Sterlite Technologies Ltd Q3 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/avtag07x9k9nfczu9gcpq79i.pdf

Key Takeaways


Optical Networking: Margins, Mix & the BEAD Catalyst

Ankit Agarwal: "we do expect that H2 of this calendar year, and definitely probably our Q2-Q3 kind of time frame is where we expect initial BEAD investments to pick up, and hence our fiber optic solutions to be starting to be required for that. But really, we expect that the larger and more significant demand will come from a CY26 perspective"

North America: The Three-Driver Demand Thesis

Ankit Agarwal: "this broadly should lead to demand in North America going from current base of 7-8 crore fiber kilometers to north of 12 crore fiber kilometers annually. So, this will be a plus in our view, that should partially play out in 2025 and then certainly 2026 onwards."

Global Services & Digital: Selective Growth, Demerger Progress


Data Center Portfolio: A 1-2 Year Build with Immediate Disclosure

Ankit Agarwal: "this will take some period of time, probably over the next 1-2 years. We will continue to build the portfolio, build our own IP and in parallel continue our conversations"

Margin Mechanics & the Path Back to 20%

Tushar Shroff: "If we have to go back to the 20% in terms of an EBITDA margin, we need to be at a capacity utilization about 70-75% that is a kind of a capacity utilization that will yield about 20% in terms of an EBITDA margin for optical network business."

Guidance & Commitments

CommitmentSpecificsTimeline
BEAD-driven demandInitial BEAD investments to pick up, driving fiber optic solution requirementsH2 CY25 (Q2-Q3 FY26)
BEAD larger demandMore significant demand from BEAD programCY26 (Q3-Q4 FY26)
Services business demergerFinal NCLT approval and listing of resulting companyQ1 FY26
Data center portfolioBuild comprehensive product suite with own IPNext 1-2 years
Optical EBITDA margin recoveryReturn to 20% EBITDA margin, requiring 70-75% capacity utilizationAs markets improve in coming year
BharatNet Jammu & KashmirAdvanced purchase order; formal purchase orders; work commencementWeeks (APO); end-Q4/early Q1 (formal PO); Q1 (work start)
Finance cost reductionDecline in finance costsEspecially from Q1 FY26
Data center plus enterprise disclosureCall out percentage of optical revenue from this segmentStarting Q3 FY25

Key Metrics

MetricQ3 FY25
Consolidated revenue₹1,261 cr, decline QoQ attributable to lower OFC volumes and lower GS business revenue
Consolidated EBITDA₹133 cr, margin at 10.5%
Consolidated PATLoss of ₹23 cr, narrowing on YoY basis
Optical networking revenue₹924 cr, healthy improvement on YoY basis
Optical networking EBITDA₹119 cr, margin at 12.9%, substantial improvement YoY driven by cost leadership
Global services revenue₹289 cr
Global services EBITDA₹20 cr, margin at 6.8%, improved YoY and QoQ despite revenue reduction
STL digital revenue₹77 cr, healthy improvement on QoQ basis
STL digital EBITDA₹4 cr, first EBITDA positive quarter
Open order book₹9,050 cr, well diversified across customer segments and business verticals
Net debt₹2,195 cr
Data center and enterprise revenue share22% of optical networking business revenue
Optical cable market share ex-China8% globally during Q3 FY25
Optical connectivity attach rateMore than 20% sustained for three consecutive quarters, approximately 20-22 cents of connectivity products for every $1 of cable sold
Optical networking capacity utilizationAround 50%, broadly flattish QoQ
9M FY25 revenue₹3,892 cr
9M FY25 EBITDA₹378 cr
9M FY25 PATLoss of ₹83 cr
STL digital open order book₹451 cr at end of quarter
BharatNet phase three project win₹2,600 cr in Jammu Kashmir
Optical networking capacity (glass and fiber)North of 5 crore fiber kilometers
Optical networking capacity (cable)North of 4.2 crore fiber kilometers
FY25 capex guidance₹120-130 cr maximum, largely maintenance capex and some interconnect investment
Realizations vs 2019 peakDown 20-30% depending on market
Finance cost 9M FY25₹238 cr, down from ₹281 cr in prior year period
Quarterly interest cost run rate₹83-84 cr, expected to come down further by Q1 FY26