Key Takeaways
- Soft quarter, resilient margins: Revenue was hit by external disruptions, yet EBITDA margin held at 22.9%, in line with FY26 and well above the 18%+ guidance.
- Aunta-Simaria divestment unlocks capital: The definitive agreement values the asset at an EV of ~₹1,000 crores, and completion in Q2 FY27 will demonstrate the capital recycling model for future BOT/HAM assets.
- Key approvals now in hand: The Dharavi-Ghatkopar Tunnel received its long-awaited High Court clearance, and the Pune-Shirur sub-concession agreement was executed, clearing the path for execution to accelerate from here.
- Growth confidence is intact but tempered: Management is confident of growth in FY27, but now expects it closer to 15% than 20%, contingent on commodity availability and geopolitical stability.
- What to watch next quarter: Completion of the Aunta-Simaria transaction and its disclosed IRR, the pace of execution ramp-up now that approval hold points are cleared, and whether the delayed WMEL orders actually convert into LOIs.
Execution Headwinds & Margin Resilience
- Three external shocks hit Q1: Supply chain disruptions from ongoing geopolitical developments, a temporary construction stoppage in Mumbai lasting several weeks, and labor migration related to elections in certain key areas combined to soften revenue.
- WMEL felt the same pressures plus an order delay: Revenue at the Michigan subsidiary moderated to ₹179 crores with a 21.3% EBITDA margin, as the same external factors were compounded by delays in the release of orders for certain projects that deferred execution and revenue recognition.
- Bhandup WTP slowed by pollution controls: The pace of execution on the 2,000 MLD water treatment plant was slower than initially envisaged because the competent authority temporarily stopped all excavation debris transportation due to severe AQI pollution in Mumbai City.
- Revenue has now declined in four of the last five quarters: Management attributed the streak to extraneous factors beyond company control, including the Mumbai construction and debris movement closure and geopolitical impacts on material availability.
- Margins held the line despite the top-line softness: EBITDA margin remained resilient at 22.9%, in line with the FY26 annual margin of 22.8% and much above the 18%+ guidance, reflecting the strength of the execution model and disciplined cost management.
- A non-recurring loss below the line: The ₹34 crores loss from discontinued operations related to the MCP project is non-recurring in nature and does not reflect ongoing profitability.
Sandeep Garg: "Despite these near-term execution challenges and resulting softer revenue performance, we maintained healthy profitability with EBITDA margins remaining resilient at 22.9% during the quarter. This is in line with our FY26 annual EBITDA margin of 22.8% and much above our guidance of 18% plus."
The Aunta-Simaria Divestment & Capital Recycling Model
- A definitive agreement is signed: The company signed a security subscription and purchase agreement for the divestment of its entire stake in the Aunta-Simaria HAM project, valuing the asset at an aggregate enterprise value of approximately ₹1,000 crores, subject to customary adjustments, approvals from NHAI and lenders and the fulfillment of other conditions precedent.
- Completion is imminent: The transaction is expected to complete during Q2 FY27, with additional details including the valuation multiple and project IRR to be shared after completion.
- This is the second proof point of the model: The divestment follows the 2022 monetization of six road assets to Actis, establishing a track record of completing the full project life cycle from development through monetization.
- The strategy is explicitly a compounding growth model: Management intends to replicate the same divestment approach across future BOT and HAM assets, including SNRP and Pune-Shirur, unlocking capital from mature assets and redeploying it into new high-growth, high-return opportunities without stretching the balance sheet.
Sandeep Garg: "Our approach is to selectively bid for and develop high-quality infrastructure assets, create value through efficient execution under our asset-light subcontracting model and monetize these assets at an appropriate stage. This enables us to unlock capital from the mature assets and redeploy it into new high-growth, high-return opportunities without stretching our balance sheet, effectively transforming a linear build cycle into a compounding growth model."
Project Milestones: Approvals Cleared, Execution Set to Accelerate
- Dharavi-Ghatkopar Tunnel is finally unblocked: The project received all requisite approvals by the end of June, including the long-awaited High Court clearance on June 22, and execution has now commenced.
