Key Takeaways
- EBITDA/ton guidance raised sharply: The normalised range jumps to ₹8,000–₹11,000 from FY26, with an aspirational ₹9,000–₹12,000 for FY27, driven by internal efficiencies and the end of costly outside rolling.
- Q4 was an outlier, not a new normal: EBITDA/ton hit ₹11,000, above the guided range, but management explicitly warns this is not sustainable and was aided by one-off quality improvements and inventory gains.
- Demand is a two-speed story: Tractors and some exports are weak, while cars, two-wheelers and commercial vehicles are steady or improving, leaving near-term volume growth dependent on a farm-sector recovery.
- The capex cycle is entering its final leg: The ₹33 crore debottlenecking package completes the current plan, with all major blocks (Kocks, furnace, solar) due online by March 2025, shifting the narrative to the next greenfield decision.
- What to watch next quarter: Whether the ₹2,500–₹3,750/ton price increase letters to OEMs stick, the pace of the tractor demand recovery, and any concrete step on the greenfield plant location.
Margin Reset: The Step-Up in Guidance
- The new floor: Management raised its sustainable EBITDA/ton range to ₹8,000–₹11,000 from FY26, up from ₹7,000–₹10,000 previously, and flagged an aspirational ₹9,000–₹12,000 for FY27. The upgrade is anchored in internal improvements, not pricing power.
- Why not this year: The upgrade was deferred to FY26 because of planned shutdowns for the Kocks block and reheating furnace, plus the continued margin leakage from rolling ~35,000 tons outside. Both headwinds clear once those assets stabilise by March 2025.
- The mechanism is spread protection, not price hikes: Management is explicit that the path to the new range runs through protecting the spread between raw material and selling prices, then layering on internal cost-out. If the spread compresses, the outcome sits at the lower end of the range.
- Q4's ₹11,000 is not the baseline: The quarter benefited from a sharp reduction in Aichi-quality internal rejections and rework, plus raw material inventory gains. Management cautions investors not to calibrate expectations off this number.
- Raw material risk is front-loaded into Q2: When raw material prices rise, the company books an inventory gain in the current quarter. If OEM price increases do not follow, a shock hits when that lower-cost inventory runs out. Letters seeking ₹2,500–₹3,750/ton have been sent; the outcome determines whether Q2 sees margin pressure.
Sachit Jain: "I sincerely hope that this new benchmark that we are setting of Rs. 8,000 to Rs. 11,000 EBITDA per ton and then aspirationally 9,000 to 12,000, we are able to meet that."
Demand & Volume: The Tractor Drag
- March missed, and the weakness started in February: Sales fell about 2.5% short of the prior year, a gap of roughly 5,000 tons, driven by a tractor slowdown and a slight dip in exports from some customers. Cars are doing well, two-wheelers are stable, and commercial vehicles are improving.
- FY25 volume target is 210,000–215,000 tons: The trajectory then steps to 220,000–230,000 in FY26 and 235,000–250,000 in FY27, implying a recovery in domestic auto and a gradual export build.
- Aichi sales are running below plan: The weak yen and lower Toyota/Thailand production have pulled Aichi offtake below expectation. Management is working on alternative products to localise into India, with some being fast-forwarded, but the catch-up will take another year or two.
- Exports remain a small, slow-burn story: FY25 export expectation is a modest 16,000–17,000 tons. The global OEM green steel opportunity is in sampling now, with any real impact visible only from FY27 given the three-year minimum qualification cycle.
- The 100% renewable power ask is manageable: Global OEs require 100% renewable power for their steel. Management states the company will be ready by the time production requirements materialise, with the solar plant and renewable grid power pathway already underway.
Capex: Closing the Current Cycle, Opening the Next
- The ₹33 crore package completes the current plan: The spend covers a fume extraction system, R&D equipment, offline maintenance redundancies, and small debottlenecking steps to lift billet capacity to 285,000 tons. Management says this is the last capex under the existing plan.
- Three big assets land by March 2025: The solar plant (contract by December 2024, benefits from FY26), the Kocks block (placed, stabilised by March 2025), and the reheating furnace (June 2025, stabilised by September–October 2025). Once the Kocks block runs, the ~35,000 tons currently rolled outside at a margin cost come back in-house.
- The greenfield plant has moved from idea to process: Management has started serious internal discussions, is evaluating which state to approach, and expects to begin identifying land parcels in the next few months. No concrete steps have been taken yet, and no timeline is offered.
- Forging is at the study stage, not a plan: The company has begun studying the forging industry, identifying potential partners and target OEs. Management pushed back firmly on calling this a plan, characterising it as early-stage exploration with no decision timeline.
- Dilution is on the table for the next leg: Management acknowledges that the scale of capex required for a new plant will need equity dilution at some stage, possibly as early as this year. Debt-to-equity is capped at 0.3x and expected to fall to 0.1x within three years under current plans.
Sachit Jain: "As the audience here would know, we are a conservative group, and we go slow and steady. So, we are a little patient and cautious and on top of that our partners are Japanese who are also slow and patient. But the beauty with our Japanese what I have seen is they take their time in planning and thinking and consolidating. But once the plans are made then they are firm, and action is fast."
Cost Structure: What Is Moving
- Job work charges stay elevated for three more quarters: The cost of rolling outside will persist until the Kocks block is fully stabilised, after which it drops out of the cost base entirely from FY26.
