Key Takeaways
- Record quarter, demand surge: Q4 footfalls, revenue, EBITDA, and PAT all breached pre-COVID levels, with March alone delivering peak-season numbers despite being an off-season month.
- Marketing transformation unlocked margin: A complete post-COVID shift from traditional to digital-only marketing lowered marketing spend while footfalls rose, a structural reset management admits should have happened years earlier.
- Ticket prices raised four times: Strong demand allowed three price increases already, with a fourth set for June 1, 2022; dynamic pricing is under consideration pending IT upgrades.
- Expansion pipeline reactivating: Odisha construction is expected to start this year, a Chennai decision is due by year-end pending tax negotiations, and Goa and Gujarat governments have both invited the company to set up parks.
- What to watch next quarter: Whether the demand surge outlasts revenge tourism, the outcome of Tamil Nadu tax negotiations for Chennai, and progress on the 60-40 non-ticket revenue mix target.
Demand & Footfall Recovery
- Q4 trajectory: The quarter began with Omicron-related weekend lockdowns in Cochin and Bangalore; footfalls improved only towards end of February but were robust from March onwards.
- March anomaly: All three parks recorded the highest March footfalls since their respective openings, driven by Women's Day and Holi celebrations; March, traditionally a very weak month, delivered April-level peak-season numbers.
- Women's Day record: The event produced the highest single-day footfall in the company's 22-year history at 32,000 visitors.
- FY22 full-year: Footfalls reached 10.5 lakhs for the year, with Q4 alone exceeding 4.9 lakhs; revenue grew 232% YoY to ₹127.5 crore from ₹38.4 crore.
- Current demand: Footfalls are now better than pre-COVID, with an event, travel, and tourism phenomenon driving extra demand whose duration is uncertain.
- Footfall history: Footfalls grew at nearly 20% CAGR until demonetisation in 2017; post-demonetisation, GST increased ticket tax and the economy slowed, preventing parks from reaching their potential.
- Per-park capacity: Current design handles approximately 1 to 0.12 crore visitors per park, with a maximum of 0.15 crore; surplus land allows expansion to eventually handle 0.3 crore if footfalls justify it.
Arun Chittilappilly: "We are seeing that extra demand which we don't know how long that will last, but I definitely feel that if there are no further waves this year should be a good year for us."
Marketing & Digital Transformation
- Structural shift: Post-COVID, the company completely stopped using traditional media and uses only digital marketing; traditional media is now used only as fillers, a complete reversal of the pre-COVID approach.
- Spend efficiency: Marketing spend has come down while footfalls are going up, a result management attributes to analytics-based online marketing being "cracked very well."
- Online booking share: Online bookings reached about 30% of total, up from 10% pre-COVID, enabling retargeting, remarketing, and better customer insight into age group, demographics, and origin that was not possible before.
- Late switch acknowledged: Management admitted the digital marketing shift should have happened in 2018 or 2019; the delay contributed to underperformance.
- CRM pipeline: Full CRM implementation and website overhaul are still in the pipeline; once the full marketing stack is online, management expects much more analytics and even footfall prediction capability.
Arun Chittilappilly: "We have completely stopped using traditional media and we use only digital marketing. We do use traditional media only as fillers unlike before, when we used to rely more on traditional media and less on digital. So, the reverse shift has happened after COVID and that has worked really well for us because our marketing spend has come down at the same time our footfalls are going up."
Revenue Mix & Non-Ticket Initiatives
- Non-ticket ratio goal: Target to shift revenue mix from 75-25 (ticket vs non-ticket) to 60-40 within 2 to 3 years.
- Initiatives underway: Adding new F&B varieties, redoing F&B outlets, adding more F&B points, collaborations for trending F&B, and park-plus events like rock shows, concerts, rain dance, Holi, and Women's Day to create buzz and attract new crowds.
- Group-sales shift: Post-COVID, dependence on group sales has reduced for Bangalore and Hyderabad, though Cochin still gets large groups; more full-price-paying customers are coming, who tend to spend more inside the park.
- Q4 spend behavior: Much higher per-capita spend compared to pre-COVID was visible in Q4 itself.
