Key Takeaways
- Volume-led H1, margin recovery promised: Sales volume grew ~17% in H1, but OPM fell QoQ on lower steel prices and plant repairs. Management expects H2 margins to improve as repairs end and prices recover from late November.
- Inventory liquidation is the working-capital engine: Aggressive scrap, by-product and defective sales lifted blended realization and cut borrowings by over Rs.3,000 crores, a strategy that will continue through H2.
- Coal cost headwind is building: Imported coal prices rose from Rs.16,600 in August to Rs.17,400 now and are expected to reach Rs.18,000–18,100 in Q3, partly offsetting the price recovery.
- Expansion capex cycle is starting: IISCO's 0.45 crore ton expansion at ~Rs.36,000 crores has major packages tendered, and FY27 capex is targeted above Rs.10,000 crores, funded 50:50 by debt and internal accrual.
- What to watch next quarter: Whether the promised November price recovery materializes, the pace of inventory liquidation, and the Q3 margin trajectory against rising coal costs.
Volume & Realization
- Sales volume drove H1: 0.95 crore tons sold, up ~17%, supported by an aggressive sales strategy and inventory reduction that also cut borrowings.
- Realization held up despite price drops: Blended realization improved QoQ even as steel prices fell, because higher sales of by-products, scrap items and defectives lifted the mix.
- Production dip now resolved: Crude steel and hot mill output fell in Q2 due to Bokaro steel melting shop issues, which were resolved just days before the call. All capital repairs across plants are now complete.
- H2 volume outlook: Production will increase in Q3 and Q4, and sales volume growth will exceed production growth to draw down sellable steel inventory, with a target to liquidate at least 50% of that inventory during FY26-27.
Margin Walk & Cost Drivers
- QoQ OPM decline: The reduction between Q1 and Q2 came from two factors: lower sales prices, and capital repairs plus Bokaro steel melting shop issues. Both are now behind the company.
- Coal cost rising: Imported coal moved from Rs.16,600 in August to Rs.17,300 in October, driven by rupee depreciation. The coal index is range-bound but edged from 187 to 194.
- H2 margin recovery path: Margins are expected to improve on three levers: steel price improvement balancing coal cost increases, cost reduction from completed capital repairs, and improved blast furnace operations.
Panda: "in Quarter 3, Quarter 4, we will have better cost reduction. So, that will add to our profitability."
- Scrap & by-product EBITDA contribution: Of the ~Rs.300 crores QoQ increase in scrap and by-product realization, at least 20–25% flowed into EBITDA and PBT. The differential between sales price and stock valuation rate directly aids profitability, while lower borrowings reduce interest cost.
- Q4 EBITDA margin target: Management expects Q4 EBITDA margin to move toward 14–15%, while Q3 may stay flat or improve slightly depending on market behavior.
Inventory & Working Capital
- Inventory composition: Finished steel inventory at 0.19 crore tons; in-process stock reduced sharply from 0.13 to 0.07 crore tons; total steel inventory flat at 0.27 crore tons.
- Scrap auction strategy: The company is running frequent auctions for by-products, steel defectives and scrap items to liquidate stock and release cash flow. This will continue in subsequent quarters.
- Scrap & by-product sales scale: Q2 scrap and by-product sales reached Rs.1,140 crores, covering defectives, rejected material, iron and steel scrap, crude tar, slag and other waste. These sales are expected to go higher in Q3 and Q4.
- Borrowing reduction: Borrowings fell by Rs.3,384 crores as of 30th September versus the same period last year, and the momentum of reduction will continue through Q3 and Q4.
Pricing & Demand Outlook
- Near-term price pressure: Steel prices declined in Q2 versus Q1, but management expects improvement from mid-to-end November, similar to last year when December and the entire Q4 saw a pickup.
- Demand recovery bet: Indian economic pickup and demand increase are expected in the later part of Q3 and Q4, which would relieve pricing pressure.
Panda: "Even if there are pressures on the price front right now, but I believe from November middle or end of November, things would improve and prices would improve."
- Rail pricing mechanism: Rail prices are finalized up to FY23-24, with FY24-25 under process. Provisional prices are set by a joint pricing committee of SAIL and Railways, and revenue is recognized per IndAS 115 at those provisional prices aligned with market. Upon finalization, arrears are booked and the provisional price resets.
- Provisional pricing book: The cumulative provisional price of Rs.13,800 crores includes rail and defense items sold to government. Quarterly and half-yearly numbers vary slightly based on concurrent debit and credit advices.
Expansion & Capex
- IISCO expansion: Major packages for the 0.45 crore ton expansion at ~Rs.36,000 crores have been tendered and the majority finalized. Order placement has begun in certain cases, with balance major packages to be completed in one or two months. Design engineering will follow, then physical supplies and ground activities.
- Debottlenecking underway: Orders for the Durgapur rebar mill were placed last year with ground activities started; the Durgapur blast furnace is also finalizing orders. Tendering is ongoing across all plant units.
