Vikran Engineering Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/ho77aondi2r46voky0zutep3.pdf

Key Takeaways


The NOPL Solar Project: The Quarter's Defining Event

Nakul Markhedkar: "We consider it that it is INR20 crores- INR30 crores project, 150 projects of each project being value of around INR20 crores-INR30 crores. So with this, what happens is, it purely becomes a function of money and not a function of anything else. So if money is ready to be infused, you can start all the projects at the same time, finish off the entire 969 megawatt in four months, five months' time."

Consolidated vs Standalone: Why the Numbers Diverge

Ashish Bahety: "Since in consol level your subsidiary becomes a part of the whole company as one entity, and that's where whatever work we are doing for the subsidiary will not be reflected as our revenue. It will be coming as our capex portion in our balance sheet."

Funding, Debt & Cash Flow

Nakul Markhedkar: "Whatever debt we are taking today, we are very confident that this project, NOPL project's revenues, future revenues, will be fully debt serviced. Without putting any stress on to our regular EPC business."

Order Book & New Business Development

Nakul Markhedkar: "This project has given us the confidence and the opportunity to target for higher margin orders from the market rather than going to stressful situations and take low margin orders."

Working Capital, Receivables & the Water Division

Ashish Bahety: "So whatever amount we are getting from these clients, we are only investing that much, and that's how we are trying to close and complete the projects village by village."

Outlook, Seasonality & External Factors

Rakesh Markhedkar: "Kindly have some patience till for the end of this financial year, as I committed by end of this financial year, we will be the cash positive. If we commission 650 megawatt of this solar NOPL, so it is all moving in a very positive direction."

Guidance & Commitments

CommitmentSpecificsTimeline
FY27 revenue₹2,300 crores to ₹2,500 crores total revenueFY27
FY27 execution₹2,200 crores to ₹2,500 crores of orders executedFY27
NOPL revenue~₹1,500 crores from NOPL this financial year, conservativeFY27
NOPL completionFull 969 MW project completedWithin next 12 months
NOPL financial closureIREDA final sanction and disbursementThis quarter
Cash positiveCompany cash positive if 650 MW of NOPL commissionedEnd of FY27
Data center orderAt least one data center orderEnd of FY27
Debtor daysSubstantial improvement from ~296-day peakEnd of FY27
JJM receivablesCompletely received and absorbedBy FY28
Blended EBITDA margin14–17% range maintainedThrough FY27

Key Metrics

MetricQ1 FY27
Standalone revenue from operations₹204 crores, up 28.2% YoY from ₹159 crores
Standalone total income₹215 crores, up 34.6% YoY from ₹159 crores
Standalone EBITDA₹28 crores, up 23.7% YoY
Standalone EBITDA margin13.7%
Standalone PAT₹17.5 crores, up 209.9% YoY
Standalone PAT margin8.6%, up from 3.5% in Q1 FY26, an improvement of more than 500 bps
Consolidated revenue from operations₹141.6 crores
Consolidated EBITDA₹11.3 crores, margin of approximately 8%
Consolidated PAT₹4 crores, margin of approximately 2.8%
FY27 revenue execution target₹2,200 crores to ₹2,500 crores
Order book₹6,496 crores, mix of solar EPC 62%, Power T&D 28%, water infrastructure 10%
NOPL solar EPC order value₹3,518 crores including GST, execution period of 12 months
NOPL revenue recognized in Q1₹62 crores
Total solar revenue in Q1₹70 crores, including ₹62 crores from NOPL and other solar projects
Water revenue in Q1₹12 crores
NOPL capacity commissioned45 MW across nine sites, with another 15 MW ready to commission and 240 MW in advance stages
NOPL capacity in advanced execution265 MW out of 969 MW
NOPL planned revenue for FY27₹1,500 crores, conservative estimate, with ₹100 crores planned for September and the remaining ₹1,400 crores in H2
NOPL project cost₹4,000-odd crores
NOPL debt-to-equity funding75:25
CFA subsidy for NOPL₹1,017 crores
MSEDCL orders secured in April₹530 crores across two orders for distribution infrastructure in Nashik and Kolhapur zones
Power Grid order₹120 crores for 400 KV GIS substation extension package
Miao-Namsai transmission line132 KV, 40.6 kilometers, 138 towers, commissioned in Q1
Jal Jeevan Mission debtors₹120 crores outstanding
Jal Jeevan Mission recovery in Q1₹23 crores received
Water division provision in Q1₹6.5 crores, related to slow JJM receivables recovery
Disputed receivable under court review₹29 crores, certified by client and shown as trade receivable
Debtor days296 days, expected to be the peak and to decline from here
EPC EBITDA margin range14% to 17%, consistent for last four years
NOPL projected annual revenue once operationalOver ₹500 crores from sale of power, with EBITDA of 80% to 89% next year onwards
NOPL commissioning target by end of FY27650 MW