Key Takeaways
- H1 FY23 surges, guidance held: Total income rose 30% YoY to ₹414 crore and PAT jumped 130% to ₹38.8 crore; full-year consolidated revenue guidance of ~₹890 crore and 30–31% gross margin are maintained.
- Order inflow momentum is strong: Order inflow grew 32% to ₹216 crore, with steam turbines, gas engines and aftermarket all tracking to record annual sales.
- Europe energy crisis opens a multi-year cycle: All-time high energy prices are making hydro and waste-to-energy plants very profitable, and the gas infrastructure replacement cycle is just beginning, with management expecting it to run at least 5 to 10 years.
- Turkey drag removed: Operations in Turkey will be suspended from 30 April 2023, cutting costs to a minimum while keeping the factory intact; the subsidiary was the only unprofitable one.
- What to watch next quarter: Whether the domestic sales dip reverses as postponed deliveries resume, the pace of gross margin recovery in Q3, and the outcome of the 9,000-horsepower railways tender expected by calendar year-end.
Revenue & Profitability
- H1 top-line growth: Manufacturing revenues rose 30% to ₹394 crore, driving total income to ₹414 crore; PAT more than doubled to ₹38.8 crore.
- Domestic sales dip is timing, not demand: Domestic sales fell ~7% YoY in the quarter due to delivery postponements; management sees no weakness in the underlying domestic market, which had very good order inflow and inquiry pipelines.
- Gross margin walk: A small sequential decline was attributed to product mix; management expects improvement in Q3 and reaffirmed the full-year 30–31% gross contribution guidance.
- Operating leverage is the margin engine: EBITDA margin expansion in H2 is driven mainly by operating leverage, with a smaller contribution from gross margin; employee expenses grow only 7–8% per year and other opex 5–6%, far below sales growth.
- Pricing power has peaked: Management does not expect to raise prices further now that raw material prices have stabilised; future improvement must come from cost reduction and operational leverage.
Nikhil Kumar: "I don't think that we will be able to increase the prices any further in the market at this point of time. So we will have to reduce the cost, and we will have to work on operational leverage."
Segment Performance
| Segment | Trend | Commentary |
|---|---|---|
| Steam Turbines | ▲ Record year | Strong demand from India and worldwide; highest sales ever this year; order book for next year very strong. |
| Gas Engines | ▲ Record year | Very good ordering forecast from Indian customers; highest sales in company history this year; significant growth forecast next year. |
| Aftermarket | ▲ Record year | Highest sales this year; repair business orders won; further expansion planned next year; projections to be disclosed from next earnings call. |
| Hydro | ▲ Filling up | Pending order book for next year almost equal to this year's sales; inquiries increased dramatically. |
| Two-Pole Motors | ▲ Revival | Market went from ~30 machines/year to zero, now at 5–8; three orders already won; ~₹50 cr revenue expected in FY '24; product now 100% indigenised, improving cost competitiveness vs BHEL. |
| Synchronous Motors | ▲ New growth | One order on hand, another closed; ~30% domestic market share achieved; ₹50 cr business expected next year, driven by large irrigation pumping stations. |
| Railways | ● Milestone | First six motors dispatched to Indian Railways; mounting on locomotives is the next step; six months of successful performance needed for full approval to bid on all tenders. |
| Nuclear | ● Early stage | Facility approved by NPCIL for specialty motors and emergency power generators; bidding for projects; steady business with very good margins expected, but no annual order size given. |
Nikhil Kumar: "These are mainly large pumping stations required for pumping the water out of rivers and into reservoirs. So this is for irrigation mainly."
Europe: The Multi-Year Energy Opportunity
- Crisis-driven demand: Energy prices at all-time highs in Europe due to gas prices make it very profitable to operate hydro and waste-to-energy plants supplying the grid; money is flowing into the segment.
- Structural shift, not a spike: Europe needs alternative energy to reduce gas dependence; replacing gas infrastructure that took 20–30 years to build will take at least 15 years for a partial replacement, putting the industry at the beginning of a 5-to-10-year cycle.
- Cost advantage compounding growth: TDPS benefits from lower production costs in India versus rising European costs, likely gaining market share, though management cannot quantify the split between market expansion and share gains.
- Competitive reality check: Siemens, ABB and other global brands remain the big competitors; TDPS must gradually take share by convincing customers, a process that will still take time because the company is not yet a global brand.
Nikhil Kumar: "The gas infrastructure in Europe has taken 20 years, 30 years to build. And replacing the gas infrastructure will... take at least 15 years to replace a part of it... So there's going to be, just in the beginning of the cycle, I think it will continue at least for five to 10 years. We're just in the beginning of it."
