Demand Environment & Market Tailwinds

Udai Singh: "I wish I could have answered you this with certainty, but we are hopeful. We are hopeful for the infusion, which is being done by the private sector and also by the government sector in terms of really infusing and putting up capital."

Order Book & Key Wins


Financial Performance

Omkar Prasad: "This quarter, I have to tell you that this is the first time a quarter we crossed INR1,000 crores. It's a stellar performance that in 1 quarter, we are crossing INR1,000 crores."

Product & Technology

Udai Singh: "These are embedded with sensors, which are really state-of-the-art and can give you the entire health of the asset. Also those type of healths, which were conventionally in the past was never available."

Margin Outlook & Risks

Udai Singh: "we are trying to see as to in this geopolitical situation, in this absolutely volatile raw material scenario, in the growing demand, which is challenging capacities of manufacturer, number one, how do we pick the right contract? Number two, how do we execute it profitably, mitigating the risk and volatility of raw material which those contracts might offer."

Capital Allocation & Disclosures


Guidance & Commitments

CommitmentSpecificsTimeline
Order execution focusContinued focus on more efficient order execution and profitabilityOngoing
Government capexNext-year capex slated at INR12.2 lakh crores, 11% higherFY27 Union Budget
Renewable target500 GW target5 years out
Data center IT load growthFrom 1.7 GW to at least 4x, reaching 7–8 GW5 years
EV penetrationTarget of 30%, currently approximately 8%Not specified
Digital economy GDP shareExpected to reach 20% of GDP, currently 12–13%By 2030
Urbanization rate41% urbanizationBy 2030
High-speed rail corridors7 corridors covering approximately 4,000 km, INR16,000 crores investmentNot specified
Dedicated freight corridor2,000 km connecting Dankuni to SuratNot specified
Indian Semiconductor Mission 2.0Additional INR1,000 crores allocatedBudgeted
Dividend decisionNecessary steps to be taken to the Board; update promised "in coming time"Undated
Capex disclosureApproved budget to be publicly announced per SEBI norms; update in March balance sheetMarch balance sheet

Key Metrics

MetricQ3 FY26
Revenue₹1,000+ cr, +20%+ YoY; first quarter crossing ₹1,000 cr
9M revenue~₹2,300 cr, +12.3% YoY
Q3 order booking₹909 cr, +60% YoY
9M order booking₹2,657 cr, +37% YoY
Order backlog₹1,700 cr, +50%+ YoY
Q3 profitability before exceptional items₹155 cr, ~15% YoY growth
9M profitability before exceptional items₹281 cr, +8.2% YoY
Exceptional item (9M)₹25 cr one-time gratuity impact from labor code change
Exports share (9M)11% to 12% of sales
Data center orders share~10% of order inflows to date
E-House / CSS / PSS market size~₹1,400 cr in India (management estimate)