- Pune-Shirur sub-concession agreement executed: The agreement was followed by a Bhumi Pujan ceremony in the presence of the Union Minister for Road Transport and Highways, the Maharashtra Chief Minister and other dignitaries, though the appointed date is still to be achieved and is expected in Q3 FY27.
- Panjrapur 910 MLD WTP is ready to ramp: The project secured in December 2025 has completed initial mobilization and all key statutory approvals are now in place, with construction activity expected to accelerate meaningfully over the coming quarters.
- Dharavi WWTF remains on track: The project is on track for commissioning by July 2027, after which it will transition into a 15-year O&M phase providing a stable, recurring annuity revenue stream.
- Several projects are nearing completion: Three segmental TBM projects plus a micro-tunneling project in Mumbai remain on track for completion during FY27, the Mumbai Storm Water Drain Rehabilitation project is on schedule for FY27 completion, and the Baroda GRP line mega trunk drain is nearing completion almost a year ahead of schedule.
- Two road projects are in the final stretch: The Varanasi-Aurangabad Road is expected to receive its provisional completion certificate shortly, and the Sattanathapuram-Nagapattinam Road is in advanced stages of completion, progressing toward PCC in Q3 FY27.
- UP Jal Jeevan Mission O&M has commenced: O&M activities have begun on a number of completed schemes, and the company remains on track to complete the balance of execution during FY27.
Growth Outlook: Confident but Cautious
- FY27 growth is now pegged closer to 15%: Management is reasonably confident of being in a growth phase in FY27, but the estimate has been tempered to closer to 15% than 20%, depending on how commodity availability and associated challenges play out.
- Three pillars underpin the confidence: The order book stands at 3 to 3.5 years even excluding O&M, statutory and approval hold points are now behind for all projects except the Pune-Shirur appointed date, and traction is coming back on targeted projects.
- The long-term internal target remains 15% to 20% annualized growth: Management is targeting that range on an annualized basis and is reasonably confident the growth phase shall continue not only in FY27 but in years to come, though FY28 will be forecast based on how FY27 evolves.
- Order inflow target of ₹8,000 to ₹10,000 crores for FY27: The company expects to aggregate that amount in orders during the year, though inflows expected in H1 may move to H2.
- Pune-Shirur will contribute ~₹500 crores in FY27: Revenue recognition is expected once the appointed date is declared in Q3 FY27, with construction activity accelerating toward the end of the fiscal year following financial closure.
- WMEL orders are expected soon: Management is confident of receiving LOIs for the delayed orders in the coming weeks, and execution activity is expected to contribute positively over the coming quarters, with a meaningful acceleration during H2 FY27 as recently awarded projects move into full-scale construction.
- The external environment remains a stated risk: Management remains mindful of the evolving external environment, including geopolitical developments, which could influence execution timelines.
Sandeep Garg: "See, the confidence is there to deliver a growth for sure. It will be more closer to 15% than 20% is what my estimate at this point in time is. It will all depend upon how things pan out and how the commodities availability and the associated challenges play out."
Water & Technology Differentiation
- Water segment EBIT margins of 20–25% are a technology story: Management attributed the premium margins to a technology play and differentiation, targeting projects that offer a technology angle rather than every project, and cautioned that these margins may not be maintainable in run-of-the-mill water projects.
- The technology source is a guarded secret: When asked whether the technology component enabling higher margins is from a third party or in-house, management declined to elaborate, citing business strategy.
- The opportunity pipeline is vast: Opportunities in the water treatment space are described as humongous, potentially in the range of a few lakh crores, with the company currently tracking approximately ₹30,000 crores of projects.
- Micro-tunneling fleet is fully utilized domestically: The fleet of machines is 100% occupied in the domestic market, and the company is not tempted to go overseas given enough opportunity exists in India.
- Smart Ops is progressing slowly and cautiously: The platform is being rolled out with extreme caution because it involves water and the Welspun brand, with revenue potentially ranging from ₹50 crores to ₹100 crores, though management declined to give formal guidance.
Sandeep Garg: "Mr. Jainam, it's all about technology play. We are not playing -- as I said, we don't target every project. So we target projects which can offer some technology play, which allow us to be differentiated. In the run-of-the-mill water project, I'm not too very sure these margins are maintainable."
