Key Takeaways
- PAT margin commitment held at 10-12%: Management declined to guide on EBITDA but repeatedly anchored PAT expectations at double digits, even as the cost structure shifts toward higher-material turnkey work.
- Order book has flipped to government-dominated: The split moved from 90% private/10% government to 90% government/10% private, driven by DISCOMs that management now calls "cash rich" with payments arriving within 24 hours.
- Debtor recovery materially de-risked the balance sheet: Of INR 58.6 crores outstanding at September-end, over INR 30 crores was collected by early November, with the remainder expected by December; the two largest debtors are state utilities.
- Revenue capacity is being sized for a step-change: Management says INR 350-400 crores is manageable with the current structure, and the upcoming investor presentation will carry projections "much better" than previously announced.
- What to watch next quarter: Whether the INR 60-65 crores of expected order wins from the INR 450 crores pipeline materialize in 3-4 months, the pace of transformer facility revenue contribution, and the updated projections in the investor presentation.
Order Book & Revenue Visibility
- Composition reversal: The order book has swung from 90% private to 90% government because DISCOMs now pay within 24 hours, making government work the preferred exposure.
- Execution timeline: The majority of orders, INR 150-170 crores, are scheduled for completion by 31st March 2025, with the remainder flowing into H1 FY26; most contracts carry 9-12 month durations.
- Revenue phasing is heavily back-ended: 50% to 60% of total revenue will land in February and March (Q4), consistent with the sector's seasonal pattern.
- Pipeline conversion: Management expects INR 60-65 crores of new order wins in the next 3-4 months from a current pipeline of INR 450 crores, applying a 10-15% win rate.
- Geographic reach expanding: The company is empanelled in Gujarat Transcom since 2014 and now has a footprint in 8 other states including Kashmir, Haryana, Rajasthan, MP, Chhattisgarh, Telangana, and Kerala; it is bidding again in other states after concentrating on Gujarat for the last 2 years.
- Bidding capacity: Management states there is no limit in terms of finance or manpower strength, and it is bidding on good projects where execution can be done speedily.
Richi Choksi: "The tenders which are coming, and the funds which are coming to the DISCOM, it's approximately 50 to 60 times what we were getting throughout the year. So the funds are there, the potential is there, the requirement is also there."
Margin Structure & Cost Dynamics
- Cost of material has structurally risen: The cost-of-material share jumped from roughly 50% to 75-80% because the company now wins large 100% turnkey projects requiring full material supply, rather than erection-only jobs where clients provided material as free issue. This model is expected to sustain.
- PAT margin guidance held firm: Management committed to PAT of at least 10%, around 10-11%, or 10-12% across different points in the call, while explicitly declining to guide on EBITDA margin in percentage terms for the near term or next 2-3 years.
- Analyst math on EBITDA was not confirmed: When an analyst asked whether 18-18.5% EBITDA for the full year was reasonable given H1 was 15.8% and substantial revenues come in H2, management did not address the number and instead repeated the PAT commitment.
- Transmission vs. distribution margin logic: Management argues larger transmission companies making 10-12% EBITDA while Viviana targets 10-12% PAT (translating to 17-18% EBITDA) because overheads increase drastically when transmission projects get delayed by right-of-way issues.
- Working capital requirement: Around 35% of revenue including retention money, with current bank facilities, cash reserves, LC and BG limits sufficient up to INR 350 crores of revenue.
Richi Choksi: "So we were executing the projects in which the clients were giving us the material as a free issue. And we were executing the erection and installation work. And at present we have technical as well as financial credentials. So we are getting large projects that are 100% turnkey modification."
Risk Management & Project Selection
- Right-of-way risk is explicitly avoided: Management will not take transmission line projects where right-of-way is in their scope, citing experience that a 6-month project can stretch to 3-5 years, proportionately reducing margins or turning them negative. Current orders are all without ROW in scope, described as "safe and secure" for on-time closure.
- Adani relationship has cooled by choice: The company successfully completed three 400 KV transmission lines for Adani grid in Khavda but has not won Adani projects for 6-8 months because it cannot afford the lower PAT margins those projects would deliver relative to existing work.
- Adani's large transmission wins are not a missed opportunity: Management notes Adani's recently won INR 15,000-20,000 crores of transmission projects are in ROW-prone areas where execution would take considerably longer than distribution projects, overheads would increase, and margins would suffer.
- Competitive positioning: Management describes the company as being in the "safest zone in the past 10 years" with funds flowing from all DISCOMs and Transcoms and tender volumes at unprecedented levels.
Richi Choksi: "We have faced, we had the learnings that a 6-month project gets delayed to 3 years, 4 years, or even 5 years. So, proportionately, the margin will get reduced even it may get in negative also."
DISCOM Environment & Market Opportunity
- DISCOM financial health has transformed: Management cites DGVCL as an example: its budget went from INR 200-300 crores to over INR 10,000 crores, and DISCOMs are now "cash rich" with payments received within 24 hours.
- Tender volumes are multiples of historical levels: Funds and tenders coming to DISCOMs are approximately 50 to 60 times what was being received throughout the year previously; management says the potential is "tremendous and much more than expectations."
- Revenue capacity being built for scale: With the current management structure and finance including the preferential allotment and expanded bank facility, INR 350-400 crores of revenue can be managed easily.
