Key Takeaways
- Earnings transformation accelerates: EBITDA excluding other income jumped 298% YoY to INR1,302 crores, with margin expanding 12.9 percentage points to 17.5%, driven by aggressive cost reduction and improved realizations.
- Cost engine delivering ahead of plan: Power and fuel costs fell 33% YoY to INR1,425 per ton, logistics costs dropped 3.1%, and other expenses reduced 13.5%, with management targeting an additional INR300+ per ton in savings over the next 12-36 months.
- Volume growth lagged the industry: Consolidated volume rose only 2.3% YoY against double-digit industry growth, hit by severe flooding in Himachal and heavy monsoons in central India; October rebounded to healthy double-digit growth.
- Capacity expansion roadmap locked in: Sanghi acquisition (INR5,000 crores, closing Q3) plus 10 new kilns and 35 grinding units ordered or planned, targeting 14 crore tons capacity by FY28, with management confident of achieving it ahead of schedule.
- What to watch next quarter: Sanghi deal closure and integration plan, pace of cost savings delivery against the INR400/ton target, and whether October's double-digit volume momentum sustains through the peak construction season.
Cost Transformation
- Power and fuel costs slashed: Reduced 33% YoY to INR1,425 per ton from INR2,134, driven by waste heat recovery expansion (90 MW operational, targeting 170 MW by March '25), own coal mine production ramp-up, better fuel mix, alternate fuels, green energy, and global fuel price declines. Each MW of waste heat costs INR1 vs grid cost of INR6-7.
- Logistics costs improving: Reduced 3.1% to INR1,377 per ton through route planning, L1 source adherence, renegotiation, GPS/tech measures, warehouse optimization, and direct dispatch increase of 5 percentage points to 49%. Average primary road lead distance reduced from 175 km to 165 km, with a target of ~100 km.
- Other expenses structurally lower: Reduced 13.5% to INR829 per ton, driven by single-entity operations, streamlined employee hierarchy, and removing redundancies between Ambuja and ACC. Technical know-how fees to Astral Olsen have been reduced for both companies.
- Savings trajectory: Of the INR400/ton cost reduction target, ~INR100 has been achieved, with ~INR300 more to come. Once INR400 is hit, the target will increase to INR500. Of the INR650/ton cost improvement vs last year, 20-25% is from lower market fuel prices, 10-15% from own initiatives. Logistics savings: ~25-30% captured, 70% still to come.
- Sustainable EBITDA target: INR1,450-1,500 per ton within 36 months, requiring completion of new lower-cost kilns, new grinding units to reduce lead distance, culmination of long-term raw material contracts, completion of current WHRS and green energy stage, and plant-level optimization projects.
Kapur: "So all those things will play out over 12 months to 36 months. Maybe earlier, but I think you can take 36 months as the last upper limit of that."
Volume Performance & Market Dynamics
- Volume growth below potential: Consolidated volume grew only 2.3% YoY, significantly trailing industry double-digit growth. July was particularly weak due to severe flooding in Himachal impacting Ambuja's Gagal unit and its grinding units, plus heavy monsoons in central India. October saw healthy double-digit growth.
- ACC hit harder by floods: ACC has one integrated unit in Gagal with few grinding units, while Ambuja is well-integrated with 4 grinding units in the North (Roper, Bhatinda, Dadri, Roorkee). ACC's entire grinding is in Gagal with a tolling arrangement with Asian, making it more vulnerable to the Himachal disruption.
- Realization improved: Up 0.9% to INR5,334 per ton, driven by micro market management strategy, dealer network expansion, blended cement mix at 89%, and premium products share increasing 0.8% to 23.4% of trade sale volume.
- East region outlook: Management expects demand to normalize to 8-10% growth post-November/December, down from the earlier 15-16% run-rate.
- Bad trade practices curtailed: Wherever there were leakages or lower EBITDA sales from some plants, those have been curtailed to improve efficiency, a structural shift management says "will stay with us."
Kapur: "We had not a very good July month. As you know, large part of our capacity north in Himachal, it was seriously flooded. It had some supply chain impact in the month of July. I think we also had very heavy monsoons in the central India."
