Key Takeaways
- Guidance raised, FY28 seeded: FY27 revenue guidance lifted to ₹2,900–3,000 crore, and an initial FY28 guide of ₹3,400–3,500 crore was set with a "very high likelihood" of upward revision, anchored by over ₹1,200 crore of book-and-bill already in hand.
- Orders surged on structural demand: Q2 order inflow jumped 57% QoQ and ~70% YoY, driven by data centers, grid stabilization, basic power generation and renewables; 92% of H1 inflows were exports.
- Siemens Energy partnership is now live: Orders have started booking for two-pole generators on a build-to-print basis, construction is underway, and the plant is targeted for readiness by calendar Q1 2028 with 70–80% utilization by FY30.
- Margins expanded, with a plant-startup dip ahead: H1 standalone EBITDA margin rose to 20.02% from 18.42% YoY; management sees a sustainable 19–20% near term, a possible small drop when the new plant starts, then upside past 20% as utilization scales.
- What to watch next quarter: Whether the ₹725–750 crore quarterly revenue run rate materializes in Q3, the pace of Siemens Energy plant execution, and any incremental capacity decision for the sub-50/60 MW segment.
Demand Environment
- Four engines firing at once: Data centers, grid stabilization, basic power generation, and the renewables push are all in full force, with demand for power equipment described as going up "through the roof."
- Data center visibility runs deep: The company sees clear visibility on real projects and real demand up to around 2030, with turbine and engine customers reporting no slowing in production slots and bookings beyond 2030.
- Geographic breadth: Strong orders came from India (steel industries, 40–100 MW segment) and Europe (grid stabilization, waste-to-energy), while the U.S. data center build-out was framed as the only growth driver in that market. Management stated the U.S. data center build-out is the only growth driver for the U.S. market.
- Market access, not new demand, drove intake: Higher order booking reflects the company now being an accepted, known brand winning business in areas previously inaccessible, rather than a step-change in underlying demand.
- Waiting period still tight: The waiting period has not come down; OEM customer capacities come online in 2028–2029, and numbers are expected to rise from 2028 onwards.
Nikhil Kumar: "We see clear visibility on real projects and real demand up to around 2030, and we also see that there is no slowing down for production slots and bookings beyond 2030. This is what our turbine and engine customers have told us very clearly, that they are continuing to get strong production slots and bookings for beyond 2030."
Siemens Energy Partnership
- Orders have begun: The company has started booking orders from Siemens Energy for manufacturing and supply of two-pole generators on a build-to-print basis, working with the gas turbine group rather than the TI group.
- Plant construction in full swing: A Bhoomi Puja is scheduled for November 19, 2026; most major equipment has been ordered and the project is on track, with the absolute outer limit for readiness at June 2028 and an internal target of calendar Q1 2028.
- Ramp-up path: Production is planned to ramp in calendar 2028 after the plant is ready, reaching around 70–80% utilization by FY30.
- Margin implications: Once the new plant reaches 50–60% utilization, there is upside potential to push margins past 20%, though a small dip is possible when the plant first starts incurring costs before revenues.
Order Book & Pipeline
- FY28 already well-supported: More than ₹1,200 crore of book-and-bill is expected within FY28, with November–March inflows still to come, giving confidence in the initial ₹3,400–3,500 crore guide.
- OEM coordination is granular: The company talks to customers very closely on a monthly basis about capacities, planning, and execution for 2028, 2029, and 2030, with detailed forecasts in place for 2027–2029 even though orders are released closer to the execution cycle.
- Hydro segment turning material: The company received its largest-ever vertical hydro order and a horizontal run-of-river order, both for projects in Nepal, with a huge pipeline of inquiries and big orders already received in Q3; major markets are Nepal and Vietnam.
- Combined cycle optionality: Management believes regulation will eventually promote combined cycle for energy efficiency, creating another large scope of business growth, though it is not expected to happen immediately.
- Captive power for data centers: If regulation requires data centers to have their own captive power, it could mean almost double the capacity required for captive plus backup, a potential demand multiplier.
Capacity & Operating Leverage
- Existing assets being stretched: Activities traditionally done in-house continue to be done in-house at a much larger scale, with more automation and better technology, yielding operating leverage; how much further existing capacity can go remains an internal debate.
- Incremental capacity decision ahead: If customer forecasts for 2028/2029 materialize, the company may need to look at incremental capacity in 2029; how much and where is still to be discussed.
