Key Takeaways
- Volume-led recovery, margin squeeze: Sales volume jumped 24% QoQ to 0.52 crore tons, but EBITDA per ton fell to ₹8,170 as imported coking coal costs spiked unexpectedly and monsoon rains hurt technical parameters.
- Coal cost guidance missed badly: Management guided for a ₹1,000–2,000/ton reduction in Q1, but Q2 imported coking coal cost actually rose ₹1,700/ton to ₹22,930 due to geopolitical issues and China demand; Q3 is expected to rise another ~₹1,000/ton.
- Capex super-cycle is real and funded: SAIL confirmed a ₹1,20,000 crore capex plan over four years to expand capacity from 2 to 3.5 crore tons, with annual spend ramping from ₹15,000 crores in FY27 to over ₹30,000–35,000 crores in later years.
- Iron ore monetization is a quiet profit driver: Iron ore fines sales surged 167% in H1, contributing ₹265 crores in incremental profit, with FY27 target of 0.7–0.8 crore tons and a long-term aspiration of 100 MTPA by FY30–31.
- What to watch next quarter: Whether October NSR gains of ~₹4,000/ton hold through Q3, whether Tasra coking coal mine stays on track for January 2027 start, and whether the promised EBITDA per ton recovery to ~₹11,000–12,000 materializes.
Volume & Realization Dynamics
- Sales volume beat the monsoon: Despite unprecedented rains in Jharkhand and Odisha hurting production and blast furnace productivity, sales volumes rose 24% QoQ through deliberate inventory reduction, increased high-end production, and improving market conditions toward September.
- NSR turning up: October NSR for longs at ₹58,700 and flats at ₹61,700, roughly ₹4,000 above the Q2 average, driven by robust demand and high coal prices; management expects these levels to continue with possible further upward movement.
- FY27 volume guidance cut: Saleable steel sales revised down to 2.1 crore tons from 2.2 crore tons, though crude steel production still expected at 2.2 crore tons; RINL sales to contribute a maximum of 500,000 tons for the full year at very small margin.
- Inventory discipline: Steel inventory reduced from 0.21 crore tons at June-end to 0.16 crore tons at September-end, and from 17.5 days to 15 days; year-end target is ~0.12–0.13 crore tons, roughly two weeks of inventory.
Panda: "Our effort was on stock reduction, on increasing sales and increasing high-end production. So, these 2 efforts have really given us a lot of advantage to the tune around ₹700 crores to ₹800."
Coal Cost: The Big Miss
- Q2 imported coking coal cost rose to ₹22,930/ton, up ₹1,700/ton QoQ, when management had guided for a ₹1,000–2,000/ton reduction; the Platts index spiked to $290/ton in August before stabilizing at $266–$267/ton.
- Q3 expected to worsen: Imported coal consumption rate expected to hover around ₹23,500/ton, with October at ₹24,100 and November similar; Q4 expected back to around ₹22,000/ton.
- Coke rate suffered: Coke rate went up in Q2 because of typical rainy-season issues (wet coal, wet raw material, blast furnace productivity), but October parameters have shown good improvement.
- No accounting change: Management explicitly stated the guidance miss was purely due to unexpected international coal price movements from geopolitical situations and China demand, not any change in accounting method.
Panda: "There is no change in method of accounting. Only thing is that actually by quarter end, quarter 1 end, we were thinking that probably the prices will come down because there was a rise in quarter 1. But because of the international situations, it started increasing."
Capex Super-Cycle & Expansion
- ₹1,20,000 crores over four years: Annual capex ramping from ₹15,000 crores in FY27 (H2: ₹9,000–10,000 crores) to ₹20,000+ crores in FY28, ₹25,000 crores in FY29, and potentially exceeding ₹30,000–35,000 crores in later years.
- Four-plant expansion to 3.5 crore tons: IISCO (major orders placed, execution started), Bokaro (advanced tendering), Bhilai (tendering starting in weeks), and Rourkela (DPR prepared, in-principle approval sought); all sites are encroachment-free.
- Funding strategy: Internal accruals targeted at ₹10,000–12,000 crores/year; debt to increase from next year onwards as capex ramps; FPO planned but timing awaits rejuvenated investor confidence; management aims to execute without adversely impacting balance sheet ratios.
- Debt reduction now, increase later: Borrowings reduced by ₹1,146 crores in Q2 and ₹1,080 crores in H1 through effective treasury management; cost of borrowings improved to 6.34%; further debt reduction expected in Q3 and Q4 FY27 before the capex-driven increase begins next year.
Panda: "We will do that in a proper way so that it doesn't impact our balance sheet and the ratios very much adversely. We are trying to actually increase our internal accruals to improve profitability through efforts in top line as well as cost reductions so that the dependence on the loan or the borrowings will be less."
Iron Ore: The Hidden Value Driver
- Iron ore fines sales surged 167% in H1 to 0.25 crore tons, contributing incremental profit of ₹265 crores; FY27 target is 0.7–0.8 crore tons, with the major chunk to come from Rowghat.
- Rowghat ramp-up: MDO has started interim mining with EC clearance of 0.3 crore tons and is near hitting those levels; main mining by MDO to start in ~1 year or more, then phased ramp-up to 1.4 crore tons over 3–4 years (0.2 → 0.3 → 0.4 → 0.6 → 0.9 → 1.4 crore tons).
- Long-term aspiration: 100 MTPA iron ore production by FY30–31, up from ~38–39 MTPA last year; fallback target of 8–8.5 crore tons if the ambitious 10 crore ton target proves difficult, with outcomes heavily dependent on Rowghat and Gua.
