ACC Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/knse9txcqiimxfmzzma3l3nq.pdf

Key Takeaways


Cost Transformation

Kapur: "So all those things will play out over 12 months to 36 months. Maybe earlier, but I think you can take 36 months as the last upper limit of that."

Volume Performance & Market Dynamics

Kapur: "We had not a very good July month. As you know, large part of our capacity north in Himachal, it was seriously flooded. It had some supply chain impact in the month of July. I think we also had very heavy monsoons in the central India."

Capacity Expansion & Projects

Kapur: "The Sanghi acquisition has two underlying strategies. First, it is a great asset at a great location and is very synergistic within our own ecosystem. Number two, it has 100 crore tons of limestone reserve, which allows us to increase clinker capacity in a very good location to help us cater to the West Coast."

ACC-Specific Turnaround

Kapur: "And either those plants would be replaced by new kilns next door or we are going to either make investment or if nothing else, we will mouth ball them."

Financial Position


Guidance & Commitments

CommitmentSpecificsTimeline
Capacity target14 crore tons cement production capacityBefore FY28
Sanghi acquisition closeINR5,000 crores enterprise value, internal accrualsQ3 FY24
Waste heat recovery170 MW operational (from 90 MW currently)March '25
Captive renewable power200 MW facility at Khavda, GujaratEnd of current financial year
Cost reductionOver INR400/ton total reduction (INR300+ remaining)12-36 months
Sustainable EBITDAINR1,450-1,500 per ton36 months (upper limit)
Lead distanceReduce average primary road lead to ~100 kmNot specified
Bhatapara clinker facilityEquipment ordered, civil execution startedQ2 FY26
Sankrail & Farakka grinding unitsEPC vendor order placed, piling startedQ3 FY25
Maratha clinker lineLOI placed, EC and CT approval expected this quarterQ4 FY26
Salai Banwa grinding unitGround breaking doneQ1 FY26
Jalgaon & Amravati grinding units0.2 crore tons each24 months from Q2 FY24
Volume growth10-12% per annum on current baseAnnual
Capex (current year)~INR7,500 cr (ACC ~INR2,500, Ambuja ~INR5,000)FY24

Key Metrics

MetricQ2 FY24
Consolidated revenue₹7,424 cr, up 4.1% YoY
Consolidated realization₹5,334 per ton, up 0.9% YoY
Consolidated EBITDA excl. other income₹1,302 cr, up 298% YoY
Consolidated EBITDA per ton excl. other income₹995, up 291% YoY
Consolidated EBITDA margin17.5%, expanded 12.9 ppt YoY
Consolidated cash and cash equivalents₹11,721 cr as of 30 Sep 2023
Consolidated capex₹1,101 cr for the quarter, funded from internal accruals
Ambuja standalone revenue₹3,970 cr, up 8% YoY, volume growth 7.3%
Ambuja standalone EBITDA excl. other income₹773 cr, up 147% YoY
Ambuja standalone EBITDA per ton excl. other income₹1,020, up 130% YoY
Ambuja standalone EBITDA margin19.5%, expanded 11 ppt YoY
Ambuja standalone PAT₹644 cr, up 364% YoY
ACC standalone EBITDA per ton gap vs Ambuja₹345 per ton, widened from ~₹220 last quarter
Power and fuel cost per ton₹1,425, down 33% YoY from ₹2,134
Logistics cost per ton₹1,377, down 3.1% YoY from ₹1,421
Other expenses per ton₹829, down 13.5% YoY from ₹958
Premium products share of trade sales23.4%, up 0.8 ppt YoY
Blended cement share of total sales volume89%, maintained YoY
Direct dispatch share49%, up 5 ppt YoY
Rail coefficient28%, up 2 ppt YoY
Average primary road lead distance165 km, reduced from 175 km in Q2 FY23
Waste heat recovery capacity90 MW as of Sep 2023, target 170 MW by Mar 2025
Captive renewable power under construction200 MW, expected ready by end of FY24
Captive coal mines capacity0.33 crore tons combined, covering 40–50% of current coal requirement
New limestone reserves won58.4 crore tons across 10 mines in 5 states
MSA volume between Ambuja and ACC0.24 crore tons, roughly 0.12 cr each, 95% cement
Clinker production, first half FY241.74 crore tons
Cost optimization target achieved~₹100 per ton of the ₹400 target realized, balance ₹300 to go; target expected to rise to ₹500
Sustainable EBITDA per ton target₹1,450–1,500, expected within 36 months
Sanghi Industries acquisition enterprise value₹5,000 cr, expected to close in Q3 FY24
Ametha integrated unit new clinker capacity0.33 crore tons per annum, commissioned
Bhatapara clinker facility0.4 crore tons, expected completion Q2 FY26
Sankrail and Farakka grinding unitsexpected completion Q3 FY25
Maratha clinker line, Chandrapur0.4 crore tons, expected completion Q4 FY26
Salai Banwa grinding unit, Uttar Pradeshexpected completion Q1 FY26
Mundra cement capacity0.45 crore tons, clinker capacity 0.23–0.24 crore tons
Marwar grinding unit0.24 crore tons
Full-year capex guidance~₹7,500 cr, ACC ~₹2,500 cr, Ambuja ~₹5,000 cr
Receivables days12 days of overall turnover
Coal advancesfully squared off, zero for both Ambuja and ACC