Quadrant Future Tek Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/7g8yuankqpfwcuapixy47s4i.pdf

Key Takeaways


The Kavach Approval Sequence

Vohra: "It is certainly not a long or a defined process... most of the tests are very intact. Most of the software or codes related to that are very-very intact. So, it should go very smoothly and very fine, you will see."

The December 2025 Delivery Challenge

Vohra: "So, if it happens, then it will take us to a new sphere. So, this is the challenge and we are relishing this challenge because this is basically a kind of, I should say, hard work or maybe that much of the room is required to enter into that level."

Kavach Order Book & Revenue Outlook


Cable Division: The Legacy Business Reboot


Financial Snapshot


Guidance & Commitments

CommitmentSpecificsTimeline
Kavach order executionDeliver 1,200 locomotive kits under purchase order awarded Dec 12, 2024By Dec 11, 2025
Kavach certificationReceive ISA certification and field trial clearanceExpected August-end 2025, leaving ~3 months for supply
Kavach field trial startLocomotive issued for formal field trialsIn 1-2 days from the call date
Trackside order supplySupply Rs. 155 crores trackside Kavach order won via RailTelWithin this calendar year
Kavach margins disclosureVisibility on Kavach margins to become clearNext quarter
Cable division growthEnter solar, EV and export markets under new CEOYear-on-year; revival described as happening now

Key Metrics

MetricQ1 FY26
Operational revenue₹28.7 cr, +12% YoY
EBITDA margin8.9%, compared to 7.3% in Q1 FY25
Revenue from Speciality Cable Division100% of total revenue
Kavach Division revenueNil, pending rollout clearance
Segment loss, Train Signalling/Kavach Division₹10.09 cr, increased from ₹4.24 cr in Q1 FY25
Total order book, Kavach Division₹984 cr (₹829 cr locomotives + ₹155 cr trackside)
Order book, Cable Division~₹40 cr
Kavach raw material inventory₹52 cr total (₹16 cr under purchases, ₹36 cr work in progress)
Kavach installation capacity300 locomotives per month
Kavach installation time per locomotive1 day
Kavach commissioning test durationNot more than half an hour
Field trial distance requirement5,000 kilometres
Installation teams ready15 teams
Quadrant content share in dense station orders75%–80%