Trom Industries Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/19scad2153edttmysw1uihi5.pdf

Key Takeaways


Revenue & Execution


Margins & Cost Structure

Management: "So what happening very, very small company have entered in PM Surya Ghar and they are not maintaining their quality and people are from that residential side, they are only price conscious. So what happening to fight with them and waste our energy you can say, use our energy to get the residential 3 kilo total like 1 lakh or 2 lakh order, apart from that we are utilizing our staff to go investment government side because there is a ticket size more than INR1 crores."

Competitive Position & Growth Constraints

Management: "If you go and see the balance sheet and details, Oriana Power do the more than 60%, 70% trading business. So if we are going to start doing the trading of the modules and inverters, so we also get uh all the INR300 crores, INR400 crores premium. This is not a part of our company and we are not looking for any trading on the site."

Order Book & New Business


RESCO, Storage & Future Bets


Guidance & Commitments

CommitmentSpecificsTimeline
Order book executionINR30 crores definitely built and billedBefore March 30
Small order executionINR15–20 crores completedDecember
FY26 revenue targetINR120–130 crore (vs last year)FY26 full year
RESCO pipeline execution~27 MW builtWithin approximately one year
RESCO ROIInvestment recoveredWithin 4–5 years of execution
Margin sustainabilityImprovement expected every year; last year's drop was one-timeOngoing

Key Metrics

MetricQ2 FY26
Revenue (H1 FY26)₹40.73 cr, down ~12% YoY from ₹46.29 cr in H1 FY25
EBITDA (H1 FY26)₹6.98 cr, up more than 16% YoY from ₹6 cr
EBITDA margin (H1 FY26)17.13%, improved from 12.96% in H1 FY25
Net profit (H1 FY26)₹4.39 cr, up a little over 6% YoY from ₹4.13 cr
Net margin (H1 FY26)10.77%, up from 8.93% in H1 FY25
FY26 revenue outlook₹120–130 cr, as stated by management
FY26 implied growth~25–30% vs last year (per an analyst's math)
Order book~₹30 cr, executable by March 30; additional ₹15–20 cr small orders completing in December
Average order ticket sizeMore than ₹1 cr
Revenue mix: residential20%–25% of total; balance from government and industrial segments
Panel cost decline (YoY)More than 30% decrease; panels represent 60%–70% of EPC cost
O&M portfolio~30 MW under operation and maintenance
RESCO pipeline~27 MW, to be executed in about one year
RESCO payback period4–5 years ROI
Generation advantage0.2%–0.3% more generation vs competitors