Waaree Energies Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/q2xt03yv668g82oab3afw9iy.pdf

Key Takeaways


Q4 Margin Compression: The Quarter's Defining Event

Abhishek Pareek: "Over the last quarter, we have seen two things which no one envisaged. The war in the Middle East and the crisis of commodity prices."

The H2 Margin Catalyst: Cell Self-Sufficiency

Varun Goenka: "One EBITDA margin is a function of the proportion of module and cell, and every company will have different proportions. So, Waaree's module volume and value is much larger being an industry leader, and that's why the module by design is higher value and margins look lower."

Order Book & Demand: A Pause, Not a Reversal


Waaree 2.0: The Capex Cycle That Redefines the Company

Abhishek Pareek: "We are converting a dependency into a pricing power, and that is an opportunity which we are excited about."
Varun Goenka: "Waaree's 20 gigawatt hour is just the beginning. I think the runway of growth and capacity is multi-decadal in this segment. So, let's be patient about how BESS segment plays out. That has the potential to create a new Waaree in itself."

Cash Flow & Working Capital: The Quarter's Other Blemish


Overseas Markets: Diversification Beyond the US

Jignesh Rathod: "Italy is always close to Mr. Doshi's heart and entire Waaree. From where we have started, our first line is from Italy with the capacity of 30 megawatts way back in 2007. And we love Italy. So, yes, it is in our growth plan."

Guidance & Commitments

CommitmentSpecificsTimeline
FY27 operating EBITDAINR7,000 crores to INR7,700 crores (20-25% growth on FY26's INR5,908 crores), inclusive of pre-startup costs for projects going live this yearFY27
10 GW cell plant liveFull cell capacity reaches 15.4 GW, entire Indian market cell requirement sourced in-houseH2 FY27
Cell production normalizationExisting 5.4 GW lines return to prior-quarter output plus 10-15% upside from G12R transitionWithin one quarter
US manufacturing capacityExpand from 1.6 GW to 4.2 GW total local US capacityNext six months
BESS Phase 13.5 GWh capacity operationalCurrent financial year (FY27)
BESS Phase 216.5 GWh capacity operationalNext financial year (FY28)
Inverter capacityRemaining 1 GW operational (total 4 GW)Current financial year (FY27)
Transformer capacityTotal 20,000 MVA achievedCurrent financial year (FY27)
Electrolyser capacity1 GW at Dungri facility, GujaratCurrent financial year (FY27)
Ingot wafer facility10 GW capacity at Nagpur (capex INR6,200 crores)FY28
PV glass manufacturing2,500 TPD capacity (capex INR3,900 crores)Over next 24 months
FY28 cell utilization80-85% on full-year 15.4 GW cell capacityFY28
FY28 module utilization28 GW global module capacity at full throttleFY28
Fund raiseEnabling resolution taken; amount and timelines to be clarifiedOver next couple of months
ALMM II regulatory clarityGovernment clarification expectedWithin a week

Key Metrics

MetricQ4 FY26
Revenue from operations₹8,480 cr, up 111% YoY
Operating EBITDA₹1,576 cr, up 70% YoY
Operating EBITDA margin18.6% (per an analyst's math), down from 22.27% in FY26 full year; impacted by commodity prices, logistics costs, and sales mix
Profit after tax₹1,126 cr, up from ₹644 cr in Q4 FY25
FY27 operating EBITDA guidance₹7,000 cr to ₹7,700 cr, implying 20%–25% growth over FY26
Module production4.2 GW, up 104% YoY
Cell production0.7 GW
Modules sold4.1 GW
Order book~₹53,000 cr, down ~₹7,000 cr sequentially; 65%–70% overseas, to be delivered over 3–4 years
Export mix21% of revenue, down from 32% in Q3; impacted by Middle East logistics disruptions
US local module capacity1.6 GW operational, expanding to 4.2 GW over next six months
US IRA benefit (cumulative FY26)~$40 million, at $0.07 per watt peak, 87%–88% of eligible amount realized
G12R cell efficiency25.4% with Fraunhofer reference cell; transition expected to lift output and realization by 10%–12%
Working capital cycle~90 days, up from ~45 days in FY25, driven by higher inventory from delayed export shipments
Cash flow from operations conversion~27.5%, down from 100%+; normalized level expected at 70%–100%