Key Takeaways
- Earnings surge, margin gap widens: Consolidated EBITDA rose 28% YoY to INR192 crores, with margins hitting ~24%, yet management reiterated an 18% guidance without reconciling the difference.
- Aunta-Simaria bridge goes live: The country's widest cable-stayed bridge achieved PCOD in May 2025, was inaugurated by the PM in August, and its monetization is expected to close within FY26.
- Pune-Shirur L1 reshapes the pipeline: Emerging L1 for a INR7,300 crore BOT toll project signals a move into larger-ticket transport assets, backed by a INR1,000 crore preferential warrant issue to strengthen the balance sheet.
- Mumbai water dominance building: Two mega water treatment plants, once complete, will supply 70% of Mumbai's freshwater, anchoring a multi-year revenue stream through FY29.
- What to watch next quarter: Closure of the Aunta-Simaria asset sale, the Pune-Shirur letter of award, and any resolution on the oil and gas block evacuation plan, all of which management expects within weeks to months.
Project Execution & Completion Milestones
- Aunta-Simaria bridge operational: The 1.8 km cable-stayed bridge achieved PCOD on May 15, 2025, and was inaugurated by the Prime Minister on August 22. The first annuity payment is scheduled for November, and monetization efforts are underway with closure anticipated within this financial year.
- Varanasi-Aurangabad Road Project delayed: Work front availability issues and local disturbances have pushed the main carriageway completion to January 2026, with overall completion now expected in Q1 FY27.
- SNRP at 74% complete: The pond ash issue has been resolved with 6.32 lakh cubic meters secured through an NLC auction, and provisional completion is expected in Q1 FY27.
- Dharavi STP on track: Asia's first multi-storey sewage treatment plant at 418 MLD has major civil structures nearing completion and mechanical equipment erection commenced, targeting commissioning by July 2027.
- Bhandup WTP execution picked up: The 2,000 MLD plant, one of the world's largest under construction, uses 30-50% less footprint than conventional plants. Work has accelerated after an extended monsoon, with completion targeted for April 2029.
- Dharavi-Ghatkopar tunnel advancing: All pre-project clearances are expected by December, and shaft work for a 150-meter shaft at Ghatkopar will commence by early March. A new TBM is being added for this project.
- Pumping stations pre-monsoon ready: All ongoing pumping stations are on track to be in service prior to the next monsoon season to address Mumbai's flooding needs.
- UP Jal Jeevan Mission progressing: The project is currently supplying water to over 300 villages and will benefit nearly 2,500 villages upon completion, though it will not finish within this financial year and is expected to complete next year.
Sandeep Garg: "Once completed, these 2 water treatment projects will provide for 70% of Mumbai's freshwater requirements."
Order Book & New Business Wins
- Panjrapur WTP added: A new order from BMC for a 910 MLD water treatment plant at Panjrapur near Mumbai marks the second water treatment project in the Mumbai region after Bhandup. The design-and-build project will see substantial revenue contribution starting FY27, with minor contribution in Q3 and Q4 of the current fiscal.
- Pune-Shirur Elevated Highway L1: The company emerged L1 for a BOT toll project from MSIDC with a total project cost of INR7,300 crores, awaiting the letter of award. Once awarded, the first six months will be consumed by financial closure and design, with minor FY26 contribution and full operational contribution starting FY27.
- H1 order inflow nearly meets FY26 guidance: Management stated that order book guidance for FY26 is almost done in H1, though it declined to provide specific guidance for the remaining five months.
- Welspun Michigan pipeline strong: The subsidiary's team continues to pursue opportunities and expects to further strengthen its order book during Q3 and Q4 of this year. Tunneling projects at Goregaon and Borivali catchment are on track for completion in FY27/FY28.
- SmartOps expansion: Four to five new projects are expected to be executed over the next 6 to 8 months, adding to the four projects that have already gone live in 18 months across Varanasi, Guwahati, and Pandharpur.
- NHAI pipeline temporarily slow: A bit of a slowdown is visible at NHAI currently, but management expects that once BOT model revisions and HAM revisions are agreed, many projects will get awarded at the center, while states are progressing as per plan.
Margin Performance & Guidance
- Consolidated EBITDA margin hit ~24%: The 600 bps YoY expansion was driven by a diversified project portfolio, continued emphasis on cost control, and execution excellence, with the Aunta-Simaria project completion contributing to the uplift.
