Key Takeaways
- Weak underlying quarter masked by incentives: Adjusted EBITDA per ton was just INR 537, a sharp sequential drop driven by shutdowns at four large plants, consolidation of high-cost acquired assets, and inventory drawdown.
- The cost-reduction story is intact but back-end loaded: Management reiterated its INR 3,650/ton cost target by FY28, a ~INR 1,000 swing from current levels, but the largest savings from captive coal mines and full green power will only materialize in later years.
- Acquired assets are a near-term drag with a long-term promise: Sanghi and Penna are running at sub-40% utilization with higher cost structures, depressing consolidated margins; management expects Sanghi to hit 80-85% utilization by March end after repairs.
- The growth engine is running hot: Volumes grew 17% YoY, with traditional Ambuja/ACC utilization at ~80% and new capacity growing at 11%; the company is pacing to hit 10.4 crore tons capacity by Q4 FY25 and 14 crore tons by FY28.
- What to watch next quarter: Whether Sanghi utilization actually reaches 80-85% as promised, the pace of cost reduction from Khavda solar and WHRS, and whether December-January price increases hold in a depressed South market.
Cost Leadership Roadmap
- The INR 3,650 target is an average, not a floor: Some plants will be lower, some higher; hill plants have structurally different cost profiles due to hill transport rates, while Penna plants near big cities could end up very low cost.
- Power cost is the biggest lever: 60% of power requirements for the planned 14 crore tons will come through green power, rising to 83% on clinkerisation, reducing power cost by around INR 100 per ton by FY28.
- Captive coal mines are the endgame: Management expects captive coal to drop fuel cost by INR 0.30-0.40 per kilocal and take the company out of day-to-day auction premiums, but this benefit comes only when mines are operational over the next couple of years.
- Logistics savings are structural and phased: Lead distance reduction of ~100 km, BCFC rakes (5 delivered, 4 more by March 25), and GPWIS rakes (11 running) will deliver another INR 100 in logistics savings around 2026-27.
- The cost walk is back-end loaded: About INR 100 reduction next year, another INR 150 the following year, with the large part of cost reduction coming towards the end when coal mines start contributing.
Ajay Kapur: "I would continue to believe that in the next 5 years, Adani Cement would not just be the lowest cost in India, but perhaps it will compete with the lowest cost in China, which is the world, first part."
Acquired Assets: The Margin Overhang
- Sanghi is still in repair mode: Utilization at 37% because one kiln has been optimized and shut down, the second kiln is under major repairs, and one power plant is also under full repairs; management expects 80-85% utilization by March end after completing this maintenance.
- Penna and Sanghi were under-invested: Both assets lack waste heat recovery, alternate fuels, and other efficiency infrastructure that Ambuja's legacy plants already have; investments are now being ordered and executed.
- The consolidation math hurts near-term margins: These assets carry higher cost structures and are running at sub-40% and sub-50% utilization; full efficiency requires 80-85% operation, and the ramp-up path depresses consolidated EBITDA per ton.
- Management expects 10-15% cost reduction for both Penna and Sanghi after efficiency initiatives are completed.
- South market mix adds realization pressure: South markets are largely OPC-led B2B segments where market prices are depressed; even though Ambuja and ACC sell at the highest end, the market itself is weak, and some volume has gone into B2B where realizations are lower.
Ajay Kapur: "So, in the market, the growth is coming in, however, at a slightly lower pace. But I'm very confident that with all these repairs and maintenance, which was very much needed, I think by March end, these assets should start delivering almost 80%, 85% utilization."
Volume Growth & Capacity Expansion
- Growth is outpacing the industry: Traditional Ambuja/ACC utilization at ~80% (vs 76% YoY), growing ~7% against industry ~5%; new capacity growing at 11%; overall 17% volume growth includes Sanghi and Penna volumes.
- The capacity pipeline is fully loaded: Bhatapara clinker unit and associated grinding units (Sankrail, Farakka, Sindri) to be commissioned by Q4 FY25; Salai Banwa in Q1 FY26; Bathinda and Marwar in Q2 FY26; Kalamboli, Dahej, Jodhpur Penna, Krishnapatnam in Q3 FY26; Maratha clinker and Warsaliganj grinding by end FY26, taking capacity to 11.8 crore tons.
- 14 additional grinding units have been identified with land acquisitions and statutory approvals under process, enabling the 14 crore ton target by FY28.
- Orient acquisition is at an advanced stage: Post-completion, operating capacity will rise to 9.7 crore tons; total capacity by Q4 FY25 to hit 10.4 crore tons.
- Organic growth becomes the driver from Q4 onwards: The company expects to hit 100-plus million tons in the March quarter, followed by 11.8 crore tons by end FY26.
Incentives: A Structural Part of the Model
- Incentives are material and recurring: Management describes them as "part and parcel" of the business, with every investment entitled to incentives; the large incentive bucket of INR 4,500 crores is being resolved and cash flows are returning to the balance sheet.
- The run-rate is INR 600-650 crores per year, with an additional ~INR 500 crores per year expected on top from expanded capacity, to be received over the next 7-9 years.
- Sequential decline was a one-time effect: The prior quarter included a one-time Sankrail incentive of ~INR 130-135 crores; removing incentives, pricing is roughly flat sequentially.