Oil & Gas: A Decision Point Approaches
- The revised Field Development Plan has been submitted: The revised FDP for MB-OSN-2005/2 has been submitted to the client, and the company has received access to ONGC platform and infrastructure to evacuate gas from the block, a positive government decision.
- FDP approval is expected in 4 to 6 weeks: Once approved, the company will be in a position to share full details.
- The intent to develop the field is high: Management indicated a very high likelihood that the company will develop the field and produce from it, given the country's focus on oil and gas and the business opportunity foreseen, though the final decision depends on FDP approval.
- Production is roughly two years from approval: The timeline from FDP approval to actual production is approximately two years.
- The long-term strategy for the segment is undecided: When asked whether the intent is to exit oil and gas as a business after FDP alignment, management said it is a matter of thought process until the FDP is approved and it is very difficult to say which way they are headed.
Digital & Operational Initiatives
- The Source-to-Pay platform is progressing toward a Q3 FY27 go-live: Implementation of the S2P platform is progressing well and is expected to go live in Q3 FY27, part of a broader transition to a unified enterprise application architecture.
- e-office and digital architecture rollout is underway: The e-office platform is being rolled out alongside the transition to an integrated digital architecture, advancing the company's digital transformation roadmap.
- AI use cases are under development: The company is developing AI-based use cases across quality assurance, safety monitoring, logistics planning and project progress monitoring, though no revenue or timeline commitments were made.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Aunta-Simaria divestment completion | Transaction to close; valuation multiple and project IRR to be disclosed | Q2 FY27 |
| FY27 revenue growth | Growth closer to 15% than 20%, contingent on commodity availability and geopolitical factors | FY27 |
| FY27 order inflow | Aggregate ₹8,000 crores to ₹10,000 crores of new orders | FY27 |
| Pune-Shirur appointed date | Appointed date expected, enabling ~₹500 crores revenue recognition | Q3 FY27 |
| Dharavi WWTF commissioning | Project commissioned, transitioning into 15-year O&M phase | July 2027 |
| S2P platform go-live | Source-to-Pay platform operational | Q3 FY27 |
| Oil & gas FDP approval | Revised FDP approved; full details shared thereafter | 4 to 6 weeks |
| Oil & gas production | First production from the field | About 2 years from FDP approval |
| UP Jal Jeevan Mission completion | Balance execution completed | FY27 |
| Three TBM projects + Mumbai micro-tunneling completion | Projects completed | FY27 |
| Mumbai Storm Water Drain Rehabilitation completion | 15.5 km project completed | FY27 |
| Sattanathapuram-Nagapattinam Road PCC | Progressing for achieving PCC | Q3 FY27 |
| Varanasi-Aurangabad Road PCC | Provisional completion certificate received | Shortly |
| WMEL order inflows | LOIs received for delayed orders | Coming weeks |
| WMEL execution acceleration | Meaningful acceleration as new projects enter full-scale construction | H2 FY27 |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Consolidated revenue | ₹774 cr, water 41%, transport 35%, tunneling 24% |
| EBITDA margin | 22.9%, above guidance of 18%+ and in line with FY26 annual margin of 22.8% |
| PAT from continuing operations | ₹90 cr |
| Loss from discontinued operations | ₹34 cr, related to MCP project, non-recurring |
| Reported PAT | ₹56 cr |
| Consolidated order book | Over ₹18,700 cr, as of June 30, 2026 |
| Order book coverage | 3 to 3.5 years, excluding O&M |
| Cash and cash equivalents | ₹1,792 cr, as of June 30, 2026 |
| Net worth | ₹3,324 cr, as of June 30, 2026 |
| Net debt | ₹109 cr, as of June 30, 2026 |
| WMEL revenue | ₹179 cr |
| WMEL EBITDA margin | 21.3% |
| WMEL order book | ₹2,135 cr, as of June 30, 2026 |
| FY27 revenue growth estimate | Closer to 15% than 20% |
| FY27 order inflow expectation | ₹8,000 cr to ₹10,000 cr, H1 inflows may shift to H2 |