Key Takeaways
- Normalization after a black-swan Q1: EBITDA per ton fell ~INR600 QoQ as war-driven price spikes unwound, but management calls Q2’s ~12% margin the sustainable baseline and has raised its full-year EBITDA per ton guidance bracket.
- Stainless steel margin held despite dumping: Chinese dumping and a QCO relaxation cost the division ~INR6–7 crores of EBITDA, yet it still delivered INR12,000–13,000 per ton, a level management expects to sustain through H2.
- Seamless pipe entry is the new growth thesis: A INR148-crore, 14,400-ton stainless-steel seamless pipe project targets a market management believes will grow 10x in a decade, with first production in FY29 and a >24% ROCE aspiration for the combined business.
- Capex cycle is fully loaded: Three expansions (Kesda, Sarora, DFT brownfield) go live between March and September 2027, with FY28 volume guided upward of ~7 lakh tons and EBITDA upward of ~INR750 crores. The seamless pipe plant is expected by March 2028.
- What to watch next quarter: Whether Q3 price normalization stabilizes at guided realizations, progress on seamless-pipe land acquisition and machinery orders, and any government action on stainless-steel import restrictions.
Quarterly Performance & Margin Walk
- The Q1-to-Q2 bridge: Q1 was an outlier where war-driven price increases outpaced raw material costs; Q2 saw those prices normalize while raw material costs rose on monsoon moisture and yield effects, compressing the spread. Management calls Q2 the real sustainable number.
- Product mix shift: Incremental sales volume came predominantly from the MS Pipes & Tubes segment; the rest of the mix stayed nearly identical to Q1.
- MS and coated margins improved: EBITDA per ton rose to INR9,000 in MS and INR7,000 in coated products, even as the blended number declined.
- Stainless steel held up: Despite heavy Chinese dumping on 200- and 300-series coil and a QCO relaxation that opened the door to imports, the division achieved INR12,000–13,000 per ton EBITDA. Management estimates the QCO relaxation alone cost INR6–7 crores of EBITDA versus Q1 potential.
- Working capital tightened sharply: Days improved to 4–5 as distributors destocked ahead of anticipated price increases, customer recoveries improved, and better supplier credit terms were negotiated.
- Structural pipe utilization capped: Q2 ran at 76% utilization, which management calls optimal with no further headroom; Q3 volume is expected to be restricted to Q1 levels because of the Q2 destocking pull-forward.
- Margin ceiling acknowledged: Management stated the best margin achievable with the existing integrated facility setup is around 13%, the level shown in Q1.
Bikash Agrawaal: "Q1 was absolutely a black swan event for us where there was a war situation, there were a lot of price increase, abnormal price was high, which now started you can say normalizing in Q2, and now also it is still normalizing in Q3."
Stainless Steel: Imports, QCO & the Demand Gap
- The dumping dynamic: China is selling 200- and 300-series coil below its production cost, per management, compressing domestic realizations.
- The policy bet: Management expects the government to take a hard call by March 2027, evaluating a minimum import price for 200 series, anti-dumping duties for 300 series, and restrictions on stainless-steel raw materials already produced domestically.
- Demand runs ahead of supply: Domestic stainless-steel coil demand is ~0.4–0.5 crore tons and growing double digits; domestic production cannot yet meet it. Once it can, management believes the government will restrict QCO imports.
- Kesda fills the gap: The 360,000-ton integrated stainless-steel facility, commissioning March 2027, will produce 0.1–0.4 mm thickness, approximately 600 mm width coils (vs. current 0.4–0.9 mm), targeting complete import substitution.
- Instant delivery as a moat: Import-dependent downstream manufacturers currently wait 2–3 months and pay advances to traders. Sambhv’s domestic production will offer delivery squeezed to 15 days and payment facilities, improving customers’ own working cycles and profitability.
- Product mix stays 200-series heavy: Going forward, the stainless-steel mix will remain ~90% 200 series and ~10% 300 series.
Bikash Agrawaal: "The price at which China is selling in market is basically they are undercutting their production cost price and they are selling into the market. So that is why I said it is dumping that is happening."
Seamless Pipe: The New Growth Vector
- The project: INR148 crores investment for 14,400 tons per annum of stainless-steel seamless pipes and tubes, housed in a subsidiary. First production is targeted for March 2028.
- The demand thesis: Management expects the seamless pipe market (alloy and stainless steel) to grow 10x over the next decade, driven by sunrise sectors (semiconductor, data center, green hydrogen, coal gasification, aerospace, defence, nuclear), traditional industry capex and maintenance, and export markets including Russia, Europe, the Americas and Latin America.
- The supply-demand gap: Current waiting periods are 6–8 months, which management likens to booking a scooter in the 1990s. Above 6-inch seamless pipe is 90% imported; the company is targeting import substitution by manufacturing up to 12-inch.
- Entry method: The piercing method was chosen over extrusion for capital and conversion-cost efficiency. Phase 1 includes mother hollow making and pilgering; round bars will be procured domestically, where supply is ample.
- Go-to-market: Initial sales for 1–1.5 years will target the commercial and replacement market where OEM approvals are not required. Basic approvals are expected in 3–6 months; a licensing and sales team is already being built.
- Backward integration deferred: Phase 2 or 3 may add a fully integrated facility with captive power, SMS and a round mill, but that is a future capex cycle.
- Funding: Total capex of INR400 crores (over and above Vision 2030), split 50% internal accruals and 50% debt or equity raised after the initial 14,400-ton plant goes live.
- Returns expectation: At 50–70% utilization, management targets INR60–70 crores EBITDA on INR150 crores capex, with combined capex plus working capital deployment of INR240–250 crores yielding >24–25% ROCE.
