Key Takeaways
- Revenue surged 70% YoY, but margin mix bit hard: Q2 revenue hit INR1,749 cr, yet gross margin fell sequentially to 8.9% as module-inclusive turnkey projects began revenue recognition, dragging operational EBITDA to INR62 cr.
- Legacy US claims forced a INR580 cr write-off: An adverse interim arbitration award on the Conti LLC case, plus two smaller US settlements, created a one-time non-cash exceptional charge that management frames as balance-sheet cleanup.
- The order book grew to INR9,300 cr with five new wins: Wins span domestic BoS, a large Khavda turnkey project, and a South Africa LOI; two L1 positions are already counted in the book.
- Credit lines are holding, but the rating overhang is real: INR2,000 cr in fresh sanctions and INR475 cr of new IREDA debt funded creditor paydowns; management insists PSU banks will not pull limits even if the rating slips.
- What to watch next quarter: Whether the ~INR178 cr promoter indemnity payment arrives by November 30, whether the two L1 positions convert to signed contracts, and whether gross margins recover as the module market stabilizes.
US Legacy Claims: The Conti Award and Balance-Sheet Cleanup
- The Conti arbitration produced the largest hit: The Arbitral Tribunal dismissed SWSS claims of USD5.51 cr and instead awarded USD0.64 cr to Conti, forcing a INR580 cr write-off of receivables that became unrecoverable.
- Two smaller US matters added to the quarter: A customer invoked an SBLC of USD0.72 cr, which the bank honoured and SWSS reimbursed; a mutual settlement with OEG Inc. closed a ~USD0.7 cr claim for USD0.23 cr, payable in two tranches by November 2025.
- The INR580 cr charge is non-cash: Management clarified the charge is a reversal of receivables, not a cash outflow; actual cash impact is only ~USD0.8-1 cr, though legal expenses and interest costs are yet to be finalized pending the final award.
- Standalone books took an additional INR2,638 cr in exceptional items: A INR600 cr loan write-off to the US subsidiary and a INR2,038 cr impairment provision on the Nigeria project were booked to align standalone net worth with consolidated.
- Corporate guarantee risk is contained, per management: One customer already invoked a bank guarantee and was paid; management stated there is no further risk of invocation on that amount, and net assets in the foreign subsidiary FZCO are recoverable.
- All legacy cases are disclosed and mostly indemnified: The Conti case was the largest not covered under indemnity; remaining cases are under arbitration or court, and consolidation has already occurred with no fresh legacy actions required.
Thakur: "While these are largely legacy project-related issues in our U.S. subsidiary, their resolutions, while financially painful in the short term represents a significant step towards cleaning up the balance sheet and enabling management to focus squarely on operational performance and profitable growth going forward."
Revenue Growth and the Margin Mix Shift
- Top-line growth stayed strong: Q2 revenue grew 70% YoY to INR1,749 cr, and H1 revenue reached INR3,510 cr, up 80% YoY, keeping the company on track with its ~20% full-year growth guidance.
- Gross margin compressed sequentially because of module scope: Q2 gross margin fell to 8.9% from 11.7% in Q1 as several large domestic turnkey projects that include module supply began revenue recognition; these carry higher revenue but lower margins than pure BoS projects.
- Operational EBITDA dipped on the same mix effect: INR62 cr in Q2 versus INR123 cr in Q1 and INR23 cr in Q2 FY25; the shift to module-inclusive projects mechanically lowers margin percentages even as absolute revenue rises.
- Recurring overheads edged up marginally: INR94 cr in Q2, driven by higher legal expenses tied to the legacy cases.
- H1 gross margin of 10.3% remains slightly above FY25's 10.1%: The full-year target range is 10-11% including O&M, and management expects module market stability to support better margins going forward.
Order Book and Pipeline
- Five new orders added since Q1, taking the order book to INR9,300 cr: Wins include a 304 MWp turnkey project in Khavda (INR818 cr), a 421 MWp BoS project from a large private IPP in Rajasthan (INR372 cr), two L1 BoS positions totalling INR760 cr for 943 MWp, and a 115 MW turnkey LOI in South Africa.
- The two L1 positions are already counted in the order book: Intimation of award has been received for projects in Uttar Pradesh and Rajasthan; detailed LOAs and contract signing are expected in 2-3 weeks.
- Order book composition is five projects: Four are domestic (one turnkey EPC including module supply) and one is international (completely turnkey with module supply); management did not provide a quantified split between module-inclusive and module-exclusive projects.
- The India pipeline remains deep: Nearly 25.2 GW of pipeline exists, with over 17 GW slated for ordering in H2 of this fiscal.
- South Africa is a focus market: Management is hopeful of concluding a few more projects there soon, building on the 115 MW LOI.
Nigeria, Reliance, and the Question of Delayed Projects
- The Nigeria project remains alive but procedurally stuck: An SPV has been formed and an agreement signed between Nigerian government utilities and Sterling and Wilson, but the timeline continues to slip; management acknowledged the project has been on the books for two years and "that is true" but insists it is not abandoned.
- The Reliance new energy project has no start date: Preliminaries work has started and module manufacturing has commenced at the Kutch site, but management said it is "difficult to say at this stage that when exactly project will start."
