Sterling & Wilson Renewable Energy Ltd Q1 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/l1u6o33pfcmsylfo0fa45hg0.pdf

Key Takeaways


Domestic EPC: The Turnaround Engine

Amit Jain: "So, there are two parts to it because the most of the like, in India is a BOS market and the modules are supplied by the developers. So, we are completely insulated from the module price risk. We do not undertake the land aggregation risk on any project in India."

Nigeria: The Binary Catalyst

Amit Jain: "Either they will be sourced from, most probably from U.S. only. And in USA market, the module prices more or less remains at the level at which we had considered in our bid. So bid value will not come down. It will stay at the values or the guidance which we have given to the market."

International EPC & Module Prices

Amit Jain: "The correction in the module prices will improve the EPC margins in the international markets. Because earlier, first of all, it will help us on two counts. The contract closure will be much faster, and more and more decisions will be taken due to the low module prices."

Order Book & Pipeline

SourceDetail
Q1 new ordersINR466 crores, driven by continuing domestic momentum
Serentica (repeat customer)319 MW DC project in Bikaner, Rajasthan
Amplus (repeat customer)72.5 MW DC project in Jhansi, UP
Nigeria MOUConversion to D&EPC agreement targeted by Q2 FY24; bid value and 10-12% margin guidance maintained
Domestic FY24 targetINR4,000-5,000 crores of orders
Combined target (ex-Nigeria)Close to USD 1 billion for domestic and international together
Hit rate expectationUpwards of 15%

Balance Sheet & Indemnity

Sandeep Mathew: "Also, just with respect to the equity raise, I think we are looking at all options, keeping all options open at this point of time. That would be the context with respect to, I guess that media article that you are referring to. So, yes, we are keeping all options open, but that does not imply that there is anything impending at this moment at least."

O&M and New Business Lines


Guidance & Commitments

CommitmentSpecificsTimeline
Nigeria D&EPC agreementConclude agreement at bid value and 10-12% margin guidanceEnd of Q2 FY24
Domestic order intakeINR4,000-5,000 croresFY24
Combined order intake (ex-Nigeria)Close to USD 1 billionFY24
Indemnity inflowsUpward of INR250 croresH2 FY24
Debt reductionSignificant reduction via receivables, indemnity, negative working capitalBy Q4 FY24
NTPC project completionBoth NTPC-1 and NTPC-2 completedH2 next year
Domestic EPC marginNormalized margins sustained for rest of yearFY24
Overhead rationalization impactResults visibleH2 FY24
Domestic EBITDA target10-11%Domestic market
India market share4-5 GW of 14-15 GW annual marketFY24

Key Metrics

MetricQ1 FY24
Revenue₹515 cr, improved substantially on a sequential basis aided by higher domestic EPC contribution
Consolidated gross margin11.3%, after 9 quarters of losses, aided by higher domestic EPC contribution
Domestic EPC margin13%, higher than average; FY23 was around 9.7%
Standalone operational EBITDABreak-even achieved in Q1
O&M revenue share9.2% of total revenue
New orders₹466 cr, aided by continuing ordering momentum in India
Unexecuted order book₹4,902 cr as of June 30, 2023, nearly 90% domestic EPC projects, executable over 12–18 months
Order inflow guidance (domestic)₹4,000 cr to ₹5,000 cr expected in FY24
Order inflow guidance (total ex-Nigeria)Close to USD 1 bn target for FY24, domestic and international combined
Domestic bid pipeline13–14 GW out of 22 GW total pipeline, 60% from India
Domestic hit rate18% to 20% in the addressed segment
Domestic order book (volume)~4 GW as of Q1
Net debt~₹2,100 cr as of June 30, 2023
Cash and cash equivalents~₹63 cr as of June 30, 2023
Core working capitalPositive ~₹140 cr; net working capital would be negative ₹402 cr excluding indemnity receivables
Indemnity crystallized~₹270 cr as of June 2023, expected to be paid by promoters in H2 FY24
Total indemnity amount in question~₹1,100 cr
Module price benchmarkNearly 18 cents per watt peak, around historic lows seen during pandemic
BloombergNEF global installation forecast344 GW for 2023, up from 316 GW projected in January 2023
India solar footprint60 GW+ in FY23, up from 3.7 GW in 2015
Nigeria project expected signingBy end of Q2 FY24; bulk of revenue expected in FY25 and FY26
Domestic EBITDA target10% to 11%