- Market consolidation thesis: Management expects smaller players (below 2,000-ton capacity, ~25–30 operating in India) to exit or need to backward-integrate and scale up; a well-capitalized, integrated entrant can consolidate.
Bikash Agrawaal: "We are now in the era of nineties where you have to book a scooter and you have to wait for six months to get a scooter. So that is the kind of scenario that is happening in stainless steel seamless pipe currently."
Capex Cycle & Capacity Ramp-Up
| Project | Capacity / Scope | Live Date | Key Financials |
|---|---|---|---|
| Kesda integrated SS facility + 25 MW power plant | 360,000 tons stainless steel | March 2027 | FY28: 30–35% utilization; FY29: 60–65% |
| Sarora 30 MW captive power plant | 30 MW (INR150 crores) | September 2027 | Saves INR60–70 crores minimum; adds INR1,000–1,500/ton EBITDA at >90% captive power |
| DFT route brownfield expansion | 150,000 tons MS | September 2027 | Part of ~INR300 crores additional MS sales in FY28 |
| Seamless pipe plant | 14,400 tons stainless steel | March 2028 | FY29: ~30% utilization; FY30: 60–65% (~10,000 tons) |
- Phase 2 and 3 cost-optimization capex: Management is studying a syngas plant, acid regeneration, and oxygen/nitrogen plants. At 0.2 crore tons production, these could save INR3–4 crores monthly, adding ~1% margin. Combined with captive power, total margin accretion of ~2.5–3% is targeted by 2030.
- Phase 2/3 total outlay: Management initially deflected on a rough estimate, then provided an approximate range of INR1,500–2,000 crores, noting it is not yet Board-approved.
- FY28 sales bridge: The existing capex cycle is expected to add ~INR2,300–2,400 crores in sales (INR2,000 crores stainless steel + INR300 crores MS DFT). Stainless steel volume is expected to add 1–1.2 lakh tons.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 sales volume | ~5.5 lakh tons | FY28 full year |
| FY27 EBITDA | Upward of ~INR550 crores | FY28 full year |
| FY27 EBITDA per ton | INR8,000–8,500 (revised upward) | FY27 full year |
| FY27 value-added product sales | 410,000–425,000 tons | FY27 full year |
| FY28 sales volume | Upward of ~7 lakh tons | FY28 full year |
| FY28 EBITDA | Upward of ~INR750 crores | FY28 full year |
| FY28 stainless steel volume addition | 1–1.2 lakh tons | FY28 full year |
| FY28 Kesda utilization | 30–35% | FY28 (first year) |
| FY29 Kesda utilization | 60–65% | FY29 |
| Seamless pipe first production | Plant live | March 2028 |
| Seamless pipe FY29 utilization | ~30% (~3,000–4,000 tons) | FY29 |
| Seamless pipe FY30 utilization | 60–65% (~10,000 tons) | FY30 |
| Seamless pipe EBITDA | INR60–70 crores at 50–70% utilization on INR150 crores capex | At target utilization |
| Seamless pipe ROCE | >24–25% on INR240–250 crores combined deployment | At target utilization |
| Captive power margin accretion | INR1,000–1,500 per ton (1–1.5% EBITDA) | When >90% electricity from captive plant |
| Cost-saving margin accretion (total) | ~2.5–3% EBITDA-level | By 2030 |
| Net debt-to-EBITDA | ~1.4x–1.5x | End of Q4 FY27 |
| Overall business utilization target | 60% | FY30 |
Business Model & Competitive Position
- Backward integration as a shield: Over 80% of coil is produced in-house, insulating the company from HRC availability issues. When coil is scarce in the open market, the integrated model becomes a relative advantage.
- Scrap sourcing is manageable: The company is only dependent on imports for high-value nickel-alloy scrap that substitutes nickel; other raw materials (manganese, chrome, sponge, MS scrap) are sourced domestically. At current stainless-steel production of 5,000–5,500 tons per month, sourcing is easy. For the larger Kesda facility, management plans to tie up with Indonesian and international traders for nickel pig iron if domestic scrap supply remains tight.
- PLI tailwind: The company received PLI approval and signed an MoU under PLI 1.2 for seamless pipe sales to priority sectors (data center, semiconductor, defence, nuclear), confirming approximately 13% revenue incentive from the Government of India.
- Vajra Alloy optionality: An investment in Vajra Alloy, which produces Nimonic, Inconel, Monel and high-nickel alloy products, could supply round bars for the seamless pipe business if demand arises.
- Geopolitics as a net positive: The prolonged war situation has extended the commodity upcycle and increased government focus on self-sufficiency across all steel types under the Vision 2047 National Steel Policy.
Bikash Agrawaal: "This is testament to our business model that during this situation where the scarcity is there, we are emerging as a better resilient player in terms of integrated steel pipe manufacturer."
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue | ₹840 cr |
| EBITDA | ₹105 cr |
| PAT | ₹61 cr |
| EBITDA margin | more than 12% |
| PAT margin | more than 7% |
| Operating cash flow | ₹213 cr generated during the quarter |
| Value-added product sale volume growth | 27% YoY |
| EBITDA per ton (blended) | ₹8,200, down from ₹8,800 in Q1 (per an analyst's math) |
| MS and coated product EBITDA per ton | ₹9,000 for MS, ₹7,000 for coated |
| Stainless steel EBITDA per ton | ₹12,000 to ₹13,000 |
| Working capital days | 4 to 5 days, improved; optimum maintained at 20 to 25 days |
| Net debt-to-EBITDA (H1 FY27) | 1.04x, expected to rise to 1.4x to 1.5x by Q4 FY27 on a net debt basis |
| Stainless steel product mix | ~90% 200 series, ~10% 300 series |
| Stainless steel capacity utilization | ~60%, described as optimal |