- Chennai ramp-up drives 42% revenue growth: The new park contributed ₹28 crores in Q2, accounting for about 73% of the ₹14.26 crores EBITDA increase, while existing parks and resorts also delivered record quarters.
- Profit held flat by depreciation: Despite EBITDA nearly doubling, PAT improved only ₹1.81 crores as about some INR500-odd crores of park investment began flowing through the P&L at 7–8% annually, a drag that will persist.
- Footfall growth is real, not just a COVID hangover: Management called out that older parks have now grown beyond the FY23–FY24 pent-up demand anomaly, with a long-term CAGR of 8 to 9 years that it considers extremely healthy for the industry.
- Non-ticket revenue is the structural margin story: Non-ticket revenue per guest grew 11% in Q2 to ₹510, reaching 34% of ARPU, and management is scaling past successes in retail, F&B and product assortments.
- What to watch next quarter: Chennai's first-ever monsoon season (mid-October to end-November) and its impact on footfall, plus whether the company closes any of the 2–3 new location deals it hopes to conclude before FY27-end.
Chennai Park: The Quarter's Engine and Its Trajectory
- Q2 contribution: Chennai delivered 1.90 lakh visitors and ~₹28 crores revenue in Q2; for H1, 4.32 lakh visitors and ~₹73 crores revenue, making it the single largest contributor to the ₹48.57 crores H1 EBITDA increase at 58%.
- Ticket pricing gap: Chennai's average ticket price of ~₹948 was 10% below Bangalore because Bangalore commands a premium as the largest park, and Q2 saw a higher mix of discounted group visitors versus retail footfall.
- Margin path is lumpy, not linear: EBITDA margins improved significantly during Q2 but will move up and down across quarters in the first year; management expects stabilization to established-park levels only after 2–3 years.
- Footfall ramp-up timeline: Management targets Bangalore-level footfall in about 3 years but will only know the Phase 2 growth trajectory by end of FY28; optimal utilization and sustainable profitability are also a 2–3 year journey.
- Monsoon uncertainty: This is Chennai's first-ever monsoon season, and management is still learning consumer patterns during the mid-October to end-November period; a full-year view is needed before drawing conclusions.
Dheeran Choudhary: "In Chennai, this is actually in sense our first ever monsoon, as Chennai monsoons happen between mid-October to end-November. We are also kind of understanding the overall consumer trends and patterns."
Existing Parks: Record Quarters and Weather Scars
- Bengaluru and Kochi delivered their best-ever Q2, while Hyderabad delivered its best-ever H1; together, existing parks grew revenue 8% YoY in Q2 with footfalls up 6%, driven by rigorous campaign execution based on customer feedback.
- Bhubaneswar bucked the trend: Footfalls fell, entirely weather-led, with 900% growth in rains, ~20 of 30 districts hit by extreme cyclones, and consumer sentiment too poor to drive visits.
- Long-term growth validated: Management is happy to have grown beyond the post-COVID pent-up demand anomaly of FY23–FY24, seeing an 8–9% CAGR over 8–9 years as extremely healthy for an amusement park.
Dheeran Choudhary: "There was a 900% growth in rains with about 20 out of 30 districts affected with extreme cyclones. And because of those weather disruptions, consumer sentiment was poor to drive footfall."
ARPU and the Volume-Value Trade-Off
- ARPU grew modestly at 1% YoY to ₹1,491: average ticket price declined 3% YoY to ₹983, offset by an 11% increase in non-ticket revenue per guest to ₹510.
- Management deliberately sacrifices ARPU in lean quarters to drive volume, betting that more visitors improve word of mouth; Q2 is seasonally the weakest quarter for ARPU, with Q1 strongest and Q3/Q4 in between.
- Non-ticket revenue is the structural growth lever: The 4–5 year CAGR is in early double digits, reaching global trends of 30%+ non-ticket share of ARPU; management continues to build on retail, F&B and product assortment strategies but declined to share granular details.
Dheeran Choudhary: "Depending on seasonality, sometimes we have to take a bit of a dip in ARPU to drive more volume, which is the utmost importance because more people will also in turn increase better word of mouth, and especially in lean quarters."
Resorts: A Meaningful Third Leg
- Resorts delivered their best-ever Q2, growing 57% YoY, and contributed 14% of the ₹14.26 crores Q2 EBITDA increase and 10% of the H1 EBITDA increase.
- Expansion decision pending: Management will wait for one full year of the new Bangalore resort to complete before deciding where to expand resorts next.
New Park Pipeline: Ambition Without a Clock
- Target is 2–3 new locations, with at least one big project in the next 1–2 years, possibly one Tier 2 city, and maybe two large cities; management hopes to conclude some deals before the end of this financial year.
- Greenfield is the preferred route: Management sees no real long-term difference between acquiring an existing park and starting from scratch, and prefers greenfield over taking over someone else's asset.
- No timeline commitment: When pressed on whether 3 parks can be completed in 3–4 years, management called it "hard to say" and declined to comment further until there is finality.
- Funding is not the constraint: No further equity dilution is planned; existing cash flows from five parks can fund most capex, with some debt possible at some point but no equity dilution needed as of now.
Arun Chittilappilly: "It's not that difficult. I mean, for us it doesn't make any difference whether we get an existing park or we start from scratch. It might take 1 or 2 years more. But other than that, I mean, there is no real long-term change for us. So we prefer to do greenfield and more than take over somebody else's asset."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Chennai park to reach optimal utilization and sustainable profitability | Achieve margin profile similar to established parks (Hyderabad, Bangalore, Kochi) after 2 to 3 years | 2 to 3 years |
| Chennai park to reach Bangalore-level footfall | Phase 2 growth ramp-up visibility | Approximately 3 years; clearer picture by end of FY28 |
| New park deal closure | Hope to conclude some deals for 2–3 new locations | Before end of FY27 |
| Resort expansion decision | Decision on where to expand resorts next | After 1 full year of new Bangalore resort operation |
| No further equity dilution | Fund capex from existing cash flows; may take some debt | Ongoing |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue from operations | ₹116.57 cr, up 45% YoY |
| Total income | ₹126 cr, up 42% YoY |
| EBITDA (incl. other income) | ₹30.11 cr, up 90% YoY |
| EBITDA margin | 24%, expanded from 18% in Q2 FY26 |
| Profit after tax | ₹5 lakh, versus a loss in Q2 FY26 |
| Other income | ₹9.1 cr, primarily gains from investments |
| H1 FY27 revenue from operations | ₹359.2 cr, up 45% YoY |
| H1 FY27 EBITDA (incl. other income) | ₹152.1 cr, up 47% YoY |
| H1 FY27 PAT | ₹72.8 cr, up 43% YoY |
| Average revenue per user (ARPU) | ₹1,491, up 1% YoY |
| Average ticket price | ₹983, down 3% YoY |
| Non-ticket revenue per guest | ₹510, up 11% YoY |
| Total footfalls (all parks) | 8.24 lakh (Bengaluru 2.13 lakh, Kochi 2.02 lakh, Hyderabad 0.99 lakh, Bhubaneswar ~20,000, Chennai ~1.9 lakh) |
| Existing parks revenue growth | 8% YoY, with footfalls up 6% and ARPU up 2% |
| Chennai Park revenue | ~₹28 cr, with footfalls of 1.9 lakh |
| Resorts business growth | 57% YoY, best ever Q2 |
| Chennai Park EBITDA contribution | ₹10.37 cr, 73% of the total ₹14.26 cr EBITDA increase |
| Depreciation increase | ₹10 cr, on account of Chennai Park operations commencing |