Key Takeaways
- Subdued H1, confident H2 ramp: Volumes were hit by elections and severe Assam floods, but October grew 12%+ YoY and management guided 12–13% YoY volume growth for both Q3 and Q4.
- Fuel cost advantage holds: Blended power cost stayed at ₹1.52/unit while peers face ₹2+; a 3-month coal stock and resumed FSA deliveries insulate Star from the industry-wide coal price panic.
- Nimbol is the unlock: Environmental clearance is imminent, groundbreaking is set for 1 December 2026, and the 0.6 Cr ton clinker-plus-grinding expansion targets commissioning by July–August 2028.
- Northeast pricing power intact: A ₹10/bag October price hike in the Northeast is expected to sustain, and management sees no margin pressure for at least two years until new competitor capacities come online.
- What to watch next quarter: Whether the Q3 double-digit volume growth materializes, the pace of Siliguri grinding unit decision-making, and any movement on the Jhajjar land aggregation that gates that project.
Volume & Demand Recovery
- H1 was a washout: Elections disrupted Q1, and Q2 lost ~1.5 months to monsoon with Assam and Nagaland completely flooded; Manipur political unrest caused ~25% de-growth in those markets, dragging overall Northeast growth.
- October inflection: Volume growth crossed 12% YoY in October, giving management confidence to guide 12–13% YoY growth in both Q3 and Q4, with the full-year FY27 cement volume growth target of ~7–8% intact.
- Northeast demand tailwind: Industry growth in the Northeast is expected at 7–8% in H2; Star Cement expects to outgrow the market with double-digit growth because of headroom and available capacity, while West Bengal should grow in the higher teens.
- Outside cement dynamics: 15–16% of Northeast market is supplied by outside players (Chhattisgarh, West Bengal) via rakes on consignment; these inflows increase when margins are good and stop when conditions harden, especially in the off-season, acting as a natural buffer.
Tushar Bhajanka: "We do expect double-digit growth in the second half, in terms of volume."
Fuel Cost & Margin Resilience
- Coal cost insulation: Blended power cost held at ₹1.52/unit in Q2, down from ₹1.55 in Q1, because the company maintains ~3 months of coal stock, avoiding the panic buying that is pushing industry fuel prices toward ₹2+.
- FSA delivery normalization: Coal India deliveries resumed in November after zero rakes in September–October; ~5 rakes received and 4–5 more expected in November, with ~60 rakes still pending from past FSAs. Management expects coal price panic to reduce in the next 3 months as pending FSAs deliver.
- Fuel cost trajectory: Q3 and Q4 fuel cost broadly maintainable at ~₹1.5/unit, with a year-end target of ₹1.45 by March; rainy season limited AFR availability in Q2, so a gradual decline is expected as conditions improve.
- Margin visibility: Management sees no margin pressure for the next two years until new competitor capacities come online; after that, some rationalization is expected but the market is growing ~0.15 crore tons/year and 15–16% outside supply will reduce, leaving dominance with incumbents.
Tushar Bhajanka: "All of them are projecting fuel price of more than INR2. But because our book stock is good, I do not think we will have to face that kind of a fuel price increase."
Pricing & Competitive Dynamics
- Northeast pricing strength: October saw a ~₹10/bag increase in the Northeast, expected to sustain; outside Northeast (West Bengal), a ~₹10–15/bag increase was achieved but the trend is a bit weak and stabilization needs watching.
- Trade share dominance: 77% trade share in Q2, among the highest in mainland India companies; most Northeast sales happen through the trade network, giving pricing leverage that new entrants will struggle to replicate quickly.
- New entrants are years away: Ambuja, JK Lakshmi, and Shree Cement have announced Northeast entries, but terrain and rain constraints (4–5 months no construction) mean 2–3 years to build plants; JK Lakshmi and Ambuja have announced, while Shree Cement has no groundbreaking yet and its timeline is unclear.
- The margin vs. volume thesis: Management argues new entrants are attracted by margins, not volume, and everyone enters to earn money; short-term pricing pressure is possible but long-term pricing should stabilize because "the money in Northeast is not in asset turnover; it is in margin."
Tushar Bhajanka: "The money in Northeast is not in asset turnover; it is in margin. I think everyone understands that. So I do think that the pricing may be a short-term pressure, but I think in the long term, the pricing should stabilize."
Expansion Pipeline
Nimbol (Maharashtra) — the flagship
- Status: EAC meeting successful, minutes received, environmental clearance to be granted in a week or two; groundbreaking planned from 1 December.
- Scale and timeline: 0.6 Cr tons (clinker + grinding) expected online by July–August 2028 (Q2 FY29); capex expected within ₹3,000 Cr as previously showcased.
- Incentive choice: Capital investment subsidy chosen over SGST reimbursement, judged better on present value and cash flow basis.
Siliguri (West Bengal) grinding unit
- Status: Environmental clearance already applied for, adjacent to the current plant; decision to be taken in Q3 or Q4.
- Economics: SGST benefit makes it lucrative because existing volumes in Siliguri mean the benefit accrues from the first year.
Jhajjar (North India) clinker plant
- Status: ~50 acres aggregated so far, more land needed; clarity expected in ~1 month; EC application pending full land aggregation.
