Key Takeaways
- Supply chain choked revenue: Q1 revenue was severely constrained because component shortages left inventory imbalanced, preventing shipment of complete systems. The company could not convert its order backlog into billable shipments.
- Gross margins under pressure: Fixed-price rupee tenders locked in before two years of component cost inflation are squeezing margins, with no pass-through mechanism available. Margins were flat QoQ at a depressed level.
- The fix is operational, not market-driven: Tejas upgraded internal systems and processes to gain visibility into EMS suppliers’ second- and third-level component details, and to allocate scarce parts optimally across products. Results are expected from Q2 onwards.
- Confident full-year growth call despite Q1 miss: Management expects quarterly revenue to accelerate through the rest of FY23 and still feels confident of significant full-year growth, citing a 12-month order coverage and large tenders awaiting conversion.
- What to watch next quarter: Whether the process and system upgrades actually translate into higher shipment volumes, the pace of gross margin recovery, and the closure of BSNL 4G commercial discussions.
Supply Chain: The Bottleneck and the Fix
- Root cause was visibility, not just scarcity: Tejas relied on EMS partners for detailed supply-chain management and took care of A-class items, but B-class and C-class components, power components, clocks, analog parts, and certain programmable devices in a specific nanometer geometry, caused the slowdown. Global competitors went into n-th level of detail earlier and executed better.
- Internal allocation made it worse: Scarcely available components were not optimally allocated across different cards and products internally, so fewer complete systems shipped than the available parts could have supported.
- The three component categories causing grief: (1) Power components, clocks, and analog parts costing a few cents to a couple of dollars, now the highest lead-time category. (2) Certain programmable devices in a specific nanometer geometry in serious short supply because only one foundry in Taiwan manufactures them after a Korean company used its capacity internally. (3) Memories are easing off, and higher-value parts from captive foundries are easing as wafers are repurposed to higher-ASP chips.
- Systems and process upgrade completed: New tools, processes, and systems implemented in Q1 give complete visibility into all components ordered by EMS suppliers and their arrival status, and enable better internal allocation of scarce components. Results expected to be visible from Q2 onwards.
- EMS partner expansion: Signed up new EMS partners to scale manufacturing capacity in anticipation of a significantly larger revenue base.
- Revenue capacity is not the constraint: For the next four quarters, if half the components needed and all placed orders arrive, Tejas can meet all its revenue targets. EMS capacity, production box-build capacity, and cash for placing large orders are all in place. The only bottleneck is component availability.
Nayak: "If I were to kind of summarize something that Tejas could have done better which we did not in the past was really not just relying on the EMS suppliers to do all the detailed supply chain management. We took care of the A class items but the B class and C class are ones which I just mentioned are the ones which got us into a slower revenue rate and that is basically probably our global competitors early on and essentially went into NS level of details and tried to do a better job of executing than we did."
Margins: Pressure and the Path Out
- Fixed-price tenders locked in margin pain: Many deals were fixed-price rupee-denominated tenders with no opportunity to increase prices to customers, while component costs have risen continually over the past two years. Gross margins were almost at the same level as Q4 of last year.
- No standard pass-through exists: For international orders, there is no fixed rule or percentage for passing through cost escalation; it depends on the competitive situation with each customer.
- Margin blend should improve with international shipments: International orders carry better margins than Indian ones, so as the international backlog is decongested, the margin blend is expected to improve.
- Near-term pressure acknowledged: For a quarter or two, some margin pressure will persist until the supply chain eases off. The strategy is to grow larger revenues to absorb slightly lower gross margins and still achieve overall profitability.
- Management expects improvement through the year: Gross margins should start improving throughout the later part of this year.
Nayak: "we should have larger revenues to be able to absorb a slightly lower gross margins so that on an overall basis we can still be achieving profitability."
Order Book and Revenue Outlook
- Order inflow slowed, but timing-driven: Q1 order inflow was slightly lower than revenues, causing backlog to decline. Some large orders expected as purchase orders crossed the quarter boundary and could not come in. No order cancellations.
- Large tenders won, awaiting conversion: Won a few large multi-hundred crore tenders which are expected to convert into purchase orders in Q2.
- Twelve-month order coverage confirmed: The company has coverage for almost the next 12 months of revenues in terms of confirmed orders to suppliers.
- No accounts lost despite delivery challenges: No customer account or order has been lost due to supply-chain-driven delivery delays.
- Full-year growth confidence intact: Management expects to accelerate quarterly revenue growth during the rest of the financial year and, on an overall year basis, still feels confident of significant growth compared to last year.
- Revenue constraint was supply, not demand: Revenue growth was limited by the supply-chain situation; if all backlog could have been shipped, more orders could have been secured.
Wireless and BSNL: The Big Bet
- 4G proof of concept completed successfully: Trials in the BSNL network went well; the customer is satisfied with technical capabilities.
- Commercial discussions ongoing: Commercials are being worked out between the front-end system integrator and BSNL. Size and price are under discussion, with closure expected in Q2 FY23, after which better visibility on order and delivery timelines will emerge.