Capacity Expansion & Projects
- Sanghi acquisition: Announced 3 August at enterprise value of INR5,000 crores, fully funded through internal accruals. Seller's conditions precedent in progress, expected to close in Q3 current year. Brings 6.6 crore tons clinker capacity (expandable to 7.2) and 100 crore tons of limestone reserve, improving footprint in Gujarat, Mumbai, parts of Maharashtra and down south where Ambuja is under-supplied.
- Ametha integrated unit: Kiln fired in Madhya Pradesh, adding 0.33 crore tons per annum clinker capacity; cement mill commissioning this quarter.
- Project pipeline locked in: Bhatapara clinker facility (Q2 FY26), Sankrail and Farakka grinding units (Q3 FY25), Maratha clinker line (Q4 FY26), Salai Banwa grinding unit (Q1 FY26). Orders placed on TCDRI, China; LOI issued for another 5 grinding units. Jalgaon and Amravati grinding units (0.2 crore tons each) expected in 24 months.
- 14 crore ton target: Management confident of achieving before FY28. Sanghi plus another Sanghi-scale addition gets ~70% there; need to open 2 new sites of 0.4 crore tons each. 3 kilns by end FY26, 7 more by FY27/FY28, all at current locations (mostly brownfield). Existing kilns can be optimized another 10%.
- Raw material security: Won bid for 0.2 crore ton coal mine in Dahegaon Gowari, Maharashtra; won bids for 10 new limestone mines across Odisha, Maharashtra, Gujarat, Madhya Pradesh, Rajasthan with total estimated reserves of 58.4 crore tons. Two captive coal mines together to cater to 40-50% of current coal requirement.
Kapur: "The Sanghi acquisition has two underlying strategies. First, it is a great asset at a great location and is very synergistic within our own ecosystem. Number two, it has 100 crore tons of limestone reserve, which allows us to increase clinker capacity in a very good location to help us cater to the West Coast."
ACC-Specific Turnaround
- Margin gap narrowing: ACC and Ambuja historically had a ~4-5% margin gap. Last September ACC was almost at negative/zero margin when acquired. Movement since then has been structurally in the right direction, with cost benefits going equally to both companies and sales/pricing driven by the same leaders. Catch-up expected to be "even sharper in time to come."
- Legacy plant rationalization: ACC's legacy plants are being structurally evaluated: either replace with new kilns next door, make investment, or mothball them. This is a multi-year footprint optimization that will permanently improve ACC's cost position.
- MSA optimization: With current footprint minus Ametha, the manufacturing services agreement between Ambuja and ACC is already optimized. Once Ametha comes in, the next set of optimization will happen. Sanghi, once acquired, will use a similar MSA arrangement.
Kapur: "And either those plants would be replaced by new kilns next door or we are going to either make investment or if nothing else, we will mouth ball them."
Financial Position
- Half-year performance strong: Revenue up 6.44% at INR16,137 crores; EBITDA up 107% to INR2,969 crores; EBITDA per ton INR1,042 (up 95%); margin expanded 8.9 percentage points to 18.4%.
- Ambuja standalone Q2: Net revenue up 8% at INR3,970 crores (volume growth 7.3%); EBITDA jumped 147% to INR773 crores; EBITDA per ton INR1,020 (up 130%); margin expanded 11% to 19.5%; PAT growth 364% to INR644 crores.
- Working capital improving: Receivables at 12 days of overall turnover; payables improved; overall working capital improved. Coal advances squared off: Ambuja coal advance zero last quarter, ACC coal advance zero in current quarter. MSA settlement changed from weekly/10-day to once a month at month-end to avoid multiple entries.