- Banking facility expanded: The facility has grown from INR 17.5 crores two years ago to INR 67 crores with the same bank, plus a tie-up with another bank for a multi-banking facility totaling around INR 76 crores.
- No further equity dilution planned: Nothing has been decided or discussed regarding further dilution for the next 5-6 months, and nothing is planned for this financial year.
Richi Choksi: "Before 2 years to 3 years, they were having the budget of around INR200 to INR300 crores for entire job for the entire year. And at present, they are having more than INR10,000 crores to utilize for the expenditure and network establishment as well as improvement."
Transformer Manufacturing & New Initiatives
- Facility inaugurated: The transformer manufacturing facility was inaugurated on 29th October 2024, with current capacity for distribution transformers up to 1,250 kVA, mainly targeting DISCOMs like DGVCL, MGVCL, and PGVCL.
- Type tests completed: Tests are done for 500 kVA, 2,563 kVA, and 200 kVA transformers.
- Revenue trajectory: Management expects INR 10-15 crores in transformer segment revenue for the next 2 years; once empanelled as a regular bidder for 2 years, revenue of more than INR 50 crores through DISCOMs is targeted.
- Export ambition: For the next 6 months the focus is on utilities; after that, transformers will be type-tested as per IEEE standards to target European and USA markets.
- Capacity expansion being explored: The company is actively exploring opportunities for plants or factories available for sale, tie-up, or collaboration, with an update promised when a deal closes.
- Adjacencies not pursued: Smart metering is not being entered because execution is "a little bit challenging" compared to current project types; Battery Energy Storage Systems have not been explored yet, with focus remaining on EPC and the transformer business.
Balance Sheet & Corporate Developments
- Debtor position substantially cleared: Total outstanding debtors stood at INR 58.6 crores as of 30th September 2024; by 4th November over 50% (INR 30 crores) had been received, with the remaining INR 20 crores expected in November and December. The two largest debtors, DGVCL and GETCO, account for INR 49 crores of the total.
- Aging is clean: No amounts have been outstanding for more than 2-3 years; the major portion outstanding for 1-2 years relates solely to retention money at 10% of basic contract value.
- Main board migration underway: Management will voluntarily announce quarterly results going forward and will hold conference calls on a half-yearly or quarterly basis, as part of preparation to upgrade and migrate to the main board.
- Investor presentation pending: A new investor presentation will be uploaded within a couple of days once expected LOAs from clients are received; projections will be "much better" than previously announced and are backed by bids on open tenders and exploration of tie-ups with big players for back-to-back orders.
Richi Choksi: "But not clicked just because of we cannot afford to have less PAT which we are getting at present in our existing projects. So, that is why, that is the major reason we are not getting any project from Adani from last 6 months to 8 months."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| PAT margin | At least double digits, around 10% to 12% | Ongoing (full year) |
| Revenue | Previous committed top line of ~INR 125 crores will be far exceeded | FY25 |
| Order book execution | Majority of INR 150-170 crores executed | By 31st March 2025 |
| Remaining order book execution | Balance orders executed | H1 FY26 |
| Transformer revenue | INR 10-15 crores | Next 2 years |
| Transformer revenue (post-empanelment) | More than INR 50 crores through DISCOMs | After 2 years of regular bidding |
| Transformer exports | Type testing per IEEE standards for Europe and USA markets | After 6 months (post initial utility focus) |
| Expected order wins | INR 60-65 crores from INR 450 crores pipeline | Next 3-4 months |
| Revenue capacity | INR 350-400 crores manageable with current structure | No date (current capability stated) |
| Funding sufficiency | Current bank facility, cash reserves, LC and BG limits sufficient | Up to INR 350 crores revenue |
| Equity dilution | Nothing decided or discussed; nothing for this financial year | Next 5-6 months / FY25 |
| Investor presentation | New presentation with updated projections | By end of this week |
| Quarterly reporting | Voluntary quarterly results and conference calls | Going forward (main board preparation) |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Revenue guidance | Far beyond ₹125 cr for FY25, previous committed top line |
| PAT margin guidance | 10% to 11% for FY25 |
| H1 EBITDA margin | 15.8% |
| Order book | More than ₹236 cr, cumulative including balance as of 31 Mar 2024, existing orders, and L1 pipeline |
| Order book execution by 31 Mar 2025 | More than ₹150 to ₹170 cr out of ₹236 cr |
| Bids submitted | More than ₹450 cr in tenders |
| Win rate on bids | 10% to 15% over last 4 to 5 years |
| Order book split | 90% government, 10% private, reversed from earlier 90-10 private-government |
| Total outstanding debtors as of 30 Sep 2024 | ₹58,62,35,000, with 50% received by 4 Nov 2024 |
| Expected collection by end of Dec 2024 | 80% to 83% of total outstanding as of 30 Sep 2024 |
| Working capital requirement | ~35% of revenue, including retention money |
| Banking facility | ₹67 cr with existing bank, multi-banking facility of ~₹76 cr |
| Revenue capacity with current structure | ₹350 cr to ₹400 cr manageable with existing management and finance |
| Transformer manufacturing capacity | Up to 1,250 kVA distribution transformers, annual capacity ~7,000 transformers |
| Transformer revenue guidance | ₹10 cr to ₹15 cr for next 2 years, more than ₹50 cr once empanelled as regular bidder |