Aditya Birla Real Estate Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/7f0ml1iutj0de3w29iczv976.pdf

Key Takeaways


Real Estate: The Growth Engine

Jithendran: "I think as we progress in our construction and the project gets closer to completion, there is still quite a bit of room for appreciation... So the value accretion from here is going to be phenomenal."

The H2 Launch Gantt Chart

Management laid out a specific, back-end-loaded launch calendar. Four to five projects are slated between December and March, and the FY25 presales number lives or dies on their execution.

ProjectLocationPlanned Launch
Wellesley RoadPuneDecember (Q3)
SarjapurBangaloreJanuary (Q4)
HindalcoThaneMarch (Q4, "more likely")
Trimaya new phaseBangaloreQ4
Sector 31 BarmaltGurugramQ4 ("touch and go")
Jithendran: "As far as Noida, we have signed a binding agreement, and there is certain preconditions precedent, which the JV partner has to fulfil. So until that is completely complied with, we are not talking or disclosing the other commercial details of the project."

Paper: The Cash-Consuming Legacy Business

Snehal Shah: "I don't think we expect to generate any cash flow this year because half year is gone. And there has not been a significant inflow of cash from the paper business. The outlook does not look very good, but we hope that it will be better in the second half, but we don't expect profits to probably reach even 50% of what we did last year."

Land Bank & Balance Sheet


Execution Risk & Market Structure

Jithendran: "NCR is a very broad market. If you look at Noida, there's hardly any supply, hardly any new projects launched, very few projects are being launched. There's virtually no supply. There's huge demand. Demand far outstrips supply."

Guidance & Commitments

CommitmentSpecificsTimeline
FY25 presalesINR 7,000–8,000 croresFY25
Annual sales run-rateCross INR 10,000 croresWithin 3 years
Wellesley Road launchLaunch projectDecember (Q3 FY25)
Sarjapur launchLaunch projectJanuary (Q4 FY25)
Hindalco launchLaunch projectMarch (Q4 FY25)
Trimaya new phase launchLaunch projectQ4 FY25
Sector 31 Barmalt launchLaunch project (conditional: "touch and go")Q4 FY25
Worli Tower C (Niyaara last phase)LaunchNext financial year
Noida JV preconditionsPartner to comply with preconditions precedentBefore December
Standalone debt/equityRemain around 1x at mostOngoing
Paper business cash flowNo cash generation expectedFY25
Capital allocationAll fresh capital to real estate; paper self-sustainsOngoing

Key Metrics

MetricQ2 FY25
Consolidated revenue from continuing operations₹1,121 cr, +32% YoY
Consolidated EBITDA₹99 cr, +50% YoY; margin 8.8%
Consolidated net profit from continuing operations₹13 cr
Real estate segment revenue (Birla Estates)₹254 cr, +500% YoY
Real estate segment EBITDA margin11%
Real estate project-level EBITDA margin~30% across all projects
Real estate bookings (pre-sales)₹1,412 cr for already launched projects
Real estate collections₹644 cr from all projects
Real estate pre-sales guidance FY25₹7,000–8,000 cr, management reasonably confident
Pulp and paper average net sales realizationDown 4% YoY, almost flat QoQ
Pulp and paper production volume+8% YoY
Pulp and paper sales volume+13% YoY and +10% QoQ
Pulp and paper EBITDADown 22% YoY and 10% QoQ
Standalone gross debt₹3,581 cr
Standalone net debt~₹3,000 cr; net debt to equity 0.7–0.8x
Consolidated net debt~₹4,500 cr; net debt to equity 1.1x
GDV acquired during the quarter₹15,400 cr (Worli ₹14,000 cr + Gurugram ₹1,400 cr)
GDV acquired year-to-date~₹21,000 cr with investment of ₹1,500 cr
International bookings contribution20–25% of total bookings
Niyaara Phase 2 (Silas) units sold77 out of 148 apartments
Walkeshwar project (Anayu) pricing₹1,50,000 per sq ft; 2 of 8 apartments sold