Key Takeaways
- Earnings surge on capacity ramp: Revenue rose 72% YoY to ₹584 crores and EBITDA rose 76% to ₹531 crores, driven by a doubling of generation and new project commissioning.
- Balance sheet is a deliberate strength: Net operational debt to EBITDA held at 4.2x, well inside the 5.5x ceiling, while DSO improved to 36 days as central off-takers grew to 86% of the portfolio.
- The battery bet is now locked in: Purchase orders for over 3.1 GWh of BESS are placed at frozen prices, and management is choosing full-container imports over local assembly to protect warranty and reliability.
- PPA pipeline is converting, not just growing: PPAs for 550 MW of FDRE/solar and 550 MWh of standalone BESS were signed in the quarter, and management expects the entire pipeline to be concluded within four months.
- What to watch next quarter: Whether the remaining 2 GWh of battery orders close on schedule, the pace of PPA signings for the 45% of the under-construction portfolio still uncontracted, and any flow-through from the RBI’s 50 bps rate cut into refinanced debt costs.
The Battery Strategy: Import, Own, and Derisk
- Full-container import over local assembly: Management evaluated importing cells and assembling in India but found the cost saving is only ~2.4% of overall project cost, a margin it considers too thin to justify sacrificing the warranty and reliability of a fully integrated Chinese containerized solution.
- Insurance gap reinforces the choice: The Indian insurance sector has not yet developed wrap-around products to cover the performance risk of locally assembled battery systems, so the warranty from a single integrated vendor is the primary risk mitigation tool.
- BESS ownership model for NHPC: ACME will own the battery asset and receive lease rentals from NHPC, which supplies the energy; ACME stores it for the Andhra Pradesh government and maintains an SLA on availability and output, a structure that avoids evacuation substation capex by installing at the customer’s premises.
- Early-commissioning economics are attractive: The BESS portion of the contracted portfolio is being commissioned ahead of schedule, with peak tariffs around ₹9 for a 1-hour average and ₹8.78 for a 2-hour average, producing good economics against reference capex.
- Battery price risk is frozen: ACME has sealed battery prices for the 3.1 GWh already ordered, insulating that portion of the pipeline from future price movements.
- Testing deliberately stressed the system: The company connected its battery to a poor-quality 33 kV grid instead of the normal 400 kV or 220 kV to test power electronics reliability, and reports the system performed well over multiple years of manual and automatic operation.
Manoj Upadhyay: "We wanted to abuse this -- abuse the testing, so we connected to 33 kV and tested all the variation possible in this one, and I'm proud to share with you that it worked very well for so many years."
PPA Pipeline and Revenue Visibility
- Signing pace accelerated: 550 MW of FDRE and solar PPAs plus 550 MWh of standalone BESS PPAs were signed in Q1, and management expects the entire pipeline to be concluded within another four months with similar traction this quarter.
- Key PPAs nearing closure: The Omega Urja PPA with SJVN has received Madhya Pradesh regulatory consent and is expected to sign in July or August; the SECI hybrid PPA involving Bihar and Uttar Pradesh has gone to the regulator and is expected in August; Urja One and Platinum Urja One are in advanced stages with MP and Chhattisgarh.
- NTPC FDRE discussion underway: NVVN is considering buying directly rather than selling on a pooled basis, a proposal still under discussion that could alter the offtake structure.
- NHPC BESS PPA structure explained: NHPC first signed a power supply agreement with Andhra Pradesh, then signed with ACME; PPAs do not get signed until the state-level power supply agreement is in place, which is now done.
- 100% PPA-tied portfolio insulates from demand softness: India’s Q1 power demand declined ~1% YoY and peak demand declined 3.2% YoY due to an early monsoon and a high base, but management notes the business is entirely PPA-linked and therefore not impacted.
- No backup instruction risk: The company briefly sold one 300 MW plant on the merchant market for 1–2 months before signing its PPA with SECI and saw tariffs drop due to lower demand, but 100% of capacity is now PPA-tied.
Nikhil Dhingra: "It is explicitly mentioned in most of the PPAs. But wherever there is a vagueness, we have taken the explicit NOC from these counterparties because it is not a source. It's just a storage resource."
Under-Construction Portfolio and Commissioning Timeline
- Scale of the build-out: 4,080 MW plus 550 MWh of storage is under construction, with 55% already covered by signed PPAs and grid connectivity secured for the entire portfolio.