- On Reliance's strategy, management had no visibility: When asked whether Reliance plans to take up EPC on its own or whether a technical issue is causing delays, management said they are not sure about Reliance's strategy and that HJT technology, while costly domestically, should pick up pace with modules initially used for captive consumption.
Thakur: "That is true. So, the project is still not abandoned... And once contract agreement was signed up between Sterling and Wilson and the utilities. So then thereon, whatever time line was slated for, that is procedurally taking a little longer. That's the concern basically, but then the project is still on."
Balance Sheet, Credit Lines, and the Rating Question
- Gross borrowings rose to INR1,194 cr: A fresh INR475 cr IREDA term loan was drawn, pushing net debt to INR742 cr.
- The new debt funded creditor paydowns: Management used the IREDA facility to reduce creditor days and now has sufficient non-fund-based limits (bank guarantees, LCs) to access 180-day credit periods via LC issuance.
- Cumulative credit sanctions since the fiscal start total nearly INR2,000 cr: This includes surety bonds from five insurance companies totalling INR400-500 cr as an alternative credit option.
- Management does not expect PSU banks to withdraw limits even if the rating is downgraded: The argument is historical: PSU banks have not withdrawn limits in the past, and the company does not foresee a major issue in credit availability.
- No equity raise is planned: Management stated it is not planning to raise fresh equity at this point, having already raised debt.
- An investor noted that similar write-offs and undelivered promises occurred three years ago: The investor pointed out that the CEO who had laughed off war-impact concerns two quarters ago has since stepped down, and promises of a clean balance sheet were not kept. No management response was recorded.
Ajit Pratap Singh: "So as of now, we don't foresee any major issues in terms of availability of credit lines... even if the rating changes, we don't foresee any issue in withdrawal of existing credit lines, whatever we have, because these are from PSU banks."
O&M, BESS, and the Margin Recovery Path
- O&M margins remain healthy at over 20-23%: The segment is sustaining profitability, and management is hopeful of bagging a few large third-party O&M orders soon.
- Internal EPC projects nearing completion will feed the O&M portfolio: This is expected to drive a meaningful pickup in O&M revenues as projects transition from construction to operations.
- BESS and hybrid wind EPC are target adjacencies: Margins on BESS and hybrid projects are expected to be similar to solar, around 10%, and the company continues to target select projects in these segments.
- Operational EBITDA margin guidance is 4-6%: Management confirmed this range, with the dip in Q2 explained by the module mix effect and an expectation of stabilization as the module market remains steady.
- Module market stability is the margin linchpin: With module prices stable, management expects margins around the same level and not to decline further.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | ~20% YoY growth for the full year | FY26 |
| Operational EBITDA margin | 4% to 6% range | Ongoing |
| Gross margin including O&M | 10% to 11% range | FY26 |
| Promoter indemnity receipt | ~INR178 cr expected from SP Group and Mr. Khurshed Daruvala | By November 30, 2025 |
| OEG Inc. settlement payment | USD0.23 cr in two tranches | October and November 2025 |
| L1 position conversion | Two L1 positions (INR760 cr combined) to signed contracts | 2-3 weeks from call date |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue | ₹1,749 cr, +70% YoY |
| H1 FY26 revenue | ₹3,510 cr, +80% YoY |
| Gross margin | 8.9%, vs 11.7% in Q1 FY26 and 10.1% in FY25 |
| H1 FY26 gross margin | 10.3% |
| Operational EBITDA | ₹62 cr, vs ₹23 cr in Q2 FY25 and ₹123 cr in Q1 FY26 |
| Operational EBITDA margin guidance | 4% to 6% |
| Reported EBITDA | loss of ₹470 cr, after non-recurring expenses of over ₹637 cr |
| PAT | loss of ₹478 cr |
| Revenue growth guidance (FY26) | ~20%, maintained |
| Order inflow (FY26 to date) | ~₹3,775 cr, including ~₹3,000 cr since Q1 |
| Unexecuted order value | ₹9,287 cr, vs ₹9,096 cr as of March 2025 and ~₹8,348 cr as of June 2025 |
| O&M portfolio | 9.1 GW as of September 2025 |
| Gross borrowings | ₹1,194 cr, after fresh ₹475 cr term loan from IREDA |
| Cash and bank balances | ₹452 cr |
| Net debt | ₹742 cr |
| Indemnity claim raised on promoters | ~₹178 cr, expected by November 30, 2025 |
| Fresh credit lines sanctioned (FY26 to date) | ~₹2,000 cr, including surety bonds |
| Domestic order book share | 84% of current order book |
| India solar EPC pipeline | 25.2 GW, with over 17 GW slated for H2 FY26 ordering |
| Creditor days | 130 days, decreased |
| IREDA term loan cost | 11.15% |
| Unutilized non-fund-based limit | ~₹1,000 cr |
| Surety bonds from insurance companies | ₹400 cr to ₹500 cr |
| Standalone exceptional items | ₹2,638 cr, including ₹2,038 cr Nigeria impairment and ₹600 cr loan write-off |
| Conti LLC arbitration write-off | ₹580 cr, one-time non-cash impact |
| OEG Inc. settlement payment | ₹19.95 cr, one-time impact |
| SBLC invocation by US customer | ₹63.47 cr (USD0.72 cr), recovery sought through litigation |