- Adjusted EBITDA reveals the operational picture: Without the incentive benefit, EBITDA per ton was only INR 537, a significant sequential drop driven by shutdown costs, acquired asset consolidation, and inventory drawdown.
Vinod Bahety: "Incentives are very much part and parcel of this business. And with every investment which is being made is entitled for incentives."
Operational Efficiency & Sustainability
- Energy costs declined 7% YoY: Kiln fuel costs reduced by 10% to INR 1.66 per 1,000 kilocal; power and fuel costs decreased 7% to INR 1,262 per ton, driven by better fuel mix and green power share rising to 21.5% from 15.8%.
- Logistics costs declined 6% YoY to INR 1,239 per ton on footprint optimization; overall lead distance reduced by 4 km to 285 km; direct dispatch to customers increased by 700 bps to 57%.
- Khavda solar is now fully online: The 200 MW solar project in Gujarat was commissioned in Q3 and reached full potential in the last week of January; full effect will be seen in Q4 and improve further in Q1 next year.
- WHRS capacity has grown nearly 5x from 40 MW at takeover to 197 MW, targeting 218 MW by March 2025; the entire waste heat program will be completed in the next 12 months.
- The alternate fuel journey will be completed in the next 24 months; 0.48 crore tons of waste-derived resources were used in Q3.
Market & Pricing Environment
- Industry demand is recovering: Cement demand expected to grow 4-5% in FY25, with H2 much better than H1 after tepid 1.5-2% growth in H1, supported by pro-infra and housing budget in 2025.
- Prices increased in December and January, but the South market remains depressed due to its OPC-led B2B structure; even premium players face realization pressure there.
- Premium products are gaining share: Premium products as a percentage of trade sales volume increased by 400 bps to 26%, now nearing 27%.
- Blended cements at 82% of the portfolio, supported by the micro-market management strategy and dealer network expansion.
- Management declined to quantify industry capacity additions for FY26-27, instead arguing that responsible capacity addition by the private sector prevents consumers from paying much higher prices.
Ajay Kapur: "The question is if the industry does not responsibly add new capacity today, which is totally private sector investments today and totally based on free competition, consumers will end up paying prices which will be much, much higher."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capacity expansion | Reach 10.4 crore tons total capacity | Q4 FY25 |
| Bhatapara clinker & grinding units | 4 MT clinker unit + Sankrail, Farakka, Sindri grinding units commissioned | Q4 FY25 |
| Salai Banwa grinding unit | Commissioned | Q1 FY26 |
| Bathinda & Marwar grinding expansion | Brownfield expansion commissioned | Q2 FY26 |
| Kalamboli, Dahej, Jodhpur Penna, Krishnapatnam | All four grinding units commissioned | Q3 FY26 |
| Maratha clinker & Warsaliganj grinding | 0.4 crore ton clinker unit + grinding unit commissioned, taking capacity to 11.8 crore tons | End FY26 |
| 14 additional grinding units | Enable 14 crore tons capacity | FY28 |
| WHRS capacity | Increase to 218 MW | March 2025 |
| RE commissioning | 1,000 MW renewable energy commissioned | FY26 (full plan by June 2026) |
| Sanghi utilization | Reach 80-85% utilization after repairs | March 2025 |
| Cost reduction target | Reach INR 3,650 per ton | FY28 |
| Power cost reduction | Reduce by ~INR 100 per ton via green power | FY28 |
| Penna/Sanghi cost reduction | 10-15% reduction in cost per ton after initiatives | No fixed date |
| Captive coal mines | Operational, reducing fuel cost by INR 0.30-0.40 per kilocal | Next couple of years |
| Logistics cost savings | Additional INR 100 per ton | Around 2026-27 |
| Full-year capex | ~INR 9,000 crores (revised from INR 8,000 crores) | FY25 |
| Incentive realization | INR 4,500 crores bucket + ~INR 500 crores/year additional | Next 7-9 years |
| Merger of Penna, Adani Cementation, Sanghi | Consummated | Next financial year (regulatory approval stage) |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Revenue | ₹9,329 cr (consolidated quarterly) |
| EBITDA | ₹1,712 cr, margin of 18.4% |
| EBITDA per ton | ₹1,038 |
| Operational cost per ton | ₹4,618 |
| Power and fuel cost per ton | ₹1,262, down 7% YoY from ₹1,355 |
| Kiln fuel cost | ₹1.66 per 1,000 kilocal, down 10% from ₹1.84 |
| Logistics cost per ton | ₹1,239, down 6% YoY from ₹1,322 |
| Volume growth | 17% YoY (consolidated) |
| Sanghi cement utilization | 37%, up from 22% YoY and 23% QoQ |
| Premium products share of trade sales | 26%, up 400 bps YoY |
| Blended cements share | 82% |
| Green power share in power mix | 21.5%, up from 15.8% YoY |
| Direct dispatch to customers | 57%, up 700 bps YoY |
| Primary lead distance | 265 km, down from 268 km YoY |
| Cash and cash equivalents | ₹8,755 cr as on December 31 |
| Net worth | ~₹63,000 cr, up from ~₹51,000 cr in April |
| WHRS capacity | 197 MW, targeting 218 MW by March 2025 |
| Ready-mix plants | 100, after commissioning 8 new plants in Q3 |