Key Takeaways
- Record Q1 top line, margin squeeze: Revenue crossed ₹200 crores for the first time in a seasonally sluggish Q1, but EBITDA margin compressed to 8.0% from 11.1% YoY as commodity volatility and inventory costs hit profitability.
- Export orders already half of FY22 full-year: Q1 export orders reached ₹35 crores vs ₹75 crores for all of FY22, driven by telecom towers for Africa and the Philippines, with full-year exports guided to ₹120 crores.
- 5G is the structural growth story: Management expects a million more towers in India over the next 4–5 years, and Salasar holds a market-leader position with no additional capex needed because existing capacity is fungible across tower types.
- Two new plants on track for FY23/FY24: A 100,000-metric-ton galvanizing unit and a 25,000-metric-ton heavy steel plant in Chhattisgarh are both under construction, with commissioning expected within the last quarter of FY23 and FY24 respectively.
- What to watch next quarter: Whether the promised margin recovery to the 10–11% band materializes as raw material prices soften, and whether 5G-related order inflow converts into booked revenue.
Top Line & Revenue Drivers
- Q1 revenue milestone: Top line crossed ₹200 crores for the first time in a Q1, a quarter normally sluggish due to budget finalization and the rainy season.
- Broad-based demand: Growth came from all sectors including telecom, power transmission, and railways, supported by good supply quantities and EPC execution, plus a tailwind from unbilled revenues carried over from the prior quarter-end.
- FY23 revenue guidance: Management targets 20% to 25% top-line growth, implying a range of ₹900–₹1,000 crores on the FY22 base of ~₹720 crores.
- FY24 early look: A further 15% to 20% YoY growth is the stated ambition for the following year.
- Order book tenure: Execution timelines range from 3 months to 24 months depending on the order, with some completing in as little as 3 months and others stretching to 6 months or beyond.
Margins: The Squeeze & The Recovery Bet
- EBITDA margin decline: Margins fell to 8.0% in Q1 FY23 from 11.1% in Q1 FY22, driven by high commodity price volatility and higher employee costs from annual increments.
- Commodity pass-through lag: Profitability was hit because dispatches in June reflected April prices while raw material was bought in May/June at elevated prices; carrying high-cost inventory from the prior quarter-end also added extra finance cost.
- Recovery thesis: Management states margins are "on a back track now" and expects improvement this quarter, helped by softening raw material prices that reduce both inventory cost and the finance cost tied to inventory.
- Sustainable margin target: The long-term sustainable EBITDA margin range is pegged at 10% to 11%, with management aiming to return there "sooner than later."
Agarwal: "I think margins are on a back track now and we hope that the margins in this quarter would be better and sustainable."
5G: The Structural Opportunity
- Tower demand math: India currently has ~600,000 towers built over 25 years; management estimates at least a million more towers are needed in the next 4–5 years to cover the country on 5G, effectively adding another 10 lakh towers in five years.
- Tonnage vs. volume trade-off: 5G towers will be lighter (almost 2 tons for 25–30 meters) and at lower heights, so per-tower tonnage is less, but the multiple increase in tower numbers means overall tonnage demand should be similar.
- No incremental capex needed: Existing manufacturing capacity is fungible across telecom towers, poles, angle bar towers, and power transmission line towers, so the 5G rollout requires no additional capital investment.
- Enquiries have begun: Post spectrum bidding, enquiries have started coming in from tower companies and operators, and management calls 5G a "game changer" given Salasar's market-leader position.
- Telecom margin caution: Despite the volume opportunity, management does not expect margin improvement in telecom specifically, citing persistent pressure from operators to provide the most optimized costings while they themselves face pressure to roll out huge numbers of sites.
Agarwal: "Today India has close to around 600,000 towers and to be able to cover the whole country on 5G network, probably they need at least a million more towers in next 4 to 5 years."
Export Business
- Q1 export surge: Export orders in Q1 FY23 already crossed ₹35 crores, compared to ₹75 crores for the full FY22, driven primarily by telecom towers.
- Full-year export guidance: Exports are expected to cross ₹110–120 crores for FY23.