Railways: The Big Bet Taking Shape
- First motors shipped: The initial six motors have been dispatched to Indian Railways; mounting on locomotives is the immediate next step, after which six months of successful performance is required to reach the approval stage for bidding on all Indian Railways tenders.
- Near-term revenue potential: Management is optimistic about adding some direct Indian Railways revenues in Q3 or Q4 next year, contingent on the approval timeline.
- Tender pipeline is large: TDPS is executing 12,000-horsepower locomotive motors now; two more bids are in play: a 9,000-horsepower tender for 1,000 locomotives (opening in about a month, results expected by calendar year-end) and another 12,000-horsepower tender opening early next year; management hopes the customer brings both or at least one.
- Alstom impact quantified: A temporary reduction in Indian Railways locomotives produced by Alstom knocked out a big chunk of what could have been achieved above ₹800–820 crore this year; that revenue shifts to next year.
- Vande Bharat uncertainty: TDPS is in play for Vande Bharat motors but management is not 100% sure it will make them; the technology level is high and the customer may want to keep it in-house for high-speed trains.
Domestic Demand & Capacity
- Captive power is now non-negotiable: No greenfield or brownfield investment is being made in India without a captive power plant, driven by power shortages and volatile power prices; management believes this will hold for at least the next four to five years.
- India remains power-short: Management stated India is a power-shortage country and will continue to be so for a long time, underpinning sustained demand for generation equipment.
- Capacity expansion underway: Continuous investment is pushing capacity from ₹1,200–1,300 crore to ₹1,400 crore; management confirmed no capacity problem next year.
Nikhil Kumar: "Nobody right now is going to put a greenfield or brownfield investment without a captive power plant. Nobody. That's the situation in India today, and nobody can take such a decision for the risk, even for the next four to five years."
Turkey & Portfolio Clean-Up
- Operations suspended, not shut down: TDPS will suspend Turkey operations from 30 April 2023, cutting costs to zero or a minimum level while all assets and the factory remain intact; the decision follows insufficient business and deteriorating economic conditions, with an exchange loss already incurred.
- Decision deferred, not final: Management will wait six months to a year to see if market conditions improve before making the next decision; the operation has fewer than 10 employees.
- Subsidiary profitability: All subsidiaries will be profitable except TDPS Turkey, so the suspension removes the sole drag on consolidated subsidiary earnings.
Nikhil Kumar: "I mentioned the word suspend the operations, so that means we're going to basically cut our costs down to 0 or to a minimum level. All our assets are going to remain there. We're going to keep our factory over there and -- but we're not going to shut down. We're going to suspend the operations until we see better market conditions."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY23 consolidated revenue | ~₹890 crore | FY23 full year |
| FY23 manufacturing sales (India) | ₹805–820 crore | FY23 full year |
| FY23 gross contribution | 30% to 31% | FY23 full year |
| FY23 standalone EBITDA (incl. other income) | Around 16%, with H2 slightly above 16% | FY23 full year |
| Gross margin improvement | Improvement in Q3 "for sure" | Q3 FY23 |
| FY24 sales growth | 20% growth, with big upside potential | FY24 |
| FY24 EBITDA margin | Expansion driven by growth and operating leverage | FY24 |
| Two-pole motor revenue | ~₹50 crore | FY24 |
| Synchronous motor revenue | ₹50 crore | FY24 |
| Turkey operations | Suspended; wait 6–12 months to reassess | From 30 April 2023 |
| Railways direct revenue | Optimistic to add some revenue | Q3/Q4 next year |
| 9,000-horsepower tender result | Expected by end of calendar year | Calendar year-end |
| Aftermarket projections | Will start disclosing a number | From next earnings call |
Key Metrics
| Metric | Q2 FY23 |
|---|---|
| Total income (standalone, H1) | ₹414 cr, +30% YoY |
| Manufacturing revenue (H1) | ₹394 cr, +30% YoY |
| EBITDA margin (standalone, H1) | 15.89%, including other income |
| Profit after tax (H1) | ₹38.8 cr, +130% YoY |
| Consolidated order book | ₹1,408 cr |
| Cash position | ₹197 cr |
| Order inflow from direct and deemed exports (H1) | ₹216 cr, +32% YoY |
| FY23 manufacturing sales guidance (TDPS India) | ₹805 cr to ₹820 cr |
| FY23 gross contribution guidance | 30% to 31% |
| FY23 standalone EBITDA margin guidance | around 16%, with H2 slightly above 16% |
| FY24 revenue growth guidance | around 20%, with upside potential |
| Employee expenses (H1) | ₹46 cr, expected to grow 7% to 8% per year |
| Other expenses (H1) | ₹30 cr, expected to grow 5% to 6% per year |
| Interest income (H1) | ₹4 cr, not considered operational income |
| Synchronous motor expected revenue (FY24) | ₹50 cr from two orders |