Key Takeaways
- Revenue nearly doubled YoY despite disruption: Consolidated revenue grew 93% YoY to INR1,762 crores even as projects in Rajasthan and Gujarat lost 40-45 days to cross-border conflict.
- Gross margin stepped up meaningfully: Consolidated gross margin improved to 11.7% from 10.1% in FY25, helped by softening input costs and a deliberate module-price renegotiation strategy.
- Order inflow stalled, but the pipeline is deep: Only one NTPC order was booked in Q1 as bidding was pushed out by ALMM II rules, ISTS waiver expiry and the border conflict; management still guides 20% order-book growth for the year.
- Balance-sheet repair is gaining momentum: A two-notch rating upgrade to BBB+, fresh bank sanctions of ~INR900 crores and surety bonds from three insurers are lowering LC/BG charges and widening the funding base.
- What to watch next quarter: Whether the 26 GW domestic pipeline starts converting before the December 2025 deadline, the pace of NTPC Khavda-2 module supply, and any resolution on ISTS waiver extension.
Revenue & Margin Performance
- Top-line growth despite disruption: Q1 revenue of INR1,762 crores was up 93% YoY, with all three segments (domestic EPC, international EPC, O&M) contributing. The sequential decline from Q4 is normal seasonality. Cross-border conflict disrupted Rajasthan and Gujarat sites for 40-45 days, but management did not quantify the rupee impact.
- Gross margin lift: Consolidated gross margin rose to 11.7% from FY25's 10.1%. Domestic EPC hit 10.8% (above the 10% target), international EPC held at 12.3% (steady-state), and O&M returned to 23% (recurring profile). Softening of key input costs helped.
- Module-price strategy, not pass-through: For turnkey orders that include modules, management renegotiated module prices downward by exploiting the time gap between order receipt and module placement. This was a deliberate business strategy that supported the bottom line, not an automatic back-to-back pass-through. The order has since been placed, so the company is protected if prices reverse.
- Other expenses: Other expenses rose because of a conservative INR21 crore impairment on receivables for one international project. Excluding that, recurring overheads were in line.
Thakur: "So basically, when we have got the project, it was ex-price of module suppose, right. And we have seen that we had cushion in the project schedule. And going forward, then we renegotiated the price of the modules. And the price that was fixed, I mean, have gone under change to take advantage of the existing market price. That was our business strategy and that has supported us to increase the bottom line."
Order Book & Pipeline
- Q1 inflow was near-empty: Only one order was won, a turnkey EPC solution with modules from NTPC, not including BESS. Bidding activity was pushed out by ALMM II cell requirements, ISTS waiver expiry, connectivity issues and the border conflict. Developers have applied for timeline relief, but no extension has been granted yet.
- Order-book composition is shifting: Last financial year, 25-30% of orders included modules. That trend is reversing because ALMM requirements mean most new tenders are expected as BoS schemes where developers handle modules themselves. Management gave no exact current percentage.
- The domestic pipeline is large and time-bound: Over 26 GW of domestic pipeline is expected to be awarded before December 2025. NTPC alone wants to reach 60 GW of renewables by 2032 (currently 6 GW operating, targeting 16 GW by 2030), backed by a government-approved INR20,000 crore investment this year and next.
- International target intact: The company is targeting $250-300 million in international orders, primarily in European and African markets. The Nigeria order faces a procedural delay; even if it materialises, revenue will not come this year because financial closure and NTP timelines are still pending.
- Hybrid and FDRE shift: The trend is moving toward FDRE schemes and hybrid projects. The company is in discussions with a few large private clients for hybrid orders (solar, wind, battery storage) but declined to name them.
Thakur: "So last call, if you can recall, so we are giving guidance to the market that we will be growing at 15% to 20% on a year-on-year basis. So for sure, I mean, what was achieved during last financial years, we will be doing better than the last ones at the rate of, say, 20% growth on the order booking."
Project Execution & Delays
- NTPC Khavda-1 nearly done: Only about 100 MW of module supply remains pending for Khavda-1.
- NTPC Khavda-2 delayed on modules: Around 200 MW of modules have been supplied, with the rest still underway. The monsoon is adding further delay. Strong notices for time extensions and claims have been submitted to NTPC.
- Customer-input delays are financially ring-fenced: Management stated that project finances are not impacted by delays caused by customer-supplied inputs.
Thakur: "So in any case, on our project finances because of delays on account of the customer input is not going to impact us."
Battery Storage & New Opportunities
- BESS revenue is tiny this year, meaningful next year: The company expects only around 500 MWh of battery storage revenue this financial year, described as miniscule. Meaningful revenue is expected from FY27 onward.
- Policy tailwind is forming: A new government scheme requires 20% of a solar plant's capacity to be supported with battery storage. Tenders are expected in Q2 and Q3. Management expects at least 10% of revenue streams to eventually come from battery and storage solutions.