- Conservative accounting explained: The company creates contingencies at the start of a project based on risk perception. As the project completes and risks are mitigated, the contingency is released toward profit. All costs on claims or change of scope are booked but not accounted for until the order or claim is received, which sometimes depresses reported profits.
- Tunneling margin potential: As projects get larger, mobilization, demobilization, overhead, management bandwidth costs, and TBM costs get apportioned over larger revenue, and reuse of machines coming off projects creates additional value. Management declined to put a specific number on peak margin potential.
- Guidance gap unresolved: Management stated that current margins "may continue" for the foreseeable future but reiterated overall guidance of "around 18%," without explaining the gap between the current ~24% and the 18% target or providing a timeline for any normalization.
Sandeep Garg: "Although we foresee at least for the next foreseeable future that these margins, what we are reporting right now may continue. But however, an overall level, we do not change our guidance, which we have always maintained, it will be around 18% of there."
Balance Sheet & Capital Allocation
- INR1,000 crore preferential warrant issue: The company is in the process of raising capital through a preferential issue of warrants via private placement with participation from the promoter group, aimed at strengthening the balance sheet as opportunities unfold over the next 18 months.
- NHAI net worth rule change driving the raise: NHAI is revising evaluation criteria for PPP projects, considering available net worth (net worth minus commitments) as the new qualification criteria for HAM projects. With current consolidated net worth at approximately INR2,800 crores and being L1 in a large project needing substantive equity commitment, the raise is preemptive.
- Aunta-Simaria monetization timeline: Under the rule of COD plus six months with a requirement to hold more than 51%, the first annuity is expected in December. Investor interest is expected to become visible then, and if value-accretive, the deal may conclude in Q4 FY26 or Q1 FY27.
- Oil and gas blocks nearing resolution: Active engagement between the company, ONGC, and the government is underway to resolve the take-off point and cost of transportation and processing for three major blocks. Management expects resolution in the next 45 days or so, after which a field development plan as cluster development will proceed, providing clarity on value creation and divestment.
Sandeep Garg: "I would also want to be very clear here with my investors that any money or anything that we will commit to any of these projects will be a prudent capital allocation if we need to, to monetize."
Segment Performance
| Segment | Trend | Commentary |
|---|---|---|
| Tunneling & Rehabilitation | ▲ Strong growth | 75% YoY growth in H1 FY26; Welspun Michigan revenues up 60% YoY in Q2 to INR169 crores with 20.8% EBITDA margin. |
| Water | ▬ Stable | Revenues remained stable; positioning as a technology-led solution provider with unique offerings like multi-story SBR and smallest-footprint plants in urban cities. |
| Transport | ▼ Declined | Revenue declined 30% impacted by completion of Mukarba Chowk-Panipat, Aunta-Simaria, and the Varanasi-Aurangabad project nearing completion. |
| Welspun Michigan | ▲ Strong | H1 revenues up 51% YoY to INR377 crores; Mithi Tunnel completed, feeding wastewater to Dharavi STP; multiple rehabilitation projects across Mumbai, Ahmedabad, Baroda, Delhi. |
Strategic Positioning & Organizational Updates
- Technology-led differentiation in water: The company is positioning itself as a technology-led solution provider rather than a bid-based player, creating unique offerings such as multi-story SBR plants with the smallest footprint in urban cities. It is also actively exploring sludge management technologies to create value from waste, potentially through tie-ups, acquisitions, IP, or collaboration.
- Digital transformation underway: The company successfully migrated to SAP RISE for S/4HANA and is adopting 3D, 4D, and 5D modeling. It has begun RFI-based DPR generation for the Bhandup project on a pilot basis and is digitizing its project management dashboard for real-time data analytics.
- Leadership strengthened: Abhishek Chaudhary was appointed as CEO of the Transportation vertical, and Hardik Dhebar was appointed as President of Finance for Welspun Enterprises. Further augmentation across verticals is expected in the coming time.
- Tunneling industry conviction: Management forecasts that the next 10 years will see more tunneling activity than the last 75 years, and the company is positioned to capture this with repeatable, larger orders that improve margin potential through cost apportionment and machine reuse.