- 4G system ready for large-scale deployment: A robust, field-proven 4G system for large-scale deployments is expected to happen in the next 12 months.
- 5G radios and RAN on track: Expected to be qualified by customers by end of CY2022 and ready for commercial deployment in CY2023.
- 5G broadcast via Saankhya Labs: Working with an anchor customer; more applications of broadcast 5G across a larger set of operators around the world expected in the next 12 to 18 months. Saankhya Labs became a subsidiary effective July 1, 2022, and R&D integration has started.
- Wireless is in investment mode: The wireless business is still in investment mode, while the wireline business continues to grow healthily and profitably. R&D investments continued without slowing in Q1 despite weak revenue.
India and International: A Two-Speed Business
- India private segment growing strongly: Year-on-year growth of 21.5%, continuing to do well.
- International revenue down sharply: International revenue declined around 48% YoY.
- Home market opportunity seen as very large: Management sees a very large opportunity in India across customers and wants to ensure it does not miss out on scaling the business to achieve high economies of scale in the shortest possible time.
- International ramp-up expected with a lag: More investments are being made in direct-geography international sales; results are expected with a time gap of a couple of quarters. The US market strategy is being revamped to use a partnership approach with other group companies or OEMs for faster acceleration.
- One European shipment completed: Shipped to one European customer for a business won last quarter; no specific Tier-1 international opportunity where available material could be diverted for a win.
Strategic Positioning and the Tata Ecosystem
- Scale is existential: Management believes telecom equipment is an industry of scale; unless Tejas gets into the top-tier category among global players, it will not have the economies of scale to play very large.
- Non-linear growth strategy articulated: The plan is to expand the product portfolio into wireless 4G/5G, leverage the large home market via the Atmanirbhar focus and the BSNL 4G and 5G capex cycle, and use the Tata ecosystem for international markets. Signs are expected to be visible this year itself.
- Tata partnership ambition is large: As part of the Tata Group, the company has a clear strategy and has started executing on it. The vision and ambition are very large, and the partnership is meant to accelerate that.
- Cash deployed for growth: A large amount of cash, including Rs.712.5 Crores from Panatone’s warrant conversion, will be used for increasing R&D investments, scaling up the business, taking longer-term bets on supply chain and international sales, and acquisitions as opportunities arise. Cash position increased to Rs.1,739 Crores.
- Design-linked PLI scheme improves incentives: Tejas decided not to avail the incentive of last year and will start the five-year block from this year. The new scheme provides an additional 1% incentive and allows R&D manpower costs to be counted as capital investment, giving a bigger envelope for incremental sales revenues on which PLI incentive is earned. No artificial hard capex investments are planned; the asset-light model continues.
Nayak: "we believe that our industry in telecom equipment is an industry of scale. Unless we get into top tier category among the global players, we will not have the economies of scale to really be able to play very large"
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth acceleration | Accelerate quarterly revenue growth; significant full-year growth vs FY22 | Rest of FY23 |
| Gross margin improvement | Margins should start improving | Later part of FY23 |
| Supply-chain process results | Results of new tools, processes, and systems to be visible | From Q2 FY23 onwards |
| BSNL commercial closure | Commercial discussions to close, giving visibility on order and delivery timelines | Q2 FY23 |
| 5G radios/RAN qualification | Qualified by customers and ready for commercial deployment | Qualification by end CY2022; deployment CY2023 |
| Large tender conversion to purchase orders | Multi-hundred crore tenders won to convert into POs | Q2 FY23 |
| Inventory normalization | Inventory level should come down as inventory gets balanced out | As year progresses |
| International sales ramp-up | Results from increased direct-geography investments | Couple of quarters out |
| PLI incentive block start | Five-year block under new design-led scheme begins | FY23 |
Key Metrics
| Metric | Q1 FY23 |
|---|---|
| Net revenue | ₹126 cr, -12.8% YoY |
| PAT | -₹7 cr, loss vs profit in prior year |
| EBIT | -₹30.7 cr, YoY decline |
| PBT | -₹12.9 cr, negative |
| EPS | -₹0.45 |
| Cash and cash equivalents | ₹1,739 cr, up QoQ after ₹712.5 cr warrant conversion |
| Order book | ₹1,158 cr, down from ₹1,186 cr at end-Q4 |
| India private revenue growth | +21.5% YoY, 49% of total revenue |
| International revenue | -48% YoY, 31% of total revenue |
| India government revenue share | 20% of total revenue, YoY growth |
| Inventory | ₹322 cr, up ~₹35–40 cr QoQ due to imbalanced inventory |
| Receivables | ₹298 cr, with ₹141 cr collected during the quarter |
| Working capital increase | ₹47 cr, driven by higher inventory |
| Saankhya Labs stake acquired | 63.43%, effective July 1, 2022; no Q1 contribution |
| PLI scheme investment (earlier application) | ~₹105 cr commitment, eligible for up to 3.8 or 3.88 times incentive |