Key Takeaways
- Record quarter, BESS scaling fast: Highest-ever revenue and EBITDA, with BESS contributing INR226 crores in power sales and cumulative commissioned capacity reaching 3.62 GWh, roughly 40% of India's total.
- BESS guidance pulled forward sharply: The 10 GWh commissioning target moved up by nearly three quarters to March 2027, and management plans to keep at least 10 GWh of batteries exposed to the merchant market annually for the next five years.
- Capex doubled on QIP proceeds: Full-year FY27 capex guidance upgraded to INR15,000–20,000 crores, funded by a completed QIP, to prepone under-construction projects and capture better return economics.
- Margins are strong but the BESS mix is a drag: Ex-BESS EBITDA margin was around 88–89%, but consolidated margin settled at 87% because BESS carries an ~82% margin versus ~88–89% for renewables, and management declined to give a firm full-year margin number.
- What to watch next quarter: Whether the 20% of BESS capacity still un-contracted gets tied up, the pace of PPA signings for the balance 1,200 MW of projects, and any concrete update on the data center segment entry.
BESS: The Growth Engine
- Commissioning cadence accelerated: ~2.3 GWh commissioned during the quarter, taking cumulative capacity to 3.62 GWh; the full-year target is now more than 10 GWh by March 2027, pulled forward from calendar year 2027, with an upward bias because contracting already exceeds 10 GWh.
- Revenue locked in, with room to run: Around 70–80% of BESS capacity is contracted for the year, generating INR1,400 crores of revenue; tying up the remaining 20% would take that figure higher, and management sees the INR1,400 cr+ run-rate as reasonable for the next 2–3 years.
- Merchant exposure is structural, not residual: Every year, at least 10 GWh of battery will sit in the merchant market in year one before moving into PPAs; management's five-year plan keeps 10–12 GWh available for short-term power annually, and pure merchant supply will stay tight because plants rotate into PPAs and new execution cycles.
- Operational performance beat design: Round-trip efficiency at ~89%, depth of discharge at ~93%, state of health above 99.9%, and plant availability above 99%, all exceeding design expectations.
- Suryodaya fire contained, no battery damage: Root cause analysis confirmed an electrical short circuit in AC cabling between the transformer and power conversion system; safety measures already deployed prevented damage to battery systems, and new measures including AI-enabled video analytics and arc-flash sensors have been added.
- BESS pricing strength has a three-year runway: Management sees no slowdown in pricing for the next three years, driven by states not yet buying BESS power, a deepening duck curve, AC penetration, and limited alternatives with gas peakers and pump storage still 3–4 years away.
Nikhil Dhingra: "We aim to have 0 open capacity by end of this year. We don't want to operate any merchant outside of PPA."
Capital Allocation & Costs
- Capex guidance doubled: Full-year FY27 capex upgraded to INR15,000–20,000 crores, with the completed QIP providing flexibility to prepone under-construction projects and improve return economics.
- Battery procurement timed to capture a window: Management views this year as a good time to buy batteries because China is imposing a 6% export tax from January, and earlier procurement benefits merchant market participation; more than 15 GWh of batteries have already been ordered from CATL and Hithium within budgeted cost.
- BESS capital cost and the inflation risk: Capitalized BESS cost is around INR93 lakhs per megawatt all-in; future costs could rise 5–10% due to lithium carbonate volatility and China supply-demand dynamics, but management says this stays within budget because other components like PCS are coming in lower than budgeted, and hedging gains from over $300 million locked at INR89–93 provide a positive bias.
- Module buying is opportunistic: From now until December is a good window to buy modules with Chinese cells at sub-INR12 levels; management will balance opportunistic purchasing with minimizing interest during construction, and will not buy modules where solar GNA is unavailable because stranding them is IRR-decretive.
- Financing nearly complete for the PPA portfolio: Debt tied up for nearly 85% of the PPA-signed portfolio, with INR6,000 crores secured for 700 MW of under-construction FDRE projects during the quarter.
Nikhil Dhingra: "It is prudent to plan such that you only supply where your lines are complete — all the elements of the line are ready, right? You right-size your plant."
PPA Pipeline & Bidding Environment
- Two PPAs signed this quarter: One hybrid project where the change offered was 1 hour of battery instead of the standard configuration, and a second project at INR6.28 per unit with no configuration change.
- ACME Marigold PPA imminent: A bank guarantee has been given and the PPA with a Northeast state is expected to be signed "very, very shortly"; the delay stemmed from railway open-access status being revised by the Supreme Court. [11–12]
- Balance 1,200 MW progressing: Projects for which PPAs are yet to be signed are progressing well and expected to be signed soon.
- Bid format has structurally shifted: No solar-only bids are expected going forward; battery-related bids will be the focus, and no renewable bid other than pump storage will come without battery; rightsizing of battery bids is expected due to delays in VGF-based projects. [10–11]
- Government-backed bid revival expected: SECI-backed bids are expected to come in strongly in the next 6–9 months, with states, CFDs, and peak power bids also reviving; SECI is consolidