Key Takeaways


The Demand-Supply Asymmetry

Sagar Agrawal: "There is no issue with orders today; there is a shortage of supply in the market. The thermal power plants want to buy 2 lakh metric tons per day, but they are getting only 20,000 metric tons per day."

Raw Material: The Binding Constraint

Sagar Agrawal: "Even now, in Haryana and Punjab, raw material collection has been happening for the last 10 years, yet 80% of the raw material is being burned. And in the whole of India, 100% of raw material is being burned."

The Torrefaction Opportunity

Sagar Agrawal: "We have broken the network of four or five people in the supply chain and given an end-to-end solution to the plants. So our competition level has decreased completely, and we are able to get long-term orders from those plants 3 year and 5 year orders."

Financial Model & Efficiency

MetricValueContext
Revenue (FY26)INR202 crore+25% YoY
EBITDA (FY26)INR16 crore+39% YoY; H2 EBITDA +58% YoY
PAT (FY26)INR11 crore+37% YoY; 5.5% margin
ROE26.8%Capital-effective business model
ROCE35.9%Lean balance sheet
Cash conversion cycle59 daysDisrupted by extended rainy season
Capacity utilization80%450 MT/day plant; constrained by raw material availability

Capacity Expansion & Geographic Rollout


Risks & Fragilities

Sagar Agrawal: "The risk is if farming stops in India, then agro-waste will decrease, so our raw material will be short; that is a very big risk for us. Otherwise, agro-waste is available all over India, it is burning everywhere, so we just have to collect it from the farm."

Guidance & Commitments

CommitmentSpecificsTimeline
RevenueINR350 crore top lineFY27
RevenueINR500+ crore top lineFY28
CapacityFive new plants, expanding from 450 to 1,000 MT/dayFY27
CapexINR15-20 croreFY27
Capex funding planPublic disclosure of funding approachWithin the week
Karnataka operationsStart operationsPossibly next month
Torrefaction R&D plantCommission 40-ton plantJuly/August 2026
Torrefaction commercial productionBegin commercial outputApproximately six months
Raw material costBring under INR2 per kgNo date
Co-firing adoption150 power plants to test, 70-80 to begin daily biomass useThis year
Market shareGrow from 5% to 30% of biomass blending systemNo date
Cash flow normalizationAchieve neutrality once 1,000-ton plant runs and sales beginWhen 1,000-ton capacity reached

Key Metrics

MetricFY26
Revenue from operations₹202 crore, growth of 25%
EBITDA₹16 crore, up 39%
H2 FY26 EBITDA₹10 crore, up 58% YoY vs H2 FY25
PAT₹11 crore, growth of approximately 37% from ₹8 crore in FY25
PAT margin5.5%
H2 FY26 PAT₹7 crore, 69% growth over H2 FY25
FY27 top-line target~₹350 crore
FY28 top-line target₹500+ crore
Manufacturing capacity450 metric tons per day
Capacity utilization80%
Target capacity post capex1,000 metric tons per day
FY27 planned capex₹15 crore to ₹20 crore
FY26 capex deployed₹4 crore
Cash conversion cycle59 days, inventory days 19, debtor days 69, payable days 27
Return on Equity26.8%
Return on Capital Employed35.9%
Revenue split: private sector60% of total revenue
Revenue split: power plants40% of total revenue
Market share in thermal power plant supply5% to 8%
Torrefied product realization improvementfrom ₹7 per kg to ₹12 per kg, approximately 71% price increase
Raw material cost reductionfrom ₹3 per kg to ₹2 per kg via VLE network optimization
Biomass fuel cost advantage vs fossil fuel70% to 80% cheaper currently, was 30% cheaper before geopolitical disruption
Government subsidy recovery on plant cost30% to 40%
Torrefaction margin premium vs non-torrefied pelletsmore than double or triple
Total biomass fuel demandapproximately 5 lakh metric tons per day
Thermal power plant sector demand2 lakh metric tons per day
Current thermal power plant biomass procurement20,000 metric tons per day against demand of 2 lakh metric tons per day
Power plants that have completed co-fire testing72 out of 280 power plants in India
Power plants currently using biomass30
FY27 target: power plants to complete co-fire tests150
FY27 target: power plants to start day-to-day biomass use70 to 80
Co-firing mandate in NCR region7% in FY27, up from 5% last year
Co-firing mandate target by FY3030%
Current co-firing utilization against mandate0.2% of capacity
Plant setup timeapproximately 3 months
MNC customer portfoliomore than 450 companies
Fuel price volatility rangeup to 5%
Torrefaction R&D plant capacity40 tons
Torrefaction commercial production timelineapproximately 6 months