- Tasra coking coal mine: On track to start production from January 2027 (Q4 FY27), with profit benefit expected from Q4; once stabilized, will reduce the burden of imported coking coal.
- Low-grade ore beneficiation: Silica reduction plant and SBP beneficiation plant already operating at Chhattisgarh Group of Mines; future beneficiation plants planned at Gua mines to beneficiate subgrade ore, then pelletize and consume.
Panda: "Regarding 10 crore tons, that is an ambitious target by us for '30-'31 or '31-'32. It a lot depends on Rowghat, lot depends on Gua. ... But if not 10 crore tons, then at least we'll able to achieve 8 crore tons, 8.5 crore tons something like that."
Costs, Margins & People
- EBITDA per ton fell to ₹8,170 in Q2 from the H1 average of ₹9,561, hit by NSR pressure and cost implications from unprecedented rains affecting furnaces, raw material costs, and techno-economic parameters; management targets Q3/Q4 recovery to last year Q4 levels of ~₹11,000–12,000/ton.
- Labour code provision: ₹198 crores booked in Q2 (₹350 crores H1) under other expenses, based on best-estimate using infrastructure-related rate since the gazette notification lacks a final industrial rate; some incremental plus/minus adjustment expected when actual figures come.
- Wage cost provisions: Planning has started but no calculation yet; thought process initiated, with no guidance provided on the potential impact.
- Headcount shrinking steadily: Down to 48,000 at Q2-end from ~50,000 last year, driven by superannuation and VRS; normal separation of 3,000–4,000/year plus ~1,000 VRS; FY27 year-end expected ~46,000, declining to ~26,000 by 2031.
- Finance cost: Cost of borrowings improved to 6.34% in H1 from 6.42% last year, but repo rate +25 bps will push Q3/Q4 interest slightly higher; management did not directly explain the Q2 rise in absolute finance cost despite lower debt.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Sales volume | 2.1 crore tons saleable steel (revised from 2.2) | FY27 |
| Crude steel production | 2.2 crore tons | FY27 |
| Iron ore fines sales | 0.7–0.8 crore tons | FY27 |
| Iron ore production | 4.8–5.0 crore tons | FY27 |
| Imported coking coal cost | ~₹23,500/ton (Oct at ₹24,100, Nov similar) | Q3 FY27 |
| Imported coking coal cost | ~₹22,000/ton | Q4 FY27 |
| EBITDA per ton | Recover to ~₹11,000–12,000/ton (last year Q4 levels) | Q3/Q4 FY27 |
| Capex spend | ₹15,000 crores (H2: ₹9,000–10,000 crores) | FY27 |
| Capex spend | >₹20,000 crores | FY28 |
| Capex spend | ₹25,000 crores | FY29 |
| Total capex outlay | ₹1,20,000 crores | FY27–FY31 |
| Tasra coking coal mine | Production start, profit benefit | Q4 FY27 (Jan 2027) |
| Rowghat iron ore mine | Main mining by MDO to start | ~1 year or more |
| Rowghat ramp-up | Phased ramp-up to 1.4 crore tons | 3–4 years |
| Steel inventory | ~0.12–0.13 crore tons (~2 weeks) | FY27 year-end |
| Employee headcount | ~46,000 | FY27 year-end |
| Employee headcount | ~26,000 | By 2031 |
| RINL sales volume | Maximum 500,000 tons | FY27 |
| Debt trajectory | Reduction in Q3 and Q4; increase from next year | FY27 / FY28 onward |
| FPO | Planned, timing dependent on investor confidence | No date |
| Wage cost provision | Planning started, no calculation yet | No timeline |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Sales turnover | ₹31,766 cr, +20% YoY and +22% QoQ |
| EBITDA | ₹4,561 cr, vs ₹553 cr CPLY and ₹2,159 cr Q1 |
| PBT | ₹2,356 cr, vs ₹553 cr CPLY and ₹2,159 cr Q1 |
| PAT | ₹1,774 cr, vs ₹427 cr CPLY and ₹1,636 cr Q1 |
| EBITDA per ton | ₹8,170, vs H1 average of ₹9,561; Q4 FY26 was ~₹11,000–12,000 |
| Sales volume | 0.52 crore tons, +5% YoY and +24% QoQ |
| Crude steel production | 0.48 crore tons, +4% YoY and +2% QoQ |
| Average NSR (longs) | ₹54,400 in Q2; October at ₹58,700 |
| Average NSR (flats) | ₹57,000 in Q2; October at ₹61,700 |
| Imported coking coal cost | ₹22,930 per ton, up ₹1,700 QoQ; Q3 expected ~₹23,800–23,900 |
| Borrowings | ₹20,583 cr, down ₹1,146 cr in Q2 and ₹1,080 cr in H1 |
| Debt-equity ratio | 0.34x at end of Q2 FY27 |
| Cost of borrowings | 6.34% in H1, vs 6.42% last year |
| Total steel inventory | 0.16 crore tons (15 days), down from 0.21 crore tons at end-Q1 |
| Iron ore fines sales volume | ~0.11–0.12 crore tons in Q2 (per management's rough estimate); H1 total 0.25 crore tons |
| Employee count | 48,000 at end of Q2; year-end expected ~46,000 |
| Labour code provision | ₹198 cr in Q2; ₹350 cr in H1 |
| RINL sales volume | 88,000 tons in Q2; full-year estimate max 500,000 tons |
| FY27 sales volume guidance | ~2.1 crore tons (saleable steel), revised from 2.2 crore tons |
| FY27 capex guidance | ₹15,000 cr; H1 achieved ₹5,500 cr |