Key Takeaways
- Volume growth held, pricing bit hard: Rolled sales rose 7.5% YoY to 52,600 tons, but revenue grew only 7.39% as price decreases from muted demand and Chinese imports outweighed the volume gain.
- EBITDA per ton stayed inside the band: At ₹8,000 per ton for Q3 and ₹8,500 for 9M, the metric held within the ₹7,000–₹10,000 range despite pricing pressure, helped by operating efficiencies and lower per-ton power costs.
- Capacity milestone de-risks the growth path: A December test run hit a 300,000-ton annualized rate, proving the melting shop can support the next leg of volume growth without a new furnace.
- Green steel is opening doors that price alone could not: European OEs are approaching Vardhman solely because of its 0.73 tCO₂ per ton footprint, well below India's 2.2 threshold, creating an inquiry pipeline that did not exist before.
- What to watch next quarter: The April board meeting for contours of the new greenfield plant, the pace of customer approvals after the Kocks Block commissions in April, and any government safeguard duty action that could ease the pricing environment.
Volume & Capacity: The Runway Is Now Proven
- December stress test succeeded: The plant made 25,000 tons for the full month, demonstrating a 300,000-ton annual run rate. Management sees this as validating the growth path for the next 3–4 years without needing a new melting furnace.
- Capacity declaration coming: The company expects to formally declare capacity of 3 lakh tons of melting and 270,000 tons of rolling by the end of the next financial year.
- Two debottlenecking projects underway: The Kocks Block sizing mill commissions in April and will add roughly 15,000 tons of input capacity after a few months of stabilization and customer approvals. A new reheating furnace follows by September or October, delivering a larger capacity impact. Together they lift rolling capacity to 300,000 tons of input.
- Volume targets are now explicit: FY26 at 225,000–230,000 tons, FY27 at 245,000–250,000 tons, and FY28 at 270,000 tons, implying a steady 7–8% growth rate aligned with the economy.
- Planned shutdown is a managed event: A 25-day partial shutdown straddling March and April was timed for the seasonal demand lull. Finished goods inventory has been built up, and outsourced rolling mills will continue operating through it.
Sachit Jain: "I'm happy to report that in the month of December, we have tested making 25,000 tons for the whole month, which means that now we have tested albeit only for 1 month but a run rate of 300,000 tons for the full year, so which means for the next 3 to 4 years, the growth path is clear."
Margins: Pricing Pressure Met With Operating Leverage
- The top-line gap tells the story: Revenue grew 7.39% while volume grew 13.5% over nine months, because price decreases were larger than warranted by the mix. Chinese imports depressed commodity steel prices, spoiling sentiment and giving OEs leverage to bargain harder.
- Cost side is doing its job: Per-ton power and fuel costs have actually declined. The absolute power figure of ₹38 crores reflects higher production volumes versus sales, with ₹53 crores of inventory buildup. Higher production absorbs semi-variable and fixed costs better, partially offsetting the pricing hit.
- Two margin tailwinds arrive next year: The solar plant commissions by March–April and will deliver nearly a full year of benefit in FY26. Outsourced job-work costs should also come down substantially in H2 FY26 once the shutdown ends and expanded in-house capacity comes online.
- EBITDA per ton guidance reset for FY26: Previously guided at ₹8,000–₹11,000, now retained at ₹7,000–₹10,000 because market conditions have turned adverse. Management remains reasonably confident of hitting ₹8,000–₹11,000 in FY26–27.
- Return on capital target intact: The company sticks with its 20–25% EBITDA-on-capital-employed target, though this year-end may come in marginally lower.
Sachit Jain: "We are not very happy with this performance, and we hope once this plant or the expansion gets stabilized, we'll be able to focus on more improvements and very soon reach our figure of INR8,000 to INR11,000 guidance."
Green Steel & Circular Economy: An Emerging Moat
- Carbon footprint is a real differentiator: Vardhman operates at 0.73 tonnes of CO₂ per ton of steel versus the government's green steel threshold of 2.2, and is planning to go down further to 0.4. European customers are approaching the company primarily because of this low carbon footprint.
- A large European OE inquiry landed solely on carbon credentials: The customer has never sourced from India before and was explicit that low carbon credit was the only reason for the approach. Samples have been sent and a meeting is planned later this year. If other large European OEs follow suit, management believes the company is "sitting pretty."
- Circular economy advantage is local and structural: North India, home to Maruti, Hero and other large auto OEMs, generates ample scrap. Vardhman does not face the scrap shortage that constrains the rest of the country, making it the best-placed company to implement the circular economy concept with those customers.
- Carbon trading will eventually monetize the advantage: The government is serious about introducing carbon trading in India. When it arrives, Vardhman expects to be a beneficiary, with a positive relative advantage over competitors. For now, management calls any financial quantification "speculation and conjecture."
Sachit Jain: "That inquiry came only because of low carbon credit. They were very clear. That's the only reason they approached us. And they have never sourced from India. And they are huge. If that happens and if other large European OEs follow suit, then we are sitting pretty."
Aichi Partnership & the Toyota Opportunity
- Aichi is filling a gap in its global map: Aichi, the world's third-largest forging company, sees India as the missing piece in its global plan. The India plant will serve the domestic market, Africa in the future, and export to Europe. Vardhman goes "the whole hog" with its partners.