- Capex run-rate: Current year ~INR7,500 crores (ACC ~INR2,500, Ambuja ~INR5,000). Next year similar at INR7,000-8,000 crores, with some current capex rolling in, some fresh capex starting, and next stage of growth to be announced. Final bifurcation between ACC and Ambuja for next year not yet available.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capacity target | 14 crore tons cement production capacity | Before FY28 |
| Sanghi acquisition close | INR5,000 crores enterprise value, internal accruals | Q3 FY24 |
| Waste heat recovery | 170 MW operational (from 90 MW currently) | March '25 |
| Captive renewable power | 200 MW facility at Khavda, Gujarat | End of current financial year |
| Cost reduction | Over INR400/ton total reduction (INR300+ remaining) | 12-36 months |
| Sustainable EBITDA | INR1,450-1,500 per ton | 36 months (upper limit) |
| Lead distance | Reduce average primary road lead to ~100 km | Not specified |
| Bhatapara clinker facility | Equipment ordered, civil execution started | Q2 FY26 |
| Sankrail & Farakka grinding units | EPC vendor order placed, piling started | Q3 FY25 |
| Maratha clinker line | LOI placed, EC and CT approval expected this quarter | Q4 FY26 |
| Salai Banwa grinding unit | Ground breaking done | Q1 FY26 |
| Jalgaon & Amravati grinding units | 0.2 crore tons each | 24 months from Q2 FY24 |
| Volume growth | 10-12% per annum on current base | Annual |
| Capex (current year) | ~INR7,500 cr (ACC ~INR2,500, Ambuja ~INR5,000) | FY24 |
Key Metrics
| Metric | Q2 FY24 |
|---|---|
| Consolidated revenue | ₹7,424 cr, up 4.1% YoY |
| Consolidated realization | ₹5,334 per ton, up 0.9% YoY |
| Consolidated EBITDA excl. other income | ₹1,302 cr, up 298% YoY |
| Consolidated EBITDA per ton excl. other income | ₹995, up 291% YoY |
| Consolidated EBITDA margin | 17.5%, expanded 12.9 ppt YoY |
| Consolidated cash and cash equivalents | ₹11,721 cr as of 30 Sep 2023 |
| Consolidated capex | ₹1,101 cr for the quarter, funded from internal accruals |
| Ambuja standalone revenue | ₹3,970 cr, up 8% YoY, volume growth 7.3% |
| Ambuja standalone EBITDA excl. other income | ₹773 cr, up 147% YoY |
| Ambuja standalone EBITDA per ton excl. other income | ₹1,020, up 130% YoY |
| Ambuja standalone EBITDA margin | 19.5%, expanded 11 ppt YoY |
| Ambuja standalone PAT | ₹644 cr, up 364% YoY |
| ACC standalone EBITDA per ton gap vs Ambuja | ₹345 per ton, widened from ~₹220 last quarter |
| Power and fuel cost per ton | ₹1,425, down 33% YoY from ₹2,134 |
| Logistics cost per ton | ₹1,377, down 3.1% YoY from ₹1,421 |
| Other expenses per ton | ₹829, down 13.5% YoY from ₹958 |
| Premium products share of trade sales | 23.4%, up 0.8 ppt YoY |
| Blended cement share of total sales volume | 89%, maintained YoY |
| Direct dispatch share | 49%, up 5 ppt YoY |
| Rail coefficient | 28%, up 2 ppt YoY |
| Average primary road lead distance | 165 km, reduced from 175 km in Q2 FY23 |
| Waste heat recovery capacity | 90 MW as of Sep 2023, target 170 MW by Mar 2025 |
| Captive renewable power under construction | 200 MW, expected ready by end of FY24 |
| Captive coal mines capacity | 0.33 crore tons combined, covering 40–50% of current coal requirement |
| New limestone reserves won | 58.4 crore tons across 10 mines in 5 states |
| MSA volume between Ambuja and ACC | 0.24 crore tons, roughly 0.12 cr each, 95% cement |
| Clinker production, first half FY24 | 1.74 crore tons |
| Cost optimization target achieved | ~₹100 per ton of the ₹400 target realized, balance ₹300 to go; target expected to rise to ₹500 |
| Sustainable EBITDA per ton target | ₹1,450–1,500, expected within 36 months |
| Sanghi Industries acquisition enterprise value | ₹5,000 cr, expected to close in Q3 FY24 |
| Ametha integrated unit new clinker capacity | 0.33 crore tons per annum, commissioned |
| Bhatapara clinker facility | 0.4 crore tons, expected completion Q2 FY26 |
| Sankrail and Farakka grinding units | expected completion Q3 FY25 |
| Maratha clinker line, Chandrapur | 0.4 crore tons, expected completion Q4 FY26 |
| Salai Banwa grinding unit, Uttar Pradesh | expected completion Q1 FY26 |
| Mundra cement capacity | 0.45 crore tons, clinker capacity 0.23–0.24 crore tons |
| Marwar grinding unit | 0.24 crore tons |
| Full-year capex guidance | ~₹7,500 cr, ACC ~₹2,500 cr, Ambuja ~₹5,000 cr |
| Receivables days | 12 days of overall turnover |
| Coal advances | fully squared off, zero for both Ambuja and ACC |