Key Takeaways
- Solid quarter, expansion narrative dominates: Revenue grew 9.2% YoY on footfall and ARPU gains, but the call was overwhelmingly about the pipeline of new parks and the margin profile during this investment cycle.
- Bhubaneswar pulled forward by two quarters: The new park now opens in May 2024 (Q1 FY25) , not Q3, pulling revenue and footfall into the next fiscal year sooner than the street had modeled.
- Margins will drift lower for years: Management explicitly guided that the 3–4% EBITDA dip this quarter is structural while new parks launch, with steady-state EBITDA staying north of 50%, but no timeline for when that steady-state arrives.
- The 10-city ambition is real but unfunded: Current projects are covered by cash flows, but management is open to debt for the next wave and ruled out equity dilution only for the next year.
- What to watch next quarter: The Bhubaneswar launch ramp and initial footfall trajectory, any sign of a Kochi recovery after the COVID-scare dip, and whether Hyderabad’s underperformance begins to correct.
Quarterly Performance & Drivers
- Footfall grew 3% YoY driven by marketing campaigns around Diwali, Christmas, New Year, and events like Sunburn at Kochi and a New Year event at Hyderabad.
- ARPU rose 6% YoY in Q3 and 15% for the nine-month period, powered by non-ticket revenue growth and healthy response across walk-in, group, and all customer segments.
- Non-ticket revenue hit ~35% of total versus 25–26% last year, a 10-percentage-point improvement that management has been deliberately targeting post-COVID.
- Kochi footfall declined due to a COVID scare in Kerala in late December and bomb blasts, with the public reacting more strongly to adverse news than in other markets. Bangalore footfall grew 10%+ as expected.
- Hyderabad underperformance persisted: footfalls remain lower than Cochin and Bangalore, which management called an anomaly and hopes to correct next year.
- Employee costs rose 20% from a 10% salary hike and a 10% increase in outsourced headcount, plus net recruitment of ~60 people. Higher group footfall also drove higher commission payouts.
Arun Chittilappilly: "I think people's preferences for nearby entertainment have changed, post COVID. I think there is a more focus on frequent but less expensive vacations for Indians. I think that is helping us as well."
Expansion Pipeline & New Parks
- Bhubaneswar park opening pulled forward to the latter half of May 2024 (Q1 FY25), earlier than the previously planned Q3 FY25, giving it all of June and part of May in the first quarter.
- Chennai park is expected to open in the second or third quarter of FY26, with performance expected to match Bangalore-level after ramp-up and ARPU comparable or slightly higher.
- Bangalore resort expansion approved: adding 40 rooms, an adventure park, and a convention center at a total investment of ₹70–80 cr, with construction taking about a year and effects visible only in FY26.
- Gujarat park will be set up between Ahmedabad and Gandhinagar, close to GIFT City.
- New park economics are favorable: all projects are expected to be EBITDA-positive from year one due to vertical integration, in-house ride manufacturing, park design, and lower capex costs. Total footfall ramp-up takes 2–3 years.
- Bhubaneswar ARPU is expected at ~₹1,000, with a footfall target of ~5 to 6 lakhs in a year. The first six months will be a launch phase, with stabilization after that.
Arun Chittilappilly: "We are expecting all our projects to be EBITDA positive from year 1 itself, thanks to our very efficient way of constructing and also because we manufacture a lot of the rides and technologies ourselves."
Margin Trajectory & Cost Structure
- EBITDA margin dipped 3–4% this quarter from peak levels last year, and management expects this to continue for the next few years as new parks come online and employee, marketing, and promotion costs rise.
- On a steady-state basis, management hopes to maintain EBITDA north of 50%, but no specific timeline was given for when the portfolio reaches steady-state.
- Maintenance capex for the next financial year is planned at ~₹45–50 cr, split between Bangalore (₹30 cr) and Kochi (₹15 cr), for new rides, facilities, and upkeep across existing parks.
- Ticket price resistance is absent: ARPU has improved 30% from FY21 to FY23/FY24, and management sees a post-COVID consumer shift toward frequent, less expensive nearby entertainment helping absorption.
Arun Chittilappilly: "We are already at peak margin last year. So like it will be slightly lower as we have new parks coming into play, and we'll be adding employees to our costs... But on a steady-state basis, the kind of margins that we are seeing where we hope to maintain our EBITDA north of 50%."
