Key Takeaways
- Guidance reset, not a miss: FY26 revenue met and exceeded the target, but FY27 EBITDA margin guidance of 7–8% sits below earlier 8–8.5% aspirations, with management calling it conservatism rather than a downgrade.
- The order book is the story: FY26 saw the highest ever order inflow of INR10,925 crores, 85% from the Adani Group, pushing the executable order book to a level that makes the INR4,500 crores FY27 revenue target look well-supported.
- One provision distorts the margin picture: A INR29 crores expected credit loss provision on unbilled Kashi project revenue pulled reported EBITDA margin to 6%; without it, Q4 ran at roughly 8%, consistent with the guided range.
- Debt-free within sight: Management expects the company to be debt-free this year or within two quarters, which would convert INR41–45 crores of annual interest into profit and lift PAT margins toward 3–4%.
- What to watch next quarter: Whether the INR60 crores of unbilled revenue on the UP Medical College project triggers another provision, and whether the promised Commonwealth Stadium tender finally drops.
Order Book & Revenue Visibility
- Inflow dominated by a single relationship: INR10,925 crores of FY26 orders, with 85% from Adani Group projects, creates both the revenue runway and a concentration risk that the company is trying to offset with external tenders.
- External pipeline exists but is smaller: Management sees a possible INR1,000–2,000 crores from outside the group if Commonwealth Games and other Gujarat government tenders materialize, against a total bid pipeline of INR6,500 crores (INR5,000 crores group, INR1,500 crores outside).
- Execution timeline supports the guidance: The large-volume order book is structured to run off over 2.5 to 3 years, and by Q3 FY27 all projects except Matunga (still in sheet piling) should be contributing to revenue.
- Revenue growth target of 20–25% for the next couple of years is framed as a floor, with management stating "visibility is not a problem" and that the constraint is now execution capacity, not deal flow.
P.S. Patel: "100% because that is the minimum which we are targeting because now visibility is not a problem. Strengthening ourselves to a larger extent in terms of executing large projects and building company to a larger extent in terms of execution, visibility is not a problem, so we can easily go to that level."
Margins: The Provision & The Promise
- Q4 margin optically weak, operationally fine: EBITDA margin fell to 6% from 7.14% a year ago, but the INR29 crores Kashi provision alone accounts for the entire miss; stripping it out puts the quarter at roughly 8%, in line with the guided range.
- FY27 guidance of 7–8% is deliberately conservative: Management pushed back on the idea of a downgrade, saying "I am not lowering, I'm keeping myself a little bit conservative" and noting the margin can move "1% plus or minus" around that band.
- Interest-cost tailwind is material: The company currently carries INR41–45 crores in annual interest; becoming debt-free, expected this year or within two quarters once Naranpura Sports Complex and UP receivables land, would drop that straight to PAT.
- No further major provisions expected beyond the two known problem accounts (Kashi and UP Medical College), though management stopped short of a firm commitment on UP, where INR60 crores of unbilled revenue sits exposed.
P.S. Patel: "I am not lowering, I'm keeping myself a little bit conservative because if you see this quarter also if you find this provision of INR30 crores then it is at 8%. So it can go up 1% plus or minus."
Problem Receivables: Kashi & UP Medical College
- Kashi project provision taken, chase continues: INR29 crores provided because accounting rules require provisioning any receivable beyond one year; the counterparty is a religious organization and the company is still pursuing recovery through relationships.
- UP Medical College is the larger exposure: Projects are handed over and the defect liability period has passed for some, but the account remains unsettled due to procedural extensions from an existing hospital renovation; INR60 crores sits as unbilled revenue with no provision yet taken.
- Management is optimistic but cannot guarantee: On UP, the company is "chasing at the government level" and expects closure "any point of time in the near future hopefully the coming quarter only," but when pressed on whether a provision would be needed, the answer was "let us hope that we get that money."
- SDB money also outstanding: INR90 crores in receivables from a counterparty that started operations only last month; the company has been chasing with bills and interest and expects "something should happen in next year."
