Key Takeaways
- Volume growth hit by elections and rain: Revenue reached Rs. 8,311 crores, but volume suffered in East and South due to an unscheduled shutdown, while elections and early monsoon dampened industry demand.
- Cost per ton declined 3% to Rs. 4,437: Driven by a 13% drop in energy costs and an 8% reduction in logistics costs, partially offsetting a 5%-6% price decline.
- Penna acquisition to close within a fortnight: The deal will provide low-cost clinker to South Indian grinding units, with integration benefits starting in Q2 and full availability in Q3.
- Sanghi clinker to hit full utilization by Q4 FY25: Both kilns are undergoing major refurbishment, set to finish by mid-November, enabling a ramp-up that has already doubled Gujarat volumes.
- What to watch next quarter: Whether post-monsoon price recovery materializes as expected, the pace of Penna integration benefits, and the commissioning of the first 200 MW phase of green power.
Cost Leadership & Margin Performance
- Energy cost down 13%: Power and fuel cost fell to Rs. 1,304 per ton from Rs. 1,501, driven by higher AFR share (9.3% from 7%) and WHRS share in power mix (15.1% from 11.5%).
- Logistics cost down 8%: Freight cost declined to Rs. 1,323 per ton from Rs. 1,436 through GPWIS rakes for clinker, BCFC rakes for fly ash, and footprint optimization that cut secondary lead distance by 9 km to 46 km.
- Green power to start delivering from August: The first 200 MW phase of renewable energy is commissioning in Q2 FY25, with 650 MW targeted by March 2025 and the full 1,000 MW by Q1 FY26, expected to reduce power cost by Rs. 90 per ton by FY28.
- Cost reduction target of Rs. 500-550 from FY24 base: The company aims to reach Rs. 3,650 per ton from the FY24 base of Rs. 4,184, driven by freight, power and fuel, raw material, and fixed cost optimization. This target is independent of price and does not yet factor in Penna's logistic strength.
Ajay Kapur: "Our estimate of 550 cost is independent of price because cost is something that is in my hand, price is something which is more discovered in the marketplace."
Demand & Pricing Environment
- Industry demand grew 7%-8% in FY24: Cement consumption reached 42.2 crore tons, with FY25 growth projected at 7%-9% to around 45 crore tons, driven by housing and infrastructure.
- Q1 demand was tepid: Elections dragged activity for nearly two months across multiple states, and the monsoon arrived early in June. New plant additions also contributed to pressure.
- Prices hit a 36-month low in some markets: Prices declined 5%-6% sequentially from the December quarter to the June quarter, and about 6%-7% year-on-year. Management expects the normal post-monsoon recovery trajectory, with demand-supply matching more closely in the December and March quarters.
- Volume growth was uneven: The company gained market share in North and West, maintained in Center, but lost volume in East and South due to a capacity constraint from one unscheduled kiln shutdown.
Ajay Kapur: "Now, this price is the lowest price I believe in the last 36 months in most of the markets especially in some of the markets where there is extra capacity."
Sanghi Ramp-Up & Infrastructure
- Both kilns undergoing major refurbishment: The program, budgeted in the acquisition cost, will end by end of October or mid-November. The last quarter of FY25 should hit more or less full clinker utilization.
- Gujarat volumes have almost doubled because of Sanghi: The ramp-up is progressing well, with infrastructure optimization underway to enable efficient cement transport from plant to jetty via mechanized conveyor belts and the marine route.
- Jetty and shipping investments next: First-level dredging is done; the next set of investments at the jetty will begin immediately after the monsoon. Wind investment at Sanghi is also being considered, over and above the 1,000 MW program.
Ajay Kapur: "I believe this whole program will come to an end by end of October or at the most mid of November. After that I believe the last quarter of current FY, we should be hitting more or less full utilization of the clinker."
Penna Acquisition & South Market Strategy
- Closing targeted within a fortnight: The acquisition is in very advanced stages; at completion, Penna will become a wholly owned subsidiary of Ambuja and will not be a listed entity. The cash outflow was not in the June quarter.
- Integration benefit in Q2, full availability in Q3: Penna will provide high-quality, low-cost clinker to grinding units in the South (Tuticorin, Thondebhavi, Madukarai of ACC), mitigating the clinker purchase cost incurred this quarter.
- Three-brand strategy for the South: Ambuja, ACC, and Penna brands will all be used to penetrate the market; the Penna brand remains with the acquired company. Krishnapatnam and Marwar project timelines remain intact.
- Acquisition math: Per an analyst's math, the valuation comes below $90 per ton. Management stated its internal target for new growth is less than $80 per ton, with a goal to drive it down by another $5-$10.
Vinod Bahety: "I am sure you also have your own math, which is actually coming below $90 a ton. Therefore, in terms of acquisition, I think we have been very careful, methodical, and in a structured manner, which we are doing."
Capacity Expansion & CAPEX
- Path to 14 crore tons by FY28: Current capacity is 8.9 crore tons, with 10 crore tons targeted by Q2 FY26, 11.2 crore tons by end of FY26, and 14 crore tons by FY28, all funded through internal accruals while remaining debt-free.
