Cost Leadership & Margin Expansion

Ajay Kapur: "I highlighted the pillars of that journey. And I'm 110 percent confident that that journey will be made before time."

Capacity Expansion & Capital Allocation

Ajay Kapur: "Three locations, one in West, one in North and one in South, 0.4 crore, 3 kilns we are ready to place orders as soon as we have the EC. And this is not so far in distant future. I'm talking of only a quarter or two at the most."

Sanghi Integration & Turnaround


Market Position & Volume Growth

Ajay Kapur: "That is an area which keeps us a little away from day to day commodity wars. But yes as more capacity comes in and if the sentiment is a little down it can have an impact on..."

Logistics & Fuel Strategy

Ajay Kapur: "We are part of an ecosystem, a platform called Adani, where we have some of the smartest guys who are running coal mines, who understand coal."

ESG & Operational Efficiency


Guidance & Commitments

CommitmentSpecificsTimeline
Capacity exitExit FY25 with almost 8.6 crore tons of cement capacityFY25 end
Bhattapara clinker facility0.4 crore tons clinkering, 0.48 crore tons cement commissionedQ4 FY25
Sankarel and Farakka grinding unitsBoth units commissionedQ3 FY25
Maratha Chandrapur clinker lineClinker line commissionedQ2 FY26
Three new kiln lines (West, North, South)Orders placed for 0.4 crore tons eachWithin 1-2 quarters of receiving EC
Sanghi kilnsBoth kilns running flat out at 100%H2 FY25
Sanghi clinker volumeMinimum 0.5 crore tons clinker from SanghiFY25
Captive coal coverage80-90% of coal requirement from captive sourcesWithin 12 months
Renewable energy capacity1,000 MW commissioned, 60% of power from green sourcesFY26
WHRS capacity186 MW commissionedMarch 2025
Cost reductionINR530/ton further reduction from FY24 baselineBy FY28
Power costReduction from ~INR6.75/unit to ~INR4.50/unitOver 5 years
End-state cost per tonINR3,650 per tonBy FY28 (management confident of beating timeline)
Market share20% market share through organic expansionNo date (linked to 14 crore ton capacity)
Grinding units35 new grinding units commissionedBy FY28
Clinker capacity8.2 crore tonsBy FY28
Sea freight share~10% of logisticsWithin 24 months
Net zeroAmbuja and ACC net zeroBy 2050
Tree planting0.83 crore trees plantedBy 2030

Key Metrics

MetricQ4 FY24
Consolidated revenue₹8,894 cr, up 12% YoY
Full-year FY24 revenue₹33,160 cr, up 7% YoY
EBITDA₹1,699 cr, up 37% YoY
EBITDA per ton₹1,026, up 17% YoY
EBITDA margin19.1%, expanded 3.5 ppt YoY
Full-year FY24 EBITDA₹6,400 cr, up 73% YoY
Full-year FY24 EBITDA margin19.3%, expanded 7.4 ppt YoY
Full-year FY24 PAT (Ambuja)₹4,738 cr, highest ever
Operational cost per ton₹4,345, down 9% YoY
Power and fuel cost per ton₹1,219, down 13% YoY from ₹1,404
Kiln-in-fuel cost₹1.84 per 1000 kcal, down 17% from ₹2.21
Logistics cost per ton₹1,280, down 8% YoY from ₹1,389
Consolidated cash and cash equivalents₹24,338 cr (including ₹8,339 cr warrant proceeds received in April)
Net worth~₹60,000 cr (including warrant proceeds)
Total grinding capacity7.89 cr tons (post Tuticorin acquisition)
Master Supply Agreement volume0.34 cr tons, up 42% from 0.24 cr tons
Sanghi MSA volume to Ambuja4.2 lakh tons
Sanghi MSA volume to ACC2.5 lakh tons
Sanghi clinker production0.07 cr tons (Q4); kiln 2 non-operational
Sanghi cement production0.08 cr tons (Q4)
Sanghi EBITDA margin20.5% (Q4); included ~₹33 cr of one-off provision write-backs
Blended cement mix of total sales86%
Premium products as a percentage of trade sales24%
Share of AFR in fuel mix10.6%, improved from 8.7%
Share of WHRS in power mix13.5%, improved from 9%
WHRS capacity134 MW currently; targeting 186 MW by March '25
Secondary lead distance48 km, reduced by 4 km
Direct dispatch to customers54%
Volume growth (Q4)~17%, ahead of industry growth
FY25 exit capacity target~8.6 cr tons
FY28 clinker capacity target8.2 cr tons
FY28 cost reduction target₹530 per ton further reduction
End-state cost target₹3,650 per ton
Power cost₹6.75 per unit currently; targeting ~₹4.50 over next 5 years
Captive coal mine coverage target50% of current requirement from three mines; 80-90% within 12 months
Limestone reserves780 cr tons total
Rail coefficient~27%
Sea freight share target~10% within 24 months
Channel partnersOver 1 lakh