Expansion Pipeline
- Odisha project: Should be able to get off the ground this financial year itself; construction timeline is scheduled at about two years from the time construction starts.
- Chennai project: A decision on whether to construct will be made this financial year; currently not viable due to high taxation; negotiations with the Tamil Nadu government are looking positive.
- Chennai land: If Chennai does not proceed, the land can be sold without loss as values have "skyrocketed"; management still hopes to come through as the new DMK government appears more aggressive on investment.
- Goa and Gujarat: The Goa government has invited Wonderla to set up a park; the Gujarat government has also extended an invitation.
- Management/takeover model: Evaluating 3 to 4 takeover or management opportunities currently; exploring taking over large projects others have invested in and converting them to Wonderla parks on a revenue-share or management basis.
- Colombo opportunity: A takeover opportunity for a park in Colombo exists, likely on hold due to the Sri Lanka situation but not off the table; significant investment has already been made by the other party with international design consultants and ride orders placed.
- Funding: If only the Odisha park starts, it can proceed with internal accruals; if more than one park starts, the company might go for debt, though no debt is planned this year.
- Existing park expansion: Hyderabad will receive investment in more rides as footfalls grow; Cochin has more than doubled in size, Bangalore is approximately 30% larger, and Hyderabad is still adding.
Arun Chittilappilly: "That is a fate of our country, you know, what can you do about it? Land acquisition is hard. Getting approvals is hard. Taxation is hard, everything is hard."
Pricing & Competitive Position
- Ticket price increases: Ticket prices have been increased three times already; a fourth increase is set for June 1, 2022, driven by strong demand.
- Dynamic pricing: Under consideration but will take time, dependent on IT system readiness.
- India vs global economics: Management noted that Indian movie tickets cost about ₹300 versus $15 to $20 in the US, a structural gap that prevents building huge parks and explains why companies like Disney or Six Flags cannot afford to build in India as they would never make the money back.
- Outdoor entertainment durability: Management believes physical activities like high-speed thrills, splashing, and water-based fun are never going out of style regardless of the generation.
Arun Chittilappilly: "...if you look at the outdoor entertainment, where there is active fun, high speed, thrill, splashing, water, these things are never going to go out of style. You know, even if you're born in 1990s or 2010 or 2020, or 2050, some of these physical activities I think are going remain..."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY23 footfalls | Expecting around pre-COVID level, possibly better than FY19 if no further waves or lockdowns | FY23 |
| Odisha construction start | Project to get off the ground; construction timeline approximately two years from start | This financial year (FY23) |
| Chennai decision | Decide whether to construct or not, contingent on tax negotiations with Tamil Nadu government | Before end of FY23 |
| Non-ticket revenue mix | Shift from 75-25 to 60-40 | Within 2–3 years |
| Ride additions | Not planning to add too many rides; if adding new rides, will remove some old rides | Ongoing |
| Debt | Not planning any debt this year | FY23 |
| Management/takeover deals | One or two in north and west India expected to reach logical conclusion | Next 2–3 years |
Key Metrics
| Metric | Q4 FY22 |
|---|---|
| Revenue | ₹127.5 cr (FY22), +232% YoY |
| Footfalls | 4.9 lakhs (Q4), 10.5 lakhs (FY22) |
| March footfalls | ~3 lakhs |
| Single-day footfall record | 32,000 visitors on Women's Day |
| Online bookings share | ~30%, up from ~10% pre-COVID |
| Revenue mix | 75% ticket, 25% non-ticket; goal is 60-40 |
| Ticket price increases | 3 increases already executed, another planned June 1 |
| GST on tickets | 18%; Tamil Nadu adds 10% local tax, total 28% |
| Chennai project investment to date | ~₹100 cr, mostly in land |
| Chennai project additional Capex estimate | ₹330 cr initial estimate, could rise by ₹10–20 cr |
| Odisha project Capex | ~₹120 cr initial outlay |
| Sustaining Capex | ~₹30 cr per year |
| FY23 Capex earmarked for Odisha | ~₹50 cr plus ~₹10 cr lease payment |
| Internal accruals | >₹100 cr per year average |
| Cash in hand | >₹120 cr as of March 31 |