Key Takeaways
- H1 delivers on the growth promise: Revenue surged 31% YoY, driven by a 40% jump in the integrated control systems vertical and a seven-fold aerospace ramp-up, putting the company on track for its full-year target.
- Margins benefit from operating leverage: EBITDA margin improved to 18.71% as costs grew more slowly than revenue; management expects H2 margins to hold at similar levels.
- A new facility unlocks the next leg: A 41,000 sq ft integrated plant is commissioning on schedule, set to eliminate over Rs. 2 crores in annual rent and consolidate backward integration under one roof.
- Aerospace is small but accelerating fast: Revenue from a key existing OEM customer hit Rs. 1 crore in H1, up from Rs. 0.14 crore a year ago, with two new tier-1 customers in active onboarding.
- What to watch next quarter: Whether Siemens switchgear cabinet production begins as guided, any early order flow from the newly onboarded GE Vernova relationship, and the pace of relocation into the new facility.
Growth Drivers: What Fired in H1
- Integrated control systems led the charge: This vertical, serving a major automation OEM with high-volume panels, was the primary reason for H1 growth and delivered a 40% YoY revenue surge.
- Aerospace hit serial production: Revenue from a key existing aviation customer jumped seven-fold as the relationship moved from qualification to repeat orders, with the OEM relying on the company's enhanced quality processes.
- EV order book is intact and executing: The 5-year Mahindra EV order continues as planned, with roughly Rs. 230 crores of remaining value spread over the next four years.
- Energy sector still absent: The anticipated pickup from energy-sector customers has not yet materialized; management describes it as an ongoing process with no timeline.
Aniket Latkar: "We are seeing growth with the key existing aviation customer where we've clocked a revenue of over Rs. 1 crore in the first half of FY'26 as compared to Rs. 0.14 crores in the H1 of FY'25. This is nearly a seven-fold increase in a single half year, which underscores the successful ramp up of serial production and the growing trust from OEM customer who are increasingly relying on our enhanced quality processes."
The New Facility & Capacity Build-Out
- Phase 1 is commissioning now: The 41,000 sq ft integrated manufacturing facility is on schedule; relocation is underway and will bring major operations under one roof, improving throughput and operational leverage.
- Rental cost elimination: Exiting legacy rented premises will save over Rs. 2 crores in annual rental costs, a direct drop to the bottom line once the transition is complete.
- Phase 2 targets high-volume contracts: A second phase of expansion, designed for long-cycle contracts in panels, HLA and aviation, is scheduled for completion by March 2026.
- Consolidation plus automation: The intent is to consolidate all three existing facilities, including the labor-intensive backward-integration unit, at one location and layer in automation to improve integration and efficiency.
- Management bandwidth reallocated: Operations will be hived off under a separate team, freeing Aniket Latkar to focus on aerospace customer acquisition and the radiator business opportunity.
- CAPEX cycle nearing its end: Only around Rs. 5 crores remains to complete the new facility; any future investment will be funded from cash flows, not additional debt.
Aniket Latkar: "The relocation is underway. The transition of the new 41,000 square feet integrated facility is on schedule, bringing some of our major operations under one roof will unlock significant operational leverage, improve our throughput and crucially also eliminate over Rs. 2 crores of our annual rental costs as we are exiting out of our rental legacy premises."
Aerospace: The Emerging Third Leg
- From qualification to production: The company obtained AS9100 certification two years ago and spent last year on customer qualifications; H1 FY26 marks the first meaningful serial production revenue from that effort.
- Existing customer runway is long: The seven-fold growth with the current aviation OEM is expected to sustain at a similar revenue uptick for at least the next couple of years, given the ramp-up trajectory.
- Two new tier-1 customers in pipeline: Initial audits are successfully completed and the bid process is ongoing; both prospects have confirmed the company's infrastructure and QMS meet global aerospace supply chain standards.
- NADCAP certification initiated: A special-process aerospace certification has been added to the quality roadmap, though management notes it will take time to complete.
- 20% revenue ambition: Management's plan is to scale aerospace to roughly 20% of the existing revenue cycle within the next couple of years, not five.
- Margins above corporate average: Aerospace EBITDA margins are expected to exceed 20%, comfortably above the company's blended margin profile.
Aniket Latkar: "I would present it as being more of value-added processes, kind of a labor activity in terms of the topline. I don't see that it will be a big jump. However, the plan is to take this close to around 20% odd of our existing revenue cycle."