- Electrode prices have turned: Prices are now softening and will come down in subsequent quarters, providing a tailwind after a period where Q4 carried higher electrode costs than the year-earlier period.
- Other income is operational, not exceptional: The ₹7–8 crore of prior-period items that flattered last year's other income are absent this year. Current other income is part of the regular costing structure and similar numbers are expected going forward.
- Gross profit per kg drivers are not disclosed: Management declined to split the improvement between lower raw material benefit and better mix benefit, arguing the factors are interdependent: lower raw material cost can mean higher power cost and lower yield.
- Solar plant cost per unit is undisclosed: Management declined to share the expected cost per unit from the new solar plant when asked.
Competitive Position: The Carbon Moat
- A two-year path to a 0.2 carbon footprint: The solar plant (December 2024) drops the footprint to ~0.45; switching to renewable grid power then takes it to 0.2 within two years. Competitors on the blast-furnace route sit at 2.5–3.0, creating a structural cost and compliance advantage as carbon regulation tightens.
- Aichi quality is now a margin driver, not a drag: Internal rejections and rework for Aichi-grade steel were significantly higher than anticipated earlier. Those have now come down, contributing directly to the better profitability in Q4 and giving management the confidence to raise the guidance range.
- R&D investment is synchronised with Aichi: The company has added sophisticated R&D equipment calibrated to Aichi's readings, with training from Aichi personnel, building a quality capability that management claims few Indian steel companies possess.
Sachit Jain: "This will make us by far the lowest carbon footprint company in our special steel sector compared to our competitors who will between 2.5 to 3 as almost all of them are from the blast furnace route. We will be at 0.2 in 2 years from now, they'll between 2.5 to 3."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| EBITDA/ton range | ₹8,000–₹11,000 per ton | FY26 |
| Aspirational EBITDA/ton range | ₹9,000–₹12,000 per ton | FY27 (to be confirmed a year from now) |
| Sales volume | 210,000–215,000 tons | FY25 |
| Sales volume | 220,000–230,000 tons | FY26 |
| Sales volume | 235,000–250,000 tons | FY27 |
| Billet capacity | 285,000 tons | Within 2 years (via ₹33 crore capex) |
| Bright bars capacity | ~60,000 tons | Within 3 years (most done in 2) |
| Outside rolling elimination | All rolling in-house after Kocks block stabilisation | FY26 onward |
| Solar plant | Contract and benefits | Contract by Dec 2024; benefits from FY26 |
| Kocks block | Stabilised | By March 2025 |
| Reheating furnace | Stabilised | By September–October 2025 |
| Carbon footprint | 0.45 with solar, then 0.2 with renewable grid power | 0.45 by Dec 2024; 0.2 within 2 years |
| Debt-to-equity | Cap at 0.3x, fall to 0.1x | 0.1x within 3 years under current plans |
| Job work charges | Continue at elevated levels | Another three quarters |
| Electrode prices | Softening | Subsequent quarters |
| Greenfield plant decision | Decide state, identify land parcels | Next few months (no concrete steps yet) |
| New plant/final capex decision | Clarity expected | Roughly 9 months to 1 year from now |
Key Metrics
| Metric | Q4 FY24 |
|---|---|
| Revenue | Not stated |
| EBITDA per ton | ₹11,000, above the stated range of ₹7,000–₹10,000 |
| EBITDA per ton guidance (FY25) | ₹7,000–₹10,000 |
| EBITDA per ton guidance (FY26) | ₹8,000–₹11,000 |
| EBITDA per ton aspirational range (FY27) | ₹9,000–₹12,000 |
| Sales volume | 52,000 tons |
| Sales volume shortfall vs previous year | 2.5%, 5,000 tons short |
| Gross profit per kg | ₹35 per kg, improved |
| Total export volume (FY24) | 12,000 tons, 7,300 tons direct plus 5,000 tons to Aichi |
| Export volume guidance (FY25) | 16,000–17,000 tons |
| Billet capacity achieved | 260,000 tons, tested in January and February |
| Billet capacity target | 285,000 tons in next 2 years, with ₹33 cr CAPEX |
| Rolling mill capacity | 210,000 tons, up from 200,000 with two new stands |
| Rolling mill capacity target | 260,000–270,000 tons after Kocks block and reheating furnace |
| Sales volume guidance (FY25) | 210,000–215,000 tons |
| Sales volume guidance (FY26) | 220,000–230,000 tons |
| Sales volume guidance (FY27) | 235,000–250,000 tons |
| Bright bars capacity | 48,000 tons per annum, target 60,000 in 3 years |
| Carbon footprint (scope 1 and 2, per ton of billet) | 0.7 tons of carbon, target 0.45 with solar, then 0.2 with renewable grid power |
| Total CAPEX announced | ₹433 cr, ₹260 cr (2022) + ₹140 cr (Jul'23) + ₹33 cr (new) |
| CAPEX spent so far | ₹82 cr out of ₹433 cr, plus ₹25 cr for land, ₹19 cr for renewable project share |
| CAPEX pending | ₹370–380 cr |
| Debt-to-equity ratio | 0.12x, not expected to cross 0.3x, back to 0.1x in 3 years under current plans |
| Solar plant capacity | 55 MW, generating ~8 crore units, savings of ₹5–15 cr annually |
| Power consumption | ~800 units per ton of steel |
| Job work (outside rolling) | ~35,000 tons rolled outside in FY24, 8,000–10,000 tons bottleneck for certain sizes |