- Capex trajectory: FY26 target is in excess of Rs.7,500 crores; FY27 target is in excess of Rs.10,000 crores; after FY27, capex will rise still further.
- Funding mix: Management is targeting a 50:50 split between debt and internal accrual for expansion funding.
- Volume growth FY27: Targeting 5–7% growth over FY26 through the de-bottlenecking process.
Balance Sheet & Raw Materials
- Debt headroom strategy: The company is reducing its non-IndAS debt-equity ratio to 0.3–0.35 or perhaps 0.4 by year-end, creating headroom for borrowings to fund expansion projects over the next four to five years.
Panda: "we are creating a headroom for having more borrowings to fund our expansion projects going forward. So, expansion projects are outlined for the next four, five years in a bigger way."
- Iron ore developments: The Rowghat mine is opening up; once production picks up, sales from the Chhattisgarh group can be considered. Jharkhand dump fines dispatches to sister plants have increased significantly, and an auction for one million tons of dump fines from Jharkhand Group of Mines was recently put up.
- NMDC volumes: Q2 NMDC volume was 3 lakh tons, valued at Rs.1,500 crores. The full-year iron ore volume target of 1.85 crore tons from NMDC remains intact.
- Coal cost outlook: Imported coal prices are expected to remain higher, moving toward Rs.18,000–18,100 in Q3; Q4 remains to be seen.
Panda: "Today, it is around Rs.17,400, it may go towards Rs.18,000, Rs.18,100, something like that in Q3 I expect. In Q4, we will see how it continues."
- Value-added product share: Targeting more than 60% going forward.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Steel price recovery | Prices to improve from mid-to-end November, similar to last year's pattern | Mid-to-end November |
| Sales volume growth | Sales volume growth to exceed production growth, drawing down sellable steel inventory | Q3 and Q4 FY26 |
| Inventory liquidation | Liquidate at least 50% of sellable steel inventory | During FY26-27 |
| Borrowing reduction | Momentum of borrowing reduction to continue | Q3 and Q4 FY26 |
| Debt-equity ratio | Reduce non-IndAS debt-equity ratio to 0.3–0.35 or ~0.4 | By FY26 year-end |
| Q4 EBITDA margin | Move toward 14–15% | Q4 FY26 |
| Capex | In excess of Rs.7,500 crores (FY26); in excess of Rs.10,000 crores (FY27) | FY26 and FY27 |
| Volume growth | 5–7% growth over FY26 through de-bottlenecking | FY27 |
| Expansion funding mix | 50:50 debt vs internal accrual | Over next 4–5 years |
| Scrap & by-product sales | Expected to go higher | Q3 and Q4 FY26 |
| Coal cost | Imported coal price moving toward Rs.18,000–18,100 | Q3 FY26 |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue from operations (H1) | ₹52,625 cr, grew 8% YoY vs ₹48,672 cr |
| EBITDA (H1) | ₹5,754 cr, growth of ~3% YoY |
| EBITDA margin (H1) | 11.01%, vs 12.9% in H1 FY25 and 11.57% full-year FY25 average |
| Profit before tax (H1) | ₹1,443 cr, increased 28% YoY |
| Profit after tax (H1) | ₹1,112 cr, increased 32% YoY |
| Sales volume (H1) | 0.95 crore tons, grew ~17% from 0.81 crore tons in H1 last year |
| Crude steel production (H1) | 0.95 crore tons, flat vs 0.95 crore tons in H1 last year |
| Blended average NSR | ₹49,000/ton, down ~₹2,700/ton QoQ from ₹51,700/ton in Q1 |
| Long product NSR | ₹49,000/ton, down ~₹5,500/ton QoQ from ₹54,500/ton in Q1 |
| Flat product NSR | ₹48,700/ton, down ~₹1,700/ton QoQ from ₹50,400/ton in Q1 |
| Coking coal cost (average) | ₹17,400/ton, with imported coal at ₹18,150/ton |
| Borrowings (non-IndAS, 30 Sep) | ₹26,427 cr, reduction of more than ₹3,000 cr vs opening |
| Debt-equity ratio (non-IndAS) | ~0.46, target to reduce to 0.3–0.4 by year end |
| CAPEX (H1) | ₹3,375 cr, above target of ₹3,100 cr; FY26 target in excess of ₹7,500 cr |
| Value-added product share | 57%, up from 55% in Q1; targeting more than 60% |
| Scrap and by-product sales | ₹1,140 cr, up ~₹250 cr QoQ from ₹869 cr in Q1 |
| Finished steel inventory (30 Sep) | 0.19 crore tons; total steel inventory flat at 0.27 crore tons opening and closing |
| NMDC trading volume (Q2) | 3 lakh tons, value ₹1,500 cr; 1.85 crore tons iron ore target for FY26 intact |
| FY27 volume growth target | 5% to 7%, more than 5% vs FY26 |
| FY27 CAPEX target | in excess of ₹10,000 cr |
| IISCO expansion | 0.45 crore tons at cost of ~₹36,000 cr; major packages tendered and orders being placed |