- Toyota's India expansion opens a direct volume path: Aichi supplies roughly 70% of Toyota's global steel requirements. With Toyota announcing a new plant and expansion in India, Vardhman gains a natural channel to supply more volume to Toyota domestically.
- Stake increase talks are progressing: Discussions with Aichi about increasing its stake have been ongoing. The likelihood looks brighter with the new project announcement expected in the next year or two. Promoters would also infuse equity to avoid excessive dilution, with the funds going toward the new plant's capex.
- Export miss tied to Japan macro, not the partnership: Exports ran below the 30,000-ton target primarily because Toyota sales in Thailand did not take off as expected. The yen depreciated significantly over five years while the rupee stayed strong, making Indian costs higher than Japanese costs. A now-depreciating rupee should shift things marginally in Vardhman's favor.
Sachit Jain: "Aichi supplies roughly 70% of Toyota's requirements of steel globally. And therefore with the announcement of Toyota's new plant and expansion in India, this will open up an opportunity for us to supply more volume in India also to Toyota."
Import Substitution & the Policy Backstop
- Chinese imports are the root of pricing pressure: Imports from China have depressed commodity steel prices and spoiled sentiment across the steel industry. Larger players like Tata and JSW have seen profits drop significantly, raising the probability that the government will step in with safeguard or anti-dumping duties.
- Import substitution is already happening: The government is clear about localizing steel imports. Orders that were coming from Korea have already shifted to Vardhman. A large Indian OE has awarded Vardhman a Tier-1 contract to replace Japanese steel imports, with supplies starting within a year.
- Coking coke policy reduced a competitive disadvantage: Recent government action on coking coke has favored Vardhman by narrowing a cost gap versus competitors.
- Tata Steel's Punjab plant is not a near-term threat: To management's understanding, that facility is not yet commissioned and is meant for construction steel, not automotive steel, so it does not compete directly with Vardhman's product mix.
New Plant & the Forging Ambition
- Greenfield planning is in final stages: Major planning at a gross level should be complete by April, with a board approval expected at the April meeting. Land negotiations in Punjab, hopefully in Ludhiana District itself, are in the last stages.
- Forging is the next logical step: More talks have started, and within the next year or two, plans should get concretized with concrete steps on the forging journey beginning.
- Incentives are likely but not finalized: A reasonable assumption is that the Punjab government will offer incentives similar to past projects, including tax refunds and electricity duty benefits, but nothing is finalized yet.
- Capex capitalization is front-loaded: Roughly ₹160–170 crores of capex will be capitalized in FY26, covering the Kocks Block, reheating furnace, and cooling bed additions. A second non-destructive testing line begins work next year and commissions the year after.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY25 volume | 215,000–220,000 metric tons | FY25 full year |
| FY26 volume | 225,000–230,000 tons | FY26 |
| FY27 volume | 245,000–250,000 tons | FY27 |
| FY28 volume | 270,000 tons | FY28 |
| EBITDA per ton (near-term) | ₹7,000–₹10,000 range retained | FY25 Q4 and FY26 |
| EBITDA per ton (medium-term) | ₹8,000–₹11,000 | FY26–27 |
| Return on capital employed | 20–25% EBITDA on CE (this year marginally lower) | Ongoing |
| Kocks Block commissioning | April, then stabilization and customer approvals | April 2025 |
| Reheating furnace commissioning | September or October | H2 CY2025 |
| Capex capitalization | ₹160–170 crores (rolling mill projects) | FY26 |
| Solar plant benefit | Full-year impact on power costs | FY26 |
| New plant board approval | Contours announced at April board meeting | April 2025 |
| Import-substitution order (large OE) | Tier-1 supply replacing Japanese imports | Within a year |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Revenue | ₹426 cr, +7.39% YoY |
| Rolled sales volume | 52,600 tons, +7.5% YoY |
| Volume growth | 13.5% YoY |
| EBITDA per ton | ₹8,000, within stated range of ₹7,000–₹10,000 |
| 9M FY25 EBITDA per ton | ₹8,500, within stated range |
| 9M FY25 PAT | ₹73 cr, +25% YoY from ₹58 cr |
| 9M FY25 total volume | 162,000 tons, +13.5% YoY |
| 9M FY25 revenue growth | 9.5% YoY |
| FY25 volume guidance | ~215,000 tons, on track despite planned shutdown |
| FY26 volume target | 225,000 to 230,000 tons |
| FY26 EBITDA per ton guidance | ₹7,000 to ₹10,000, retained from prior range |
| Power and fuel cost (Q3) | ₹47 cr, of which ₹38 cr is power |
| Variable power cost | ₹5.65 per unit |
| Solar power input cost range | ₹3 to ₹4 per unit |
| CO2 emissions | 0.73 tons per ton of steel, targeting 0.45–0.48 |
| Scrap in raw material mix | ~80%, tested up to almost 100% |
| Capex to be capitalized in FY26 | ₹160–170 cr |
| GST refund and electricity duty benefit | ₹24–25 cr per annum, equally distributed |
| Other expenses (Q3) | ₹67 cr, variable costs, no one-off item |