Key Takeaways
- Margin inflection ahead, not yet in the numbers: EBITDA margin improved YoY to 9.8% but the real step-up waits on Q3/Q4, when newly secured high-margin orders begin contributing materially to revenue after design approvals.
- BESS is a credible second engine, not a slideware story: The Supa plant is under construction, first product is due by end-Q1 FY27, and management is already bidding BESS EPC with a pipeline of INR 5,000 crore this year, targeting a 50:50 revenue mix with water by 2030.
- The order book is converting, just slowly: INR 1,438 crore won in Rajasthan, with INR 1,125 crore of L1 awards expected in Q3 (possible spillover to Q4); management does not recall any case where an L1 was not awarded.
- Arbitration awards are a material, multi-year cash catalyst: INR 647 crore in awards (including interest) is expected to repay the remaining NARCL debt, with a further INR 1,500 crore of award visibility over the next two years, though realization timelines stretch four to five years.
- What to watch next quarter: Whether the three L1 awards convert to orders, the pace of new-project revenue ramp in Q3, and any update on BESS product certification and first customer orders.
Margin Trajectory: The Mix Shift
- Legacy drag nearly done: Roughly INR 1,600 crore of old, low-margin orders remain in the book and are gradually completing; their dilutive effect fades as new orders take over the revenue mix.
- New orders structurally more profitable: Orders from Konar, Jharkhand, MP, Rajasthan and Chennai all carry margins above 10%, and design drawing approvals (aided by the monsoon period) are substantially complete, clearing the path for revenue recognition.
- Sequential ramp expected: Management expects profit margin to keep increasing from Q3 to Q4 to Q1 next year as the new-order share grows; old projects continue at the same level in Q3 while new projects begin contributing, with quarterly turnover benchmarked at roughly one-twelfth of total project cost.
- Selective bidding enforced: The company will not take any EPC business below 10% margin, and contract clauses must include pass-through provisions; projects must also be fully funded and in states where execution is comfortable.
Digga: "In taking the order, because that criteria, we have made it out that if it is a fully funded project, it is a project which is our desire and support we have with our supplier and customer, which is a profit more than 10%, where the contract clause is having the pass-through..."
BESS: The Second Engine
Manufacturing & timeline
- Supa plant on track: Phase I (2.5 GWh) at Pune MIDC is in advanced construction with ground works started, targeting commissioning by Q1 FY27; Phase II follows by FY28.
- First product by end-Q1: First FAT is scheduled for January, with SAT at the Supa site planned for April; end-to-end testing and validation fits within that three-month window.
- Speed to deploy: At two containers per day manufacturing capacity, a 100 MW order can begin delivery within two months and commission in 45 to 60 days, implying three to four months from order to commissioning.
- Capitalization treatment: All BESS expenses until commencement of commercial production will be capitalized, not charged to the P&L; segmental profitability will be disclosed separately.
Technology & sourcing
- Energy Vault partnership: The JV partner has granted SPML a licensing agreement under IP ownership to use its systems design on the SPML trademark for Indian and global markets, covering EMS, electrical architecture, thermal management and safety IP for entire BESS containers.
- Cell sourcing: Cells will be imported from China or Indonesia; only cells and PCS need importing, with the rest localized within Pune.
- Technology shift underway: LFP cell concepts, especially 314Ah cells, are entering the Indian segment; 5.015 MW DC block systems are anticipated to launch.
Market opportunity & positioning
- Thermal BESS is a game changer: BESS tenders were previously only for renewable energy, but thermal power tenders have now started, which management expects will multiply BESS volume and requirements manifold.
- Already bidding, ahead of demand: The company is participating in a INR 5,000 crore BESS pipeline this year and expects to have its own battery pack unit ready by the time orders materialize; customer demand is expected mid-next year (June to August), while SPML will be ready by March or April.
- End-to-end integrator model: SPML positions itself as a one-stop turnkey solution provider, doing EPC using its own batteries rather than just assembling or reselling.
- 50:50 ambition: Internal target is for BESS and water/power turnover to reach 50:50 by 2029 or 2030, up from water at roughly 90% today; historically water and power was 75:25, now 90:10, with power including BESS.
- Margin uplift from manufacturing: Once the assembly line is operational, revenue should increase by a further 4% to 5% and margin by 4% to 5%, taking the target margin with battery pack manufacturing to 14% to 15% as EPC.
Patel: "SPML's entire model is to do an end-to-end turnkey integration. So, we will be one-stop solution provider for the clients."
Order Book & Pipeline
- Recent wins: New projects secured individually and through JVs in water infrastructure totaling over INR 3,772 crore across Jharkhand, Madhya Pradesh, Rajasthan and Tamil Nadu.
