ACME Solar Holdings Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/68t2nkqli7djpowil7p0oy0a.pdf

Key Takeaways


The Battery Strategy: Import, Own, and Derisk

Manoj Upadhyay: "We wanted to abuse this -- abuse the testing, so we connected to 33 kV and tested all the variation possible in this one, and I'm proud to share with you that it worked very well for so many years."

PPA Pipeline and Revenue Visibility

Nikhil Dhingra: "It is explicitly mentioned in most of the PPAs. But wherever there is a vagueness, we have taken the explicit NOC from these counterparties because it is not a source. It's just a storage resource."

Under-Construction Portfolio and Commissioning Timeline


Financing Costs and Balance Sheet

Nikhil Dhingra: "There is an interplay of two things here. One is the overall macro and the other is the micro of improvement of our we listed last year and of course our rating has gone up for all our projects. So, both these interplay will take our interest costs further down because as we accessed capital markets and we also understand that there is an arbitrage between the capital markets and the bank loan market also."

Operational Performance and Efficiency Gains

Manoj Upadhyay: "From the next project onwards, we should be able to reduce our land requirement by 15%, 20% time, which means that existing land in the high radiation can accommodate 15%, 20% more solar."

Technology and Innovation Pipeline


Guidance & Commitments

CommitmentSpecificsTimeline
PPA pipeline conclusionEntire pipeline of PPAs to be signedWithin 4 months
Battery order completionClose remaining 2 GWh of battery ordersNext month or so
Capex order closureClose orders for ~₹14,000 cr of capexThis year (FY26)
Debt tie-up for 2.2 GWFully tied up for all 2.2 GW of under-construction PPA portfolioNext quarter
Interest cost reductionSignificant reduction, RBI 50 bps magnitude reasonable to assumeBy end of FY26
Capacity addition for revenue450 MW of capacity and ~2.5 GWh of battery component of FDRE projectsFY26
2.2 GW PPA commissioningStaggered across FY26 and FY27, no significant delayBy FY27
NHPC BESS commissioning18 months from June; aiming for early commissioning, within 6 months of state go-aheadBy December 2026 (18 months) or earlier
FDRE battery commissioningBattery component of FDRE projectsQ3 and Q4 FY26
Land requirement reductionReduce land requirement by 15%–20%From next project onwards
Perovskite second-stage resultsShare results from 50–100 kW testingNext 2–3 months
Net debt to EBITDA ceilingMaintain at or below 5.5x at all timesOngoing

Key Metrics

MetricQ1 FY26
Total revenue₹584 cr, +72% YoY
EBITDA₹531 cr, +76% YoY
EBITDA margin91%, aided by operational capacity growth and cost reduction
PAT₹131 cr
Net operational debt to EBITDA4.2x, within guided range of 5.5x
Net debt to net worth1.7x
Days sales outstanding36 days, down from prior periods
Operational portfolio2,890 MW, including 350 MW commissioned in Q1
Units generated163 crore units, +107% YoY
Capacity utilization factor28.5%, improved from 27% last year
Rajasthan CUF30.3%, for 2,250 MW of operational portfolio
Under-construction portfolio4,080 MW plus 550 MWh of storage, 55% with signed PPAs
PPAs signed in Q1550 MW of FDRE and solar, 550 MWh of standalone BESS
Purchase orders placed for under-construction portfolio₹7,000 cr
FY26 capex guidance₹12,000–₹14,000 cr, with similar number expected next year
Q1 capex incurred~₹800 cr
Interest cost on operating portfolio~8.75%
Refinancing disbursement₹1,070 cr for 250 MW operational project at 8.5% fixed for 5 years, 95 bps reduction
Central off-takers in portfolio86%
BESS project capex$100 per kWh, landed price including duties, logistics, BOS, transformer
BESS project IRRhigh-teens, above 16%
Battery orders placed3.1 GWh, catering to 50% of demand for 2.3 GW contracted portfolio
Total battery requirement for 4 GW under construction~10 GWh
Peak tariff reference (last 12 months)~₹9 for 1-hour average, ₹8.78 for 2-hour average
India Q1 renewable capacity addition12 GW (10.6 GW solar, 1.6 GW wind), total installed 234 GW including large hydro
India Q1 power demand44,600 crore units, ~1% YoY decline
India Q1 peak power demand242 GW, 3.2% decline YoY