue growth guidance | Minimum 15% |
| UP projects cumulative revenue | ₹1,459 cr till Mar 31, 2024; ₹741 cr booked in FY24 |
| UP projects pending revenue | ₹40-50 cr remaining |
| SDB settlement additional amount | ₹170 cr over and above ₹1,790 cr certified; total approved project value ₹1,960 cr excluding GST |
| SDB pending revenue to be booked | ₹64 cr upon receipt of certificate |
| Net working capital days | 35 days (debtor days 50, creditor days 62, inventory days 47) |
| Net unbilled revenue | ₹442 cr |
| Precast revenue FY24 | ~₹200 cr |