- FDRE commissioning is staggered: Partial commissioning of the battery component happens this year (Q3 and Q4), solar commissioning follows in the June–September quarter, and full FDRE commissioning arrives next year.
- 2.2 GW PPA portfolio on track for FY27: Commissioning will be staggered across FY26 and FY27 with no significant delay expected; connectivity timelines are aligned.
- NHPC BESS has an 18-month clock from June: Management is aiming for early commissioning and is working with the Andhra Pradesh government on readiness; once the state gives the go-ahead, ACME can commission within six months.
- FDRE battery revenue is substantially larger than NHPC: At 550 MWh, the FDRE battery component is roughly five times the size of the NHPC project, with substantially higher revenue and profit, though management declined to guide on peak revenue since it is a merchant-based project.
- Capex cycle is in full swing: Purchase orders exceeding ~₹7,000 crores were placed in Q1, and the company plans to close orders for approximately ₹14,000 crores of capex this year; Q1 capex done was ₹800 crores, with the difference reflecting the order-to-execution cycle.
- Debt tie-up is deliberately paced: Debt sanctions are on time with multiple offers per project, but management has consciously deferred taking sanctions for some projects to sync disbursement timelines with capex timelines, since lenders want disbursement within six months or debt needs revalidation; all 2.2 GW will be fully tied up next quarter.
Financing Costs and Balance Sheet
- Refinancing delivered a 95 bps reduction: ₹1,070 crores was refinanced for a 250 MW operational project at 8.5% fixed for five years, bringing in Bank of America, Standard Chartered, and India Infradebt Limited as new lenders.
- Further interest cost reduction expected by FY26-end: The RBI’s 50 bps rate cut has not yet flowed through because some projects have annual resets that have not arrived and most ISTS projects have not yet been refinanced; management considers it reasonable to assume that magnitude of reduction over the next 6–8 months.
- Capital markets access is the next lever: Three ISTS projects remain to be refinanced, and management sees an arbitrage between capital markets and bank loan markets that could reduce costs further, encouraged by the AA- family rating now secured on four SECI assets totaling 1,200 MW.
- Credit rating trajectory is positive: The company expects ratings to remain consistently in the AA family for projects, given the contribution of central REIA counterparties, and is increasingly focused on capital markets as a funding source.
- Net debt to EBITDA held at 4.2x: Well within the guided ceiling of 5.5x, with net debt to net worth at 1.7x, reflecting what management calls a disciplined approach to growth.
Nikhil Dhingra: "There is an interplay of two things here. One is the overall macro and the other is the micro of improvement of our we listed last year and of course our rating has gone up for all our projects. So, both these interplay will take our interest costs further down because as we accessed capital markets and we also understand that there is an arbitrage between the capital markets and the bank loan market also."
Operational Performance and Efficiency Gains
- CUF improved to 28.5% from 27% YoY: The Rajasthan portfolio of 2,250 MW delivered a particularly strong 30.3% CUF, while total generation more than doubled to 163 crore units.
- Operational portfolio EBITDA run-rate: The 2,890 MW operational portfolio is capable of delivering annual steady-state project-level EBITDA of ₹2,000–₹2,050 crores, implying an EBITDA yield of 14%–15%.
- DSO dropped to 36 days: The improvement was helped by central off-takers growing to 86% of the portfolio, reducing collection risk.
- Land optimization in the pipeline: ACME is working on a new configuration to reduce land requirement by 15%–20% from the next project onwards, allowing existing high-radiation land to accommodate 15%–20% more solar capacity, a meaningful advantage as high-radiation zones become scarcer.
- Connectivity strategy is proactive: The company sources connectivity independent of and prior to bids, de-linking PPA signing from connectivity timelines; it has taken connectivity only at locations with the highest GHI in each state and is diversifying across Rajasthan, Andhra Pradesh, and Karnataka to match PPA commissioning timelines.
- No HVDC dependency in the current pipeline: Projects under construction with connectivity available in 2026 and 2027 are not dependent on HVDC; projects planned for 2027–28 have connectivity based on bids yet to be won; only connectivity for 2029–30 is dependent on HVDC, and the government is aiming to commission HVDC prior to 2030, possibly in 2029.
Manoj Upadhyay: "From the next project onwards, we should be able to reduce our land requirement by 15%, 20% time, which means that existing land in the high radiation can accommodate 15%, 20% more solar."