- FY25 CAPEX target closer to Rs. 10,000 crores: Approximately Rs. 6,000 crores of cash was utilized this quarter, including Rs. 3,300 crores for organic and inorganic growth (Tuticorin acquisition, ongoing CAPEX, Penna), Rs. 630 crores in dividends, and the balance toward working capital.
- Green power investment of Rs. 6,000 crores: Rs. 1,500 crores already invested, with Rs. 4,500 crores outflow expected in the next 12 months. This will deliver a benefit of close to Rs. 100 per ton on cost of production.
- Year-end cash expected around Rs. 10,000 crores: After Penna outflow and CAPEX outflow. Over the next 5 years, after acquiring 1.4 crore tons of assets and building another 1 crore tons, the company would still have cash left of about Rs. 10,000-11,000 crores.
ACC Cash Position & Lease Renewals
- ACC's cash declined Rs. 2,000 crores sequentially: Driven by CAPEX buildup, working capital buildup, dividend, and tax. Investments include an office building in Ahmedabad (Rs. 600-700 crores), a regional office in Delhi (below Rs. 500 crores), the Rajpura unit acquisition, and Wadi unit modernization.
- Lease renewal exposure is limited: Ambuja has nil leases expiring in 2030. ACC has 19 leases coming up for renewal by 2030, but only 11 will remain by then.
- No current plan to take ACC or Sanghi private: When asked about consolidation of listed entities, management stated there are no such plans as of now, and any future decision will be communicated when clarity emerges.
Ajay Kapur: "As of now, we have no such plans. Whenever we have something to announce, we will certainly come out and..."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Penna acquisition close | Full closing and transfer | Within a fortnight |
| Penna integration benefit | Partial benefit in Q2, 100% available | Q3 FY25 |
| Sanghi clinker full utilization | Both kilns refurbished, full clinker utilization | Q4 FY25 |
| Green power phase 1 commissioning | First 200 MW RE | Q2 FY25 |
| Green power full commissioning | 650 MW by Mar 2025, 150 MW by May 2025, ~1,000 MW total | Q1 FY26 |
| Cement capacity milestone | 10 crore tons | Q2 FY26 |
| Cement capacity milestone | 11.2 crore tons | End of FY26 |
| Cement capacity milestone | 14 crore tons | FY28 |
| Cost reduction target | Rs. 500-550 reduction from FY24 base of Rs. 4,184 to reach Rs. 3,650 per ton | FY28 (implied by capacity timeline) |
| Green power cost benefit | Reduce power cost by Rs. 90 per ton | FY28 |
| Secondary lead distance reduction | Reduce by 100 km from current levels | FY28-29 |
| Waste heat recovery capacity | Increase to 186 MW | March 2025 |
| Waste heat recovery end state | Closer to 300 MW | FY28 |
| Year-end cash position | Closer to Rs. 10,000 crores after Penna and CAPEX outflows | End of FY25 |
| Demand growth | 7%-9% industry growth to ~45 crore tons | FY25 |
| Post-monsoon price recovery | Prices to follow normal trajectory as demand-supply matches more in Dec and Mar quarters | Post-Diwali |
Key Metrics
| Metric | Q1 FY25 |
|---|---|
| Revenue | ₹8,311 cr, consolidated YoY |
| EBITDA | ₹1,280 cr, margin of 15.4% |
| EBITDA per ton | ₹807 |
| Cost per ton | ₹4,437, decline of 3% YoY |
| Power and fuel cost per ton | ₹1,304, decreased 13% YoY from ₹1,501 |
| Logistics cost per ton | ₹1,323, reduced 8% YoY from ₹1,436 |
| Cement and clinker volume growth | 3% YoY, consolidated Ambuja level |
| Cement standalone volume growth | ~1% YoY |
| Blended cement mix | 86% of total sales volumes |
| Premium products share | 24% of trade volume, up 200 bps |
| Kiln-fuel cost | ₹1.73 per 1000 kilocal, reduced 17% from 208 paisa |
| Secondary lead distance | 46 km, reduced by 9 km YoY |
| Direct dispatches | 55% of total, up 4 ppt |
| WHRS share in power mix | 15.1%, up from 11.5% YoY |
| AFR share in fuel mix | 9.3%, up from 7% YoY |
| Consolidated cash and cash equivalents | ₹18,299 cr as on 30th June |
| Operating cement capacity | 8.9 crore tons, post Penna acquisition |
| FY25 cement demand growth outlook | 7% to 9%, to around 45 crore tons |
| FY25 government capex outlay | ₹11.11 lakh cr, 3.4% of GDP |
| Full year CAPEX target | ~₹10,000 cr, growth and maintenance |
| Green power investment outlay | ~₹6,000 cr for 1,000 MW RE initiative |
| Cost reduction target | ₹500–₹550 per ton from FY24 base of ₹4,184 |
| Sequential price decline | 6.5% |
| YoY price decline | ~6%–7% |