- Timing: Both Nimbol and Jhajjar clinker plants to come online within 1–2 months of each other; grinding units may come slightly before clinkerization, broadly in the same quarter, targeting 18–24 months from groundbreaking.
Umrangso (Northeast) clinker plant
- Status: Standard ToRs for EC received; EC expected in 2–3 months; plant land already acquired; in-principle decision taken to build.
- Readiness posture: Civil activities being sorted so the plant can be built in 18 months whenever demand triggers the go-ahead; the company has clinker sufficiency for the next 3.5 years in the Northeast, so Umrangso timing is demand-contingent.
Bihar grinding unit
- Status: Earlier plot had a dispute; a new plot is being identified; if found in 2–3 months, the company will buy, apply for permissions, and keep ready for future; Bihar is deferred once Siliguri is built.
Jorhat (Assam) land acquisition
- Status: Land being acquired for a future grinding unit.
Capacity roadmap
- ~1.8 crore tons in ~2 years (0.6 crore tons North + 0.2 crore tons Siliguri/Bihar); crossing 2 crore tons by 2030–2031 with Jorhat grinding unit and Umrangso.
Operational Levers & Non-Cement
- Silchar railway siding: Expected operational by January 2027; cost savings in fly ash and operations to follow from Q4 FY27.
- Clinker sales strategy shift: 126,000 tons of clinker sold in H1 to smaller non-branded grinding units that do not directly compete with Star Cement; from Q3 onwards, clinker prices increased to sell selectively and improve realization, so tonnage may reduce but margins may increase.
- RMC expansion: One RMC opened in Siliguri, one in Guwahati; one planned in Gujarat; North India RMC plan being acted on, with activities possibly starting in 4–5 months on a contract model to serve the market before own production launches.
- Non-cement revenue: Full-year target of ~₹100 Cr maintained.
Tushar Bhajanka: "You see that from Q3 onwards, the tonnage may reduce, but the margins may increase in clinker sales."
Balance Sheet & Capital Allocation
- Capex guidance: Broadly in line with Q1 presentation numbers; any revision will be in the updated investor presentation; numbers should only go down as optimization continues.
- Capex flexibility: FY28 estimate of ₹1,910 crores is flexible; can shift to FY29 or FY30 via 2-year buyer's credit on imported machinery.
- QIP not planned: Markets have corrected significantly; management does not think this is the right time; expansion is manageable through debt and internal accruals.
- Net debt to EBITDA: Not expected to cross 1.5x.
- H2 FY27 incentive: Expected ₹65–70 Cr, reflecting the revised Assam incentive policy (remaining 20 years compressed to 12 years) that increased subsidy accrual in Q2.
Tushar Bhajanka: "I think the markets have also corrected significantly. I do not think this is the right time anyway for the company to do QIP."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| H2 FY27 volume growth | 12–13% YoY volume growth in Q3 and Q4 | Q3 and Q4 FY27 |
| Full-year FY27 cement volume growth | ~7–8% YoY | FY27 |
| Fuel cost | Maintain ~₹1.5/unit in Q3/Q4; ₹1.45/unit by year-end | March 2027 |
| Silchar railway siding | Operational, cost savings to follow | January 2027 (Q4 FY27) |
| Nimbol groundbreaking | Construction start | 1 December 2026 |
| Nimbol commissioning | 0.6 Cr tons clinker + grinding online | July–August 2028 (Q2 FY29) |
| Nimbol capex | Within ₹3,000 Cr | By Q2 FY29 |
| Siliguri grinding unit decision | Go/no-go decision | Q3 or Q4 FY27 |
| Umrangso EC | Environmental clearance receipt | 2–3 months |
| Full-year non-cement revenue | ~₹100 Cr | FY27 |
| Full-year EBITDA | Guidance reiterated as achievable | FY27 |
| Net debt to EBITDA | Not to exceed 1.5x | Ongoing |
| Capacity | ~1.8 crore tons | ~2 years |
| Capacity | Cross 2 crore tons | 2030–2031 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue | ₹831 Cr, vs ₹811 Cr YoY |
| EBITDA | ₹164 Cr, vs ₹194 Cr YoY |
| EBITDA per ton | ₹1,372, vs ₹1,651 YoY |
| PAT | ₹39.58 Cr, vs ₹71 Cr YoY |
| Cement sales volume | 11.23 lakh tons, vs 10.72 lakh tons YoY |
| Clinker sales volume | 0.74 lakh tons, vs 1.01 lakh tons YoY |
| Northeast cement sales volume | 7.96 lakh tons, vs 7.84 lakh tons YoY |
| Outside Northeast cement sales volume | 3.27 lakh tons, vs 2.88 lakh tons YoY |
| H2 FY27 volume growth guidance | 12–13% YoY |
| Trade share | 77% |
| Premium product share | 17.3% |
| Fuel cost per unit | ₹1.52, vs ₹1.55 in Q1 FY27 |
| Green power share | 28% |
| Lead distance | 208 km |
| Clinker factor | 68.6 |
| Incentive booked | ₹36 Cr; H2 FY27 expected ₹65–70 Cr |
| Non-cement revenue | ₹22 Cr; full-year target ~₹100 Cr |
| H1 FY27 capex incurred | ₹203 Cr |