P.S. Patel: "For you its financial figure but for us as a company its our money."
Balance Sheet & Working Capital
- Trade receivables spike is seasonal, not structural: The majority of Q4 revenue was booked in February and March, so the 31 March balance sheet shows elevated receivables that will be collected in April.
- Working capital days guided to stay within 60 going forward, with trade receivable days maintained around 60–70; group orders come with favorable payment terms including ad hoc advances against bills submitted.
- Debt-free target tied to two specific receipts: Management expects the company to be debt-free "by this year or maybe in next two quarters once we receive all the payments and even the receivables from like Naranpura Sports Complex and UP," with quarterly interest of INR11–12 crores dropping to zero from Q3 or Q4 onwards.
- Capex moderating: FY26 capex ran above 3% of revenue because most was for projects now entering execution; FY27 is expected at roughly 2% of revenue, or INR120–150 crores, with depreciation of INR30–35 crores.
Execution & Precast Capability
- Project 90 as a proof point: A precast residential building (three basements plus ground plus 18 upper floors) was completed in 148 days, under five months, demonstrating the speed the precast technology can deliver.
- Precast plant utilization is healthy: Current capacity of 0.3 crore sq ft per year is absorbed by the 120-metre building already completed plus three more orders in execution from Adani and GIFT City airport; no major expansion is needed currently.
- Monsoon risk reduced: Most projects are now out of the foundation stage, so the seasonal weather disruption that typically hits construction should be less of a factor going forward.
- Matunga is the one laggard: The project remains in the sheet piling phase and is the only major job in the order book not yet contributing to revenue, though it is expected to join the revenue stream later.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue | INR4,500 crores | FY27 |
| EBITDA margin | 7% to 8% (can move 1% plus or minus) | FY27 |
| Debt-free | Zero debt, interest cost drops to nil | This year or within two quarters |
| Working capital days | Within 60 days | Going forward |
| Capex | ~2% of revenue (INR120–150 crores) | FY27 |
| Depreciation | INR30–35 crores | FY27 |
| Revenue growth | 20–25% | Next couple of years |
| UP Medical College settlement | Account closure expected | Coming quarter |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue from operations | ₹1,115 cr, +66% YoY |
| EBITDA | ₹60 cr, +85% YoY |
| EBITDA margin | 5.36%, vs 4.81% YoY; includes ₹29 cr ECL provision for Kashi project |
| PAT | ₹21 cr, +244% YoY |
| PAT margin | 1.88%, vs 0.93% YoY |
| Full-year FY26 revenue | ₹3,149 cr, +25% YoY |
| Full-year FY26 EBITDA margin | 6.0%, vs 7.14% YoY |
| Full-year FY26 PAT | ₹55 cr, -2% YoY |
| FY27 revenue guidance | ~₹4,500 cr, management maintained |
| FY27 EBITDA margin guidance | 7% to 8%, management expects improvement |
| Order book (outstanding) | ₹13,447 cr, +85% YoY; 67% group, 33% external |
| Order inflow in FY26 | ₹10,925 cr, highest ever; 85% from Adani Group |
| Order inflow in Q4 FY26 | ~₹6,000 cr |
| Bid book | ₹6,600 cr+, 60% group, 40% external |
| Trade receivables | ₹928 cr, up from ₹530 cr in FY25; spike from Feb–Mar billings |
| Net unbilled revenue | ₹440 cr |
| Mobilization advance | ₹814 cr, all interest-free |
| Gross debt | ₹317 cr (long-term ₹43 cr + short-term ₹274 cr); management expects to be debt-free in FY27 |
| Capex in FY26 | ₹192 cr (year-to-date); Q4 ₹40 cr |
| Working capital days | 94 days currently; expected within 60 days going forward |
| Provision for expected credit loss (Kashi project) | ₹29 cr, one-off provision on unbilled revenue |
| UP Medical College exposure | ₹60 cr unbilled + ₹40 cr receivables; final certification awaited |
| SDB receivable | ₹90 cr, operations started last month; recovery expected in FY27 |