ARPU & Non-Ticket Revenue Strategy
- Non-ticket revenue is the core ARPU lever: management is trying to push NTR to ~40% of total ARPU, up from the current 25–30%, through new F&B options, retail, adventure parks, and resort additions.
- Park differentiation supports repeat visits and ARPU: parks are tailored to local climate and tastes (heated pools in Bangalore, not in Kochi), and Chennai and Bhubaneswar will have different rides and experiences from existing parks, encouraging cross-park visitation.
- Ticket price increases are expected at 5–10% every year in ARPU terms, with no resistance observed so far.
- Bangalore resort revenue is expected to double or more than double once the expansion is complete, with detailed projections to follow after the investment plan is finalized.
Competitive Positioning & Geographic Ambition
- Management wants to be in about 10 cities with concrete plans within the next few years, preferring Tier 1 cities (NCR, Bombay-Pune, Kolkata) but open to Tier 2 depending on land acquisition and government support.
- On a competitor expanding into Indore, management noted the competitor’s parks are much smaller and said Wonderla’s offering would be large-format amusement parks, adding: "we are not really worried about that."
- UP government has approached Wonderla for parks in Ayodhya and Varanasi; the company is evaluating but has not decided, with a stated philosophy of one large city per state and a preference for NCR.
- No interest in a Disney-style IP tie-up: management said Disney does not tie up and its model is too expensive for India, though left the door open to other IPs if needed.
- Expansion strategy is a mix of asset-heavy and asset-light depending on geography and land availability; Tier 1 and Tier 2 cities are hard for land leases, but the company is open to it if available.
Arun Chittilappilly: "I think they have a couple of parks, which they already had. They've integrated into one company, but they are much smaller parks than our, and I don't know whether we'll be directly competing with them. Our offering in Indore will be large format amusement parks, not small parks. So we'll have to wait and see, but we are not really worried about that."
Funding & Capital Allocation
- Current two projects (Bhubaneswar, Chennai) can be managed with existing cash flows and cash accruals; the company is currently debt-free.
- For new projects beyond these, management is open to taking on some debt, with a decision on funding structure "maybe after the next year, not immediately."
- Equity dilution is off the table for at least the next one year.
- Hyderabad resort will be taken up only after FY26, once the Bangalore expansion model is proven and stabilized.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Bhubaneswar park opening | Latter half of May 2024 | Q1 FY25 |
| Chennai park opening | Second or third quarter of FY26 | FY26 |
| Mature parks footfall growth | 3–5% for the full year | FY24 |
| Bhubaneswar footfall target | ~5 to 6 lakhs annually | After ramp-up |
| Bhubaneswar ARPU | ~₹1,000 | At launch |
| Non-ticket revenue target | ~40% of total ARPU | No date |
| Steady-state EBITDA margin | North of 50% | No date (after new parks stabilize) |
| Equity dilution | None | At least next 1 year |
| Hyderabad resort | Construction start | After FY26 |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Revenue from operations | ₹123.6 cr, +9.2% YoY |
| Revenue including other income | ₹129.5 cr, +10% YoY |
| EBITDA | ₹60.4 cr, -1% YoY |
| EBITDA margin | 46.7%, down 3–4 ppt YoY |
| Profit after tax | ₹37.3 cr, -4% YoY |
| PAT margin | 28.8% |
| Revenue including other income (9M FY24) | ₹401.1 cr, +18% YoY |
| EBITDA (9M FY24) | ₹209.5 cr, +18% YoY; margin 52.2% |
| PAT (9M FY24) | ₹135.3 cr, +19% YoY; margin 33.7%, +20 bps YoY |
| Footfall | 9.45 lakhs, +3% YoY |
| ARPU | ₹1,256, +6% YoY; ticket ₹890, non-ticket ₹366 |
| Non-ticket revenue contribution | ~35% of revenue, up from 25–26% in Q3 FY23 |
| Group footfall mix | 66% group, balance general |
| Bhubaneswar Park planned capex | ~₹189 cr, ~₹140 cr spent to date |
| Bhubaneswar Park target ARPU | ~₹1,000 |
| Bhubaneswar Park expected annual footfall | 5–6 lakhs |
| Existing parks footfall growth guidance | ~5% for FY25 |
| Bangalore resort expansion investment | ₹70–80 cr, adding 40 rooms, adventure park, convention center |
| Maintenance capex (FY25) | ~₹45–50 cr, roughly 10% of top line |