Vikram Solar Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/w0ykf2kmc2cn1se3guyceaiw.pdf

Key Takeaways


Volume Shock: What Broke and What Is Recovering

Nagpal: "See, this decline in volume we experienced in Q2, we consider it as a temporary decline. It was a combination of different factors, which I outlined in my remarks. We are already seeing that some of those issues have been addressed, and the offtake is normalizing, both in IPP customers and in C&I customers."

Order Book Reset and Composition

Nagpal: "The U.S. Section 232 circular of August 6 introduced a minimum import price and an additional 15% ad valorem duty with an enforcement deadline of 4th December. As a result, 1 GW of U.S. export orders, which we were carrying in our order book, is no longer viable. We have removed these orders, and our closing order book stands at 8.2 GW."

Margins: Mix Saved the Quarter, Cells Will Transform the Structure

Jindal: "We see four levers for our margin recovery. One, the mix. This has started to deliver and will deepen as distribution scales further. Second, the cost. ... Third, the capacity utilization. This is the largest near-term lever. ... Fourth, the integration. Progressive backward integration, starting with our own cells, will structurally improve margins for FY28."

The Cell Fab and Backward Integration Timeline

Jindal: "Things will drastically change in FY28 with captive cells coming in. We will be penetrating into the DCR market more with our own cells. Let's wait and watch."

Capital Allocation and Balance Sheet


Guidance & Commitments

CommitmentSpecificsTimeline
Cell fab first cell-outFirst cell out from 9 GW TOPCon Plus facilityDecember 2026
Cell fab full commissioningAll lines sequentially commissioned, project CODMarch 2027
Cell margin capture beginsUptick in margins as captive cells flow into DCR modulesFY28
Full cell line operational9 GW cell line fully rampedQ2 FY28
BESS assembly commercial operations7.5 GWh BESS assembly plant starts commercial opsQ1 FY28
Wafer ingot commissioning9 GW wafer and ingot facility commissionedMid FY29
BESS cell manufacturing7.5 GWh battery cell manufacturing live, commissioning in two phases to 15 GWh2029–2030
Order book conversion60%–70% of 8.2 GW order book executedNext 12–18 months
H2 EBITDA per wattPeak maintained at around Q2 levels (₹1.71)H2 FY27
H2 volumesSubstantially higher than H1H2 FY27
Q3 volumeBack to around 1 GW (fair estimate)Q3 FY27
H2 capex₹3,800 crores infused, mostly for cell projectH2 FY27
FY28 capex~₹3,800 crores towards cell plant capexFY28
ALMM List-II enlistment inspectionInspection at cell fab, result 30–40 days afterQ4 FY27

Key Metrics

MetricQ2 FY27
Revenue from operations₹1,077 crores, down 40% sequentially on lower volumes
EBITDA₹101 crores, down from ₹126 crores in Q1 FY27
EBITDA margin9.4%, compared to 12.8% in Q1 FY27
Profit after tax₹6 crores
EBITDA per watt₹1.71, up 37% sequentially from ₹1.25 per watt in Q1
H1 FY27 revenue₹2,641 crores, up 18% YoY
H1 FY27 EBITDA₹227 crores, compared to ₹477 crores in H1 FY26
Volume sold591 MW, down ~40% sequentially
Distribution volume259 MW, up ~80% from 145 MW in Q1; 44% of total volume
DCR volume growth71% QoQ
Order inflow1.7 GW, more than double the previous quarter
Closing order book8.2 GW, after removing 1 GW of unviable U.S. export orders
Order book execution visibility60%–70% over the next 12–18 months
Gross debt₹632 crores
Net debt-to-equity ratio0.17
Distribution network133 distributors, up from 119 last quarter; 750+ dealers and system integrators