Solex Energy Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/zilxxgjvttqu8f2pnim0apdg.pdf

Key Takeaways


The Q2 Hit: Utilization, Supply Chain and a Strategic Shipping Call

Chetan Shah: "We planned certain shipments with $900 to $1,000 per container and then we ended up paying $3,500 per container and we did that because we wanted to stand by with our commitment of delivery to our customer rather than, I mean sometimes losing customer is something which is more harmful than the paying higher cost for the shipping cost, so that was a strategic call that we took."

Cell Line: The December 2027 Anchor

Chetan Shah: "The real journey starts 1 year down the line and then there will be enough capacity available in India, and which will definitely give the correct picture of this industry."

BESS: High Volume, Not High Margin

Chetan Shah: "I don't see any chance of very high percentage of margins for BESS, but yes, it will be very high on our revenue and of course, the rupees, profitability also in terms of that."

Policy, DCR and the ALMM Overhang


Export Markets and US Manufacturing Ambition


Product and Technology Updates


Industry Structure and Competitive Positioning

Chetan Shah: "We are not in hurry. Sometimes, we are taking all our steps very cautiously and carefully so that our investors' money is secure and it helps to grow."

Guidance & Commitments

CommitmentSpecificsTimeline
Revenue and margin recoveryRecover revenue, EBITDA margin and PAT margin from current levels using existing order bookWithin 4.5 months
Cell line ground-breakingLand, pollution and EC clearances resolved; equipment and service providers alignedAnnouncement very soon
Cell line production startTOPCon cell line operationalDecember 2027
BESS assembly line startTotal capex INR250 croresSeptember 2027
FY29 financial guidanceRevenue ~INR4,000 crores; EBITDA margin 23–24%; PAT margin 12–14%FY29
Tapi RQ commercial launchCertification complete, production line upgraded, product launched for Indian marketOnce certification ready
DCR capacity adequacySufficient domestic DCR capacity available, prices come downWithin 6 months
US market focusRe-engage US export market; study US manufacturing feasibilityExport focus now; manufacturing study ongoing, no date
BESS consultant deliverablesDocumentation and EPRL prepared; orders placedWithin a couple of months
Fundraising approachRaise structured debt (CCD) to protect timelines; convert to equity once valuation improvesOngoing; CCD term sheet signed, documentation in progress

Key Metrics

MetricQ2 FY27
Revenue₹1,600+ cr in FY26, with ~6–6.5% PAT margin; Q2 FY27 absolute figure not stated
EBITDA margin11%, improved from 7–8% in prior periods (per an analyst's math)
PAT margin~6–6.5% in FY26; Q2 FY27 impacted by industry challenges, management expects recovery
Other expenses₹14.6 cr, down from ₹30 cr QoQ due to lower production and fixed cost absorption
FY29 revenue guidance~₹4,000 cr, with EBITDA margin of 23–24% and PAT margin of 12–14%
FY29 EBITDA margin guidance23–24%, driven by backward integration into cell manufacturing
FY29 PAT margin guidance12–14%, conservative estimate post cell line commissioning
TOPCon cell line capex₹500–600 cr per GW, including land and building with good technology machines
Cell line commissioning timelineDecember 2027, on track after resolving land and environmental clearance issues
BESS assembly line capex₹250 cr, with target start by September 2027
BESS assembly line timelineSeptember 2027, documentation and EPRL preparation underway
MOU with Gujarat government₹4,000 cr for 5 GW solar cell and 10 GW BESS assembly
Near-term capex (Phase 1)₹4,500 cr, part of $1 billion 2030 vision, MOU signed with Gujarat government
Longer-term investment roadmap beyond 2030₹12,500 cr (per an analyst's math)
Module supply to Welspun and Zelestra200 MW, supplied under Solex brand with LONGi arrangement, not OEM
Warranty coverage30-odd years, insured by Munich Re with premium being paid
Shipping cost overrun$3,500 per container paid vs planned $900–$1,000 per container, absorbed strategically
India module nameplate capacity230 GW as per ALCM list, with average utilization of 50%
TOPCon capacity in India~75–80 GW, after removing 35 GW Mono PERC and 7–8 GW HJT/thin-film
India TOPCon module demand (FY26)~60 GW supplied, consumed against 50 GW of solar projects
Grandfathered projects allowed to import cells~30 GW, providing sufficient non-DCR business for module manufacturers
DCR cell availabilityShortage of quality DCR cells against demand; majority of FY27 supply will be non-DCR modules
CCD proposed for cell line subsidiary₹50 cr, term sheet signed, documentation in progress
Historical revenue reference₹608 cr revenue when market cap was much higher than current levels