Steel Authority of India Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/xzmet52mo1cspad04lil4dyy.pdf

Key Takeaways


Volume & Realization Dynamics

Panda: "Our effort was on stock reduction, on increasing sales and increasing high-end production. So, these 2 efforts have really given us a lot of advantage to the tune around ₹700 crores to ₹800."

Coal Cost: The Big Miss

Panda: "There is no change in method of accounting. Only thing is that actually by quarter end, quarter 1 end, we were thinking that probably the prices will come down because there was a rise in quarter 1. But because of the international situations, it started increasing."

Capex Super-Cycle & Expansion

Panda: "We will do that in a proper way so that it doesn't impact our balance sheet and the ratios very much adversely. We are trying to actually increase our internal accruals to improve profitability through efforts in top line as well as cost reductions so that the dependence on the loan or the borrowings will be less."

Iron Ore: The Hidden Value Driver

Panda: "Regarding 10 crore tons, that is an ambitious target by us for '30-'31 or '31-'32. It a lot depends on Rowghat, lot depends on Gua. ... But if not 10 crore tons, then at least we'll able to achieve 8 crore tons, 8.5 crore tons something like that."

Costs, Margins & People


Guidance & Commitments

CommitmentSpecificsTimeline
Sales volume2.1 crore tons saleable steel (revised from 2.2)FY27
Crude steel production2.2 crore tonsFY27
Iron ore fines sales0.7–0.8 crore tonsFY27
Iron ore production4.8–5.0 crore tonsFY27
Imported coking coal cost~₹23,500/ton (Oct at ₹24,100, Nov similar)Q3 FY27
Imported coking coal cost~₹22,000/tonQ4 FY27
EBITDA per tonRecover to ~₹11,000–12,000/ton (last year Q4 levels)Q3/Q4 FY27
Capex spend₹15,000 crores (H2: ₹9,000–10,000 crores)FY27
Capex spend>₹20,000 croresFY28
Capex spend₹25,000 croresFY29
Total capex outlay₹1,20,000 croresFY27–FY31
Tasra coking coal mineProduction start, profit benefitQ4 FY27 (Jan 2027)
Rowghat iron ore mineMain mining by MDO to start~1 year or more
Rowghat ramp-upPhased ramp-up to 1.4 crore tons3–4 years
Steel inventory~0.12–0.13 crore tons (~2 weeks)FY27 year-end
Employee headcount~46,000FY27 year-end
Employee headcount~26,000By 2031
RINL sales volumeMaximum 500,000 tonsFY27
Debt trajectoryReduction in Q3 and Q4; increase from next yearFY27 / FY28 onward
FPOPlanned, timing dependent on investor confidenceNo date
Wage cost provisionPlanning started, no calculation yetNo timeline

Key Metrics

MetricQ2 FY27
Sales turnover₹31,766 cr, +20% YoY and +22% QoQ
EBITDA₹4,561 cr, vs ₹553 cr CPLY and ₹2,159 cr Q1
PBT₹2,356 cr, vs ₹553 cr CPLY and ₹2,159 cr Q1
PAT₹1,774 cr, vs ₹427 cr CPLY and ₹1,636 cr Q1
EBITDA per ton₹8,170, vs H1 average of ₹9,561; Q4 FY26 was ~₹11,000–12,000
Sales volume0.52 crore tons, +5% YoY and +24% QoQ
Crude steel production0.48 crore tons, +4% YoY and +2% QoQ
Average NSR (longs)₹54,400 in Q2; October at ₹58,700
Average NSR (flats)₹57,000 in Q2; October at ₹61,700
Imported coking coal cost₹22,930 per ton, up ₹1,700 QoQ; Q3 expected ~₹23,800–23,900
Borrowings₹20,583 cr, down ₹1,146 cr in Q2 and ₹1,080 cr in H1
Debt-equity ratio0.34x at end of Q2 FY27
Cost of borrowings6.34% in H1, vs 6.42% last year
Total steel inventory0.16 crore tons (15 days), down from 0.21 crore tons at end-Q1
Iron ore fines sales volume~0.11–0.12 crore tons in Q2 (per management's rough estimate); H1 total 0.25 crore tons
Employee count48,000 at end of Q2; year-end expected ~46,000
Labour code provision₹198 cr in Q2; ₹350 cr in H1
RINL sales volume88,000 tons in Q2; full-year estimate max 500,000 tons
FY27 sales volume guidance~2.1 crore tons (saleable steel), revised from 2.2 crore tons
FY27 capex guidance₹15,000 cr; H1 achieved ₹5,500 cr