- BESS project economics: Margins are expected to be the same as solar projects, but timelines are 15-20% shorter because civil works and complexity are lower. Battery BoS revenue is estimated at INR30-40 lakhs per MWh.
- Reliance pilot: One pilot project combining various technologies is doing well, with planning still underway for Kutch regions. Opportunities are not yet reflected in the market.
Thakur: "Margin would be same as the solar projects. And in terms of time lines, it will be lesser than the solar projects because the complexity involved here is less, the civil works requirement is less. So you can say, 15% to 20% less time lines and same margin."
Balance Sheet, Claims & Legacy Items
- Rating upgrade and fresh funding: A two-notch upgrade to BBB+ was received for working capital facilities and the term loan. Fresh sanctions of ~INR900 crores were obtained from three new banks, plus ~INR200 crores in surety bonds from three newly inducted insurance companies. The improved rating is already reducing LC and BG charges.
- Customer claims of INR800 crores: These claims (Note 7A and 7C) carry a small indemnified portion and a portion that is not indemnified. No impairment or provision has been made, based on legal advice and auditor agreement. The 7A claim is not indemnifiable; cash is already out, so an adverse order would hit the P&L but not cash flow.
- Receivables aging: Out of ~INR1,500 crores in total receivables, INR330 crores are more than six months old, primarily retention amounts. Management did not provide a further breakdown during the call.
- Legacy subsidiary losses: Losses from subsidiaries with no active projects (U.S., Australia, Dubai) are driven by overheads and legal expenses. South Africa, Spain and Italy subsidiaries are profitable.
- Legal expenses to persist: Legal costs are expected to continue at ~INR40 crores per year for at least 1.5 to 2 years, after which they should drop to zero. No substantial write-off is expected because most legacy receivables are indemnified and current receivables are all booked.
Singh: "Yes, at least 1.5, 2 years."
Competitive Landscape
- High but cyclical intensity: Many infrastructure players are entering solar EPC. Management described the pattern as cyclic: new entrants take one or two projects, struggle to execute, and then exit. The company expects competition to persist for some time.
- DCR deadline approaching: The DCR (Domestic Content Requirement) deadline is 1 June 2026. The existing order book has no DCR component; everything is on the international sale and module side.
Thakur: "I'm not sure how long and how best they can be continuing on, but then yes, it is cyclic. So sometimes you see that, I mean, there are only a few, but suddenly, you find so many people coming in, they take 1 or 2 projects, not able to execute, again they will exit."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Order inflow growth | 20% year-on-year growth on order booking | FY26 |
| Revenue growth | 20% year-on-year | FY26 |
| Q2 revenue | Similar or slightly better than Q1, with monsoon seasonality | Q2 FY26 |
| EBITDA margin | Operational EBITDA ~7%, overall EBITDA ~5.8%; maintain same range | Ongoing |
| Domestic pipeline conversion | Over 26 GW expected to be awarded | Before December 2025 |
| International order target | $250-300 million, primarily Europe and Africa | FY26 |
| BESS revenue | ~500 MWh (miniscule); meaningful revenue from next financial year | FY26 / FY27 onward |
| Legal expenses | ~INR40 crores per year, then drop to zero | 1.5-2 years |
| Additional bank lines | Hopeful to get ~INR1,500 crores in additional lines | This year |
Key Metrics
| Metric | Q1 FY26 |
|---|---|
| Revenue | ₹1,762 cr, +93% YoY; sequential decline due to seasonality |
| Gross margin | 11.7%, up from 10.1% in FY25; aided by softening of key input costs |
| Domestic EPC gross margin | 10.8%, above target range of 10% |
| International EPC gross margin | ~12.3%, reflective of steady-state margin profile |
| O&M margin | 23%, reflective of recurring margin profile |
| Operational EBITDA | ₹123 cr, 7% margin vs ₹25 cr in Q1 FY25 and ₹158 cr in Q4 FY25 |
| Reported EBITDA | ₹102 cr, 5.8% margin, up 175% YoY from ₹37 cr in Q1 FY25 |
| PAT | ₹39 cr, vs ₹5 cr in Q1 FY25 and ₹55 cr in Q4 FY25; higher tax expense due to standalone and international profitability |
| Unexecuted order book | ₹8,348 cr as of June 2025; over 88% domestic, international comprises 2 projects each in Europe and South Africa |
| O&M portfolio | 9.3 GW as of June 2025 |
| Bid pipeline | >30 GW, including >26 GW for India alone; majority expected to be awarded before December 2025 |
| Net debt increase | ~₹205 cr during the quarter; ₹200 cr disbursement from Bank of Maharashtra utilized in Q1 |
| Credit rating | BBB+, two-notch upgrade for working capital facilities and term loan |
| New banking sanctions | ~₹900 cr from 3 new banks, plus surety bonds of ~₹200 cr; hopeful for additional ~₹1,500 cr lines this year |
| Receivables impaired | ₹21 cr on a conservative basis for one international project |