Archean Chemical Industries Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/jspinr7tjp3areix577mrsvq.pdf

Key Takeaways


The Cyclone: Damage, Accounting & Recovery

Pendurthi: "I think absolutely noted, I think the difficulty with something like salt is dissolves in water. And it takes us some time to precisely understand the extent of the loss."

Bromine: Demand Recovery Without a Declaration

Pendurthi: "I personally refrain from saying the worst is behind us because I think the global market is evolving in ways that most of us have not anticipated or seen."

The Deep-Tech Pivot: SiC Semiconductors & Zinc-Bromide Batteries

InvestmentStakeWhat Archean GetsCommercial Timeline
Clas-SIC Wafer Fab Ltd (UK)21.33% for GBP 1.5 crExclusivity in India for silicon carbide MOSFET power devices; first Indian company to invest in SiC device production capability2–3 years to manufacture high-quality SiC power devices
Offgrid Energy Labs Inc. (US, Delaware)21% for ~USD 1.2 cr (Series A)Access to zinc-bromide battery technology; option to set up giga factories in India or license the technology to others abroadPilot plant completion and commercial-scale demonstration on track; giga factory roadmap ~2 years
Pendurthi: "I think zinc-bromide technology is not new in that context. But I think what Offgrid has done and with their technical capabilities is found ways to make it, one, as we said, in terms of stability, in terms of cost and in terms of reliability, I think they have discovered something that is unique and possibly the only ones in the world who have done what they have done."

SOP: A Chemistry Problem, Now Solved on Paper


New Businesses: Early Traction, No Numbers Yet


Capex & Balance Sheet


Guidance & Commitments

CommitmentSpecificsTimeline
Industrial salt volume run rateExceed 0.1 crore tons per quarterH2 FY25 (coming quarters)
Bromine production (FY25)20,000+ metric tons (incl. captive use), with possible 10% variance from cycloneFY25
Bromine production (FY26)Likely around 20,000–25,000 tonsFY26
Oren Hydrocarbons plant restartTwo plants fully operational; meaningful business contributionsOperational in "next few weeks"; contributions from Q4 FY25
SOP production fixPilot tests with German partners, then plant-scale tests in GujaratBefore next monsoon
SiC power device manufacturingProduce high-quality SiC power devices2–3 years
Zinc-bromide battery commercializationPilot plant completion, then giga factory roadmapPilot on track; giga factory ~2 years
Return on capital for SiC ventureAnswer once government approval and incentive clarity received"A couple of months"

Key Metrics

MetricQ2 FY25
Total revenue₹252.1 crore, down ~17% YoY
Export revenue share77% of total revenue, domestic 23%
Bromine revenue share38% of total revenue
Industrial Salt revenue share62% of total revenue
EBITDA₹89.8 crore, margin 36%
Net profit₹21.9 crore
Exceptional item (Cyclone Asna)₹40.18 crore loss, 472,000 metric tons of Industrial Salt damaged
H1 FY25 total revenue₹475.4 crore, down ~28% YoY
H1 FY25 net profit₹70.3 crore
Industrial Salt volume7.5 lakh tons, vs 9.76 lakh tons in Q2 FY24
Bromine sales volume4,800+ tons
Sulphate of Potash sales volume27 tonnes
Bromine production aim (full year FY25)In excess of 20,000 metric tons, including captive use
Bromine production projection (FY26)20,000–25,000 tons
Capex expected (next 6 months)₹50–75 crore at the very most