- Engine and turbine capacity coming: New engine and turbine capacity entering the market from 2028 onwards will drive generator numbers higher, supporting the growth trajectory.
- OEM scope expansion: Within the existing OEM base, the company is actively pursuing opportunities to look at other models, turbines, and engines, and to be a second or primary supplier.
Margins & Pricing
- H1 margin expansion: Standalone EBITDA margin expanded to 20.02% in H1 FY27 from 18.42% in H1 FY26, though no specific drivers were broken out beyond inclusion of other income and exclusion of exceptional/treasury items.
- Pricing is stable with protection: Pricing is not expected to go up drastically; price variation clauses with customers pass through raw material cost changes, protecting margins.
- Volume-driven revenue: The revenue increase was volume-driven; management declined to quantify any price hike component.
- Near-term margin band: Sustainable margin around 19% in the short term, between 19% and 20% over the next few quarters, with upside past 20% once the Siemens plant scales.
Nikhil Kumar: "Pricing is not going to go up drastically. Pricing will go up to the extent of the as per the price variation formulas that we have based on raw materials... So, our margins will be protected in the end of the day."
Strategy & Long-Term Ambition
- Billion-dollar top line in sight: Management feels a $1 billion top line is possible in the medium term, though no exact timeline was given; conservatively, 20–25% minimum yearly growth potential exists.
- Guidance philosophy is conservative: The company will only put out numbers that are achievable and will update with upside potential as visibility emerges; it will not give long-term or medium-term yearly guidance.
- Product development tied to legacy models: The company is primarily working on legacy models of OEM customers and is deeply plugged into upgrades to those models; none of our customers have developed exclusively new products for the market right now.
- Competitive positioning with OEMs: Being tied to one turbine OEM limits access to others, as the others are not going to come to a supplier linked to a rival.
Nikhil Kumar: "20%-25%. Conservatively."
Nikhil Kumar: "t's really important for us as an organization to deliver what we commit. When we put some numbers out there in the market, we put numbers that are achievable. We don't want to be in a situation where we start putting out numbers and then we have to go back on them."
Guidance & Commitments
| Comitment | Specifics | Timline |
|---|---|---|
| FY27 revenue | ₹2,900–3,000 crore, with H2 split equally at ₹725–750 crore per quarter | FY27 |
| FY28 initial revenue | ₹3,400–3,500 crore, with "very high likelihood" of upward revision | FY28 |
| FY28 order book coverage | Over ₹1,200 crore of book-and-bill already expected within FY28 | FY28 |
| Siemens plant readiness | Outer limit June 2028; internal target calendar Q1 2028 | Calendar 2028 |
| Siemens plant utilization | 70–80% utilization expected | FY30 |
| Near-term margin band | Sustainable around 19%, between 19% and 20% | Next few quarters |
| Margin upside trigger | Upside past 20% once Siemens plant reaches 50–60% utilization | After plant ramp |
| Incremental capacity decision | May need incremental capacity for sub-50/60 MW segment | 2029, if forecasts materialize |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Standalone total income (H1) | ₹1,455 cr, +91% YoY |
| Standalone EBITDA margin (H1) | 20.02%, vs 18.42% in H1 FY26; includes other income, excludes exceptional and treasury income |
| Standalone PAT and comprehensive income (H1) | ₹207.4 cr, +110% YoY |
| Consolidated total income (H1) | ₹1,486 cr, +78% YoY |
| Consolidated PAT (H1) | ₹209.6 cr, +89% YoY |
| Order inflow | ₹824 cr, +57% QoQ and ~70% YoY |
| Manufacturing segment order booking (H1) | ₹2,319 cr, comprising generators ₹2,088 cr, railway ₹170 cr, spares and aftermarket ₹16 cr, Turkey business ₹45 cr |
| Export share of H1 order inflows | 92% of H1 order inflows, domestic 8% |
| Pending order book | ~₹2,300 cr |
| Cash position | ₹419 cr, including customer advances and preferential share issue money |
| FY27 revenue guidance (revised) | ₹2,900 cr–₹3,000 cr |
| H2 FY27 quarterly revenue guidance | ₹725 cr–₹750 cr per quarter, equally distributed between Q3 and Q4 |
| FY28 initial revenue guidance | ₹3,400 cr–₹3,500 cr, with very high likelihood of upward revision |
| Sustainable EBITDA margin range | ~19%, with upside potential past 20% once new plant reaches 50%–60% utilization |
| Units sold in Q2 | ~400 units, vs ~320 units in Q1 |