- Rajasthan award: INR 1,438 crore won since the last meeting; two further Rajasthan awards (Pratapgarh, INR 700 crore) are still pending.
- L1 pipeline: Three L1 awards worth INR 1,125 crore expected in Q3 FY26, with possible spillover to Q4; one additional L1 received in Chennai. Management does not recall any case where an L1 was not eventually awarded.
- FY26 order book target: INR 5,000 crore of new orders targeted for the current fiscal, with a higher target next year; growing opportunities across all three sectors are expected to help exceed this level.
- H2 revenue visibility: Sizable turnover expected in Q3 and Q4 from three projects: Rajasthan (INR 385 crore), Jharkhand (INR 650 crore) and Indore (INR 1,036 crore).
- Execution cadence: Average three to six months for design drawing approval after order receipt; average project completion in two to three and a half years, with orders executed proportionately at roughly one-twelfth per quarter.
- Water side target: Every year the target on the water side is INR 5,000 crore of orders, to be executed over three and a half years.
Arbitration Awards: The Hidden Balance Sheet
- Award stock: INR 647 crore in arbitration awards (including interest up to October 2025) is expected to repay the remaining INR 400 crore NARCL debt (including interest).
- Further visibility: Management sees an additional INR 1,500 crore of awards becoming due in the next two years.
- Historical conversion rate: Roughly 41% of claim value has historically converted into award.
- Realization timeline: From claim to arbitration award normally takes two to three years; from award to cash realization normally takes four to five years as customers can challenge in various forums.
- Settlement acceleration possible: Courts now require a 75% deposit if a customer wants to challenge an award; the government's Vivad Se Vishwas scheme allows settlement at 65%; settlement discussions have already started for some awards at the court level, which could accelerate realization.
Digga: "huge changes has come into the arbitration claim and award settlement. Lot of timeline has been decided by the government of India. Lot of stringent rules and regulations they have made into that. So, I hope the settlement will become much, much faster and the resolution will become much faster."
Balance Sheet & Capital Structure
- Bank facility enhancement: Sanctioned bank facilities enhanced from INR 205 crore to INR 505 crore by a leading public sector bank.
- Surety bond approved: Approval received from a leading insurance company, providing additional bidding flexibility.
- ICRA rating: Company recognized as a 'Stable' firm by ICRA for its entire financial and banking facilities.
- NARCL allotment: Preferential allotment to NARCL to maintain their holding at roughly 12.5% on expanded capital; warrants to be converted early.
- Warrant inflows: Roughly INR 150 crore expected from warrant conversions between now and March, coming every month.
- Working capital: A strong network of empaneled, credible suppliers and contractors supports effective working capital management, reflected proportionately in quarterly debtor and creditor levels.
- Unanswered: An analyst asked about the promoter group's source of funds for INR 125 crore in warrants; the transcript shows no response to this query.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| New order intake | INR 5,000 crore target for current fiscal | FY26 |
| L1 award conversion | INR 1,125 crore of L1 tenders awarded | Q3 FY26, possible spillover to Q4 |
| BESS Phase I commissioning | 2.5 GWh facility at Supa, Pune | Q1 FY27 |
| First BESS product ready | End-to-end testing and validation complete | End of Q1 FY27 |
| Revenue expectation | More than INR 850-900 crore this year | FY26 |
| Margin floor (EPC) | No business taken below 10% margin, water and power including BESS | Ongoing |
| Margin target (with manufacturing) | 14% to 15% as EPC once battery pack assembly line operational | When assembly line is ready |
| Revenue mix target | BESS and water/power turnover at 50:50 | By 2029 or 2030 |
| NARCL debt repayment | Remaining INR 400 crore (including interest) repaid via INR 647 crore arbitration awards | As awards are realized (four to five year timeline) |
| Power substation order | At least one order expected | This financial year |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue | ₹199 cr, marginally up 2% YoY |
| EBITDA | ₹20 cr |
| EBITDA margin | 10.0% |
| PAT | ₹15 cr |
| PAT margin | 7.7% |
| H1 FY26 revenue | ₹363 cr |
| H1 FY26 EBITDA margin | 9.8% |
| H1 FY26 PAT margin | 7.6% |
| Order book (existing) | ~₹1,600 cr |
| New orders secured (H1 FY26) | >₹3,772 cr across Jharkhand, MP, Rajasthan, Tamil Nadu |
| L1 position | ~₹1,125 cr, expected award in FY26 |
| Targeted new order inflow (FY26) | ₹5,000 cr |
| Sanctioned bank facilities | ₹505 cr, enhanced from ₹205 cr |
| Arbitration awards | ~₹645 cr (including interest up to Oct 2025) |
| BESS Phase I capacity | 2.5 GWh, commissioning targeted Q1 FY27 |