Customer & Segment Updates
- GE Vernova onboarded: The company has successfully made it onto the approved vendor list for GE Vernova's new factory located nearby; however, management does not expect any orders for at least another six months.
- Siemens qualification progressing: Product qualifications for electrical switchgear cabinets are underway, with production expected to begin by next quarter.
- Railways remains a steady ~25% contributor: Revenue continues through a JV partner on the diesel locomotive side; the company is now in the quotation process to bid for EV locomotive business with a different customer.
- Defense is a small slice: Per management, defense accounts for roughly 5% of the total order book.
- Order book visibility is deliberately short: Most customers operate on OEM long-term contracts with only three-month visibility; order inflow arrives quarterly, so management declined to provide a one-year backlog figure.
Margins, Costs & Balance Sheet
- Operating leverage drove the margin lift: EBITDA margin reached 18.71% in H1 as employee costs and other expenses declined as a percentage of revenue, even while revenue grew 31%.
- H2 margin outlook is stable, not expanding: Management expects H2 margins to remain similar to H1; depreciation from the new facility will begin to weigh from next financial year, capping further improvement.
- Debt rose to fund construction: Long-term borrowings increased because new term loans were disbursed for constructing the first floor of the newly acquired facility.
- Inventory built to support revenue: The increase in inventory is directly linked to the revenue ramp-up and is intended to cater to higher volumes.
- Radiator business margin profile: The emerging radiator business, targeting data-center power generation requirements, is expected to deliver margins close to 20%.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Full-year revenue | Close to Rs. 140 crores | FY26 |
| H2 vs H1 growth | ~15% growth over H1, in line with typical seasonal pattern | H2 FY26 |
| H2 EBITDA margin | Similar to H1 levels | H2 FY26 |
| Phase 2 facility completion | Construction complete, production orders begin as add-on revenue | By February 2027 |
| Siemens switchgear production | Enter production for qualified electrical switchgear cabinets | Next quarter (Q3 FY26) |
| GE Vernova first orders | No orders expected for at least six months | Not before H2 FY26 |
| Aerospace revenue trajectory | Seven-fold growth pace sustained with existing customer | At least next couple of years |
| Aerospace revenue share | Scale to ~20% of existing revenue cycle | Next couple of years |
| Revenue milestone | Cross Rs. 200 crore mark | Next couple of years |
| Asset revenue potential | Rs. 500 crore revenue realization target from ~Rs. 150 crore gross block | Long-term (no date) |
| Remaining CAPEX | ~Rs. 5 crores, final leg of current cycle; future CAPEX from cash flows | Near-term completion |
| Mahindra EV order remaining value | ~Rs. 230 crores | Over next 4 years |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue from operations (H1 FY26) | ₹58.31 cr, +31% YoY (H1 FY25) and +22% vs H2 FY25 |
| Integrated control systems revenue share | ~57–58% of total revenue |
| Engineered metal assembly revenue share | ~37% of total revenue |
| EBITDA margin (H1 FY26) | 18.71%, improved from prior periods; cost controls offset revenue growth |
| Net profit (H1 FY26) | ₹6.63 cr |
| Total assets | ₹147.63 cr |
| CAPEX invested (H1 FY26) | ~₹15 cr |
| Capital work in progress | ₹9.4 cr |
| Cash and cash equivalents | ₹1.59 cr, declined from ₹3.26 cr due to CAPEX and working capital |
| Current-quarter order book | ~₹50 cr |
| Mahindra EV order executed (Feb '24–Sep '25) | ~₹10 cr |
| Mahindra EV order pending | ~₹230 cr, to be executed over the next 4 years |
| Aerospace revenue (H1 FY26, key customer) | Over ₹1 cr, nearly 7x vs ₹0.14 cr in H1 FY25 |
| Railways revenue share | ~25% of total revenues |
| New integrated facility size | 41,000 sq ft |
| Annual rental cost elimination from new facility | Over ₹2 cr |
| H2 vs H1 revenue growth trend | ~15% growth expected |
| FY26 revenue guidance | Close to ₹140 cr |
| Future CAPEX for facility completion | ~₹5 cr, last leg of CAPEX cycle |
| Gross block | ₹147.63 cr |
| Revenue potential from current gross block | ~₹500 cr (per management target) |
| Aerospace revenue target | ~20% of existing revenue cycle, within next couple of years |