Technology and Innovation Pipeline
- Perovskite testing is advancing: ACME started with a few hundred watts of perovskite testing and is happy with performance; it is moving to the second level of 50–100 kW in the next 3–4 months, with results expected in 2–3 months, before final installation happens in the November–February window.
- 10 MWh pilot battery installation: A 10 MWh battery will be installed in the next two months and will go through operational testing before the larger projects are commissioned, serving as a real-world validation step.
- FDRE execution risk is concentrated in wind: Management characterizes FDRE execution as not challenging overall, but flags wind resource assessment as a complication from a risk perspective; the company is minimizing the wind component to reduce variability.
- Battery is explicitly not a generation source in PPAs: Most PPAs explicitly state this, and where there is ambiguity, ACME has obtained explicit NOCs from counterparties, which is critical for the early-commissioning strategy.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| PPA pipeline conclusion | Entire pipeline of PPAs to be signed | Within 4 months |
| Battery order completion | Close remaining 2 GWh of battery orders | Next month or so |
| Capex order closure | Close orders for ~₹14,000 cr of capex | This year (FY26) |
| Debt tie-up for 2.2 GW | Fully tied up for all 2.2 GW of under-construction PPA portfolio | Next quarter |
| Interest cost reduction | Significant reduction, RBI 50 bps magnitude reasonable to assume | By end of FY26 |
| Capacity addition for revenue | 450 MW of capacity and ~2.5 GWh of battery component of FDRE projects | FY26 |
| 2.2 GW PPA commissioning | Staggered across FY26 and FY27, no significant delay | By FY27 |
| NHPC BESS commissioning | 18 months from June; aiming for early commissioning, within 6 months of state go-ahead | By December 2026 (18 months) or earlier |
| FDRE battery commissioning | Battery component of FDRE projects | Q3 and Q4 FY26 |
| Land requirement reduction | Reduce land requirement by 15%–20% | From next project onwards |
| Perovskite second-stage results | Share results from 50–100 kW testing | Next 2–3 months |
| Net debt to EBITDA ceiling | Maintain at or below 5.5x at all times | Ongoing |
Key Metrics
| Metric | Q1 FY26 |
|---|---|
| Total revenue | ₹584 cr, +72% YoY |
| EBITDA | ₹531 cr, +76% YoY |
| EBITDA margin | 91%, aided by operational capacity growth and cost reduction |
| PAT | ₹131 cr |
| Net operational debt to EBITDA | 4.2x, within guided range of 5.5x |
| Net debt to net worth | 1.7x |
| Days sales outstanding | 36 days, down from prior periods |
| Operational portfolio | 2,890 MW, including 350 MW commissioned in Q1 |
| Units generated | 163 crore units, +107% YoY |
| Capacity utilization factor | 28.5%, improved from 27% last year |
| Rajasthan CUF | 30.3%, for 2,250 MW of operational portfolio |
| Under-construction portfolio | 4,080 MW plus 550 MWh of storage, 55% with signed PPAs |
| PPAs signed in Q1 | 550 MW of FDRE and solar, 550 MWh of standalone BESS |
| Purchase orders placed for under-construction portfolio | ₹7,000 cr |
| FY26 capex guidance | ₹12,000–₹14,000 cr, with similar number expected next year |
| Q1 capex incurred | ~₹800 cr |
| Interest cost on operating portfolio | ~8.75% |
| Refinancing disbursement | ₹1,070 cr for 250 MW operational project at 8.5% fixed for 5 years, 95 bps reduction |
| Central off-takers in portfolio | 86% |
| BESS project capex | $100 per kWh, landed price including duties, logistics, BOS, transformer |
| BESS project IRR | high-teens, above 16% |
| Battery orders placed | 3.1 GWh, catering to 50% of demand for 2.3 GW contracted portfolio |
| Total battery requirement for 4 GW under construction | ~10 GWh |
| Peak tariff reference (last 12 months) | ~₹9 for 1-hour average, ₹8.78 for 2-hour average |
| India Q1 renewable capacity addition | 12 GW (10.6 GW solar, 1.6 GW wind), total installed 234 GW including large hydro |
| India Q1 power demand | 44,600 crore units, ~1% YoY decline |
| India Q1 peak power demand | 242 GW, 3.2% decline YoY |