- Key customers and geographies: American Tower Corporation (ATC) is the primary buyer across multiple African countries (Kenya, Rwanda, Ghana, Nigeria, Burkina Faso, Gabon), alongside Airtel for their African operations; the Philippines is a newer market opened about two years back with new tower companies building out sites.
- Export demand durability: Management expects export demand to continue for the next couple of years as 5G rolls out, noting that Africa is a few years behind India in the cycle.
- Solar export add-on: Small export orders for galvanized solar structures have also been received, roughly ₹2 crores in solar plus ₹4–5 crores from telecom buyers like ATC for solar structures.
Capacity Expansion
- New galvanizing plant (Unit 3): Adjacent to the existing plant, with a capacity of almost 100,000 metric tons; land is acquired, construction is ongoing (sheds being fabricated, foundations laid, designs completed), and plant and machinery orders are already placed. Machinery is being shipped from overseas by October–November, with execution in place by December–January; the plant is expected to be "comfortably up and running" within the last quarter of FY23.
- Chhattisgarh heavy steel plant: A 25,000-metric-ton capacity heavy steel structure division in Bhilai, focused on bridges; land is acquired, development work is ongoing, and construction is expected to start September–October, with commissioning targeted within the last quarter of FY23.
- Capacity utilization trajectory: Current utilization is ~60%; management sees it rising to 75–80% in the current or next quarter, a level considered full capacity given ideal conditions versus actual product mix. For FY23 as a whole, utilization is expected at 70% to 75%. New plants will run at lower utilization for the first six months to a year before ramping up.
Agarwal: "Typically if we are able to achieve anything between 75 to 80% that I would consider as a full capacity because the capacity calculation is based on certain ideal conditions..."
Segment Dynamics: Solar, Smart Cities & Power Transmission
- Solar segment caution: Management is "personally not very bullish" on solar because end customers are not making money, many smaller players manufacture very light structures, and demand for galvanized structures in India is limited; the company takes only what suits in terms of quantity and price.
- Smart city disappointment: Salasar has not been able to get much business from smart cities because the revenue case for telecom operators is not lucrative: smart city SPVs want operators to do the capex and share revenues, but operators are investing only where they can get immediate revenues.
- Power transmission upside: Monopoles for power transmission lines are expected to deliver likely better margins as well as good revenues.
- Heavy steel traction: The new heavy steel structure division making bridges has secured a "very good order book" and is seeing good traction.
Agarwal: "I'm personally not very bullish in the sense that the margins in the solar sector for our end customer have been excused. If your customer is not making money, it is impossible for you to make money in that."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 20% to 25% top-line growth (₹900–₹1,000 crores) | FY23 |
| Revenue growth | 15% to 20% YoY growth | FY24 |
| EBITDA margin recovery | Return to 10%–11% sustainable range | "Sooner than later" |
| Capacity utilization | 70% to 75% | FY23 |
| Capacity utilization (existing) | 75% to 80% | This quarter and next quarter |
| Export orders | Cross ₹110–120 crores | FY23 |
| Chhattisgarh plant commissioning | Within last quarter | FY23 |
| UP galvanizing plant commissioning | Within last quarter of next year | FY24 |
Key Metrics
| Metric | Q1 FY23 |
|---|---|
| Consolidated revenue | ₹211 cr, +58.6% YoY |
| EBITDA | ₹17 cr, +15% YoY |
| EBITDA margin | 8.0%, declined from 11.1% in Q1 FY22 |
| PAT | ₹7.3 cr, in line with Q1 FY22 |
| FY23 revenue growth guidance | 20–25%, implying ₹900–₹1,000 cr |
| FY24 revenue growth guidance | 15–20% YoY |
| Overall order book | ₹1,182 cr as on 30 Jun 2022 |
| Unexecuted EPC orders | ₹809 cr |
| L1 EPC orders | ₹89 cr |
| Heavy steel structure division orders | ₹233 cr, up from ₹200 cr on 31 Mar 2022 |
| Export orders in hand | ₹62 cr |
| Capacity utilization | ~60%, produced ~14,000 tons |
| Net debt | Unchanged from 31 Mar 2022, no new debt |
| Cash and cash equivalents | ~₹12 cr as on 30 Jun 2022 |
| Cost of debt | ~7% |