Sterling & Wilson Renewable Energy Ltd Q4 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/j2sa50rukmj8viy7x8kacak7.pdf

Key Takeaways


Financial Performance

Ajit Pratap Singh: "Basically, it is the exposure of what we have as a standalone entity to our subsidiaries in Dubai. So the loans and advances given to them, that has been translated as on 31 March. And it is only a book entry, the moment this currency will get stabilized, this will get squared off and will come back."

Segment Margins & O&M


Order Pipeline & New Business

Chandra Kishore Thakur: "No such vendors in the country has that kind of capacity to, I mean, claim that he will be the only sole vendor - so it's not possible."

International Strategy

Chandra Kishore Thakur: "A lot of Tier 1 EPC players got into this market, and they are operating at a very lower margin. That is not our appetite."
Chandra Kishore Thakur: "Having burnt our finger in past, so we are very careful."

Execution Capacity & Financing


People & Organization


Guidance & Commitments

CommitmentSpecificsTimeline
Revenue growth FY2615% to 20% growth over FY25, excluding Reliance and NigeriaFY26
Order intake growth FY2615% to 20% growthFY26
O&M gross margin20% to 25% rangeGoing forward
Interest expense1.2% to 1.7% of revenueFY26
Indemnity receipt~₹850 croresDue September
Non-fund-based limit expansionAdditional limits from existing and new lendersQ1 before June, more in Q2
O&M revenue pick-upMeaningful pick-up from large EPC projects nearing completionH2 FY26
International order target₹1,000 crores to ₹2,000 crores from Africa and Europe (Iberia, Balkans)FY26
Nigeria financial closureSix to nine months after order signingPost order signing
NTPC commissioningOver 2 GW commissioned; 1.2 GW possible spilloverBefore/around June
DTA utilizationRemaining ~₹23 crores utilizedNext one to two years

Key Metrics

MetricQ4 FY25
Revenue₹2,519 cr, up ~114% YoY and 37% QoQ
Full-year revenue₹6,302 cr, up 108% YoY
Gross margin~10.4% (Q4), full year 10.1%
Domestic EPC gross margin~10% (full year), trended back to target range
International EPC gross margin~8% (full year), impacted by legacy projects
O&M gross margin~21% (full year), with ~₹4 cr write-off in Q4
Operational EBITDA₹158 cr, 6.3% margin, vs ~₹90 cr in Q3
Reported EBITDA₹116 cr, 4.6% margin, impacted by FOREX loss in March 2025
Profit before tax₹87 cr, up ~112% sequentially
Profit after tax₹55 cr, with non-cash deferred tax asset charge of ₹18 cr
Net debt₹178 cr at 31 March 2025, marginal increase of ₹3 cr QoQ
Unexecuted order valueover ₹9,096 cr, 84% domestic Indian projects
O&M portfolio8.7 GW as of March 2025
Revenue growth guidance15% to 20% for FY26 over FY25
Order intake growth guidance15% to 20% for FY26
Non-fund-based limit~₹4,500 cr, against appraised limit of ~₹10,000 cr
Interest expense guidance1.2% to 1.7% of revenue for FY26
International order inflow target₹1,000 cr to ₹2,000 cr for FY26
Indemnity expected~₹850 cr, due in September
Khavda order book concentration4-plus GW, mostly in advanced stage of execution
NTPC orderslightly over 3 GW, ~2 GW to be commissioned before June, 1.2 GW may spillover
JSW BESS order book value~₹234 cr to ₹250 cr
Deferred tax asset remaining~₹23 cr, expected to be utilized in next one to two years
FY25 solar capacity additions (India)nearly 24 GW, up from 15 GW in FY24, utility-scale contributed ~17 GW