- No vertical split planned: Management sees no current visibility about splitting the company into verticals or verticals into separate companies, though it remains open to any consideration that creates stakeholder value depending on size, scale, and evolution.
Sandeep Garg: "Tunnelling, as I said, is one of the fastest-growing industry at this point in time, and we forecast that in the next 10 years, we will do what we have not done in last 75 years."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Consolidated revenue target | INR4,000 crores for FY26, subject to climate support and statutory approvals | FY26 |
| Aunta-Simaria monetization | Asset sale closure anticipated | Within FY26 |
| Varanasi-Aurangabad Road Project | Main carriageway completion by Jan 2026; overall completion by Q1 FY27 | Jan 2026 / Q1 FY27 |
| SNRP completion | Provisional completion expected | Q1 FY27 |
| Dharavi STP commissioning | Asia's first multi-storey 418 MLD STP | July 2027 |
| Bhandup WTP completion | 2,000 MLD plant, one of world's largest | April 2029 |
| Dharavi-Ghatkopar tunnel | Pre-project clearances by December; shaft work at Ghatkopar to commence | Dec 2025 / early March 2026 |
| Pumping stations | All in service prior to next monsoon season | Pre-monsoon 2026 |
| Oil and gas block resolution | Evacuation plan and cost agreement with ONGC and government | Next ~45 days |
| Pune-Shirur letter of award | Expects LOA definitely in this quarter | Q3 FY26 |
| UP Jal Jeevan Mission completion | Will not complete this fiscal; expects completion next financial year | FY27 |
| Overall EBITDA margin guidance | Maintained at around 18% | No expiry stated |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Consolidated total income | ₹803 cr |
| Consolidated total income (H1 FY26) | ₹1,674 cr |
| Consolidated EBITDA | ₹192 cr, up 28% YoY from ₹150 cr in Q2 FY25 |
| Consolidated EBITDA margin | ~24%, up 600 bps YoY from 18% in Q2 FY25 |
| Consolidated EBITDA before exceptional items | ₹126 cr, up 24% YoY from ₹102 cr in Q2 FY25 |
| Consolidated PAT | ₹99 cr, up 63% YoY from ₹60 cr in Q2 FY25 |
| Consolidated PAT margin | 12.3%, improved on a YoY basis |
| Standalone revenue from operations | ₹593 cr |
| Standalone EBITDA | ₹116 cr, up 18% YoY from ₹99 cr in Q2 FY25 |
| Standalone PAT | ₹95 cr, up 9% YoY from ₹87 cr in Q2 FY25 |
| Consolidated order book | ₹15,615 cr, including O&M contracts of ~₹5,400 cr |
| Water order book | ~₹11,000 cr, of which ~₹5,400 cr is O&M |
| Welspun Michigan order book | ₹2,650 cr, 60% tunneling, 22% pumping stations, 14% rehabilitation |
| Welspun Michigan Q2 FY26 revenue | ₹169 cr, up 60% YoY |
| Welspun Michigan EBITDA margin | 20.8% |
| H1 FY26 segmental EBIT margin – Transport | 26% |
| H1 FY26 segmental EBIT margin – Water | 28% |
| H1 FY26 segmental EBIT margin – Tunneling & Rehabilitation | 21% |
| Consolidated net worth | ₹2,870 cr |
| Consolidated net debt | ₹688 cr |
| Standalone net worth | ₹2,810 cr |
| Standalone cash and cash equivalents | ₹986 cr |
| Consolidated cash reserves | ₹1,043 cr |
| Tunneling & Rehabilitation segment revenue growth (H1 FY26) | 75% YoY |
| Transport segment revenue decline (H1 FY26) | 30% YoY, impacted by completion of major projects |
| Pune-Shirur Elevated Highway total project cost | ₹7,300 cr, 54 km, 6-lane, ~37 km elevated; L1 bidder, awaiting LOA |
| Panjrapur 910 MLD WTP EPC value | ₹1,685 cr (excl. GST), O&M component ₹980 cr |
| Aunta-Simaria project PCOD | 15 May 2025, first annuity scheduled for November 2025 |
| SNRP project completion | ~74% complete, provisional completion expected Q1 FY27 |
| UP Jal Jeevan Mission receivables | ₹200–220 cr, with ~₹500 cr unexecuted balance |
| Fundraising through preferential warrants | ₹1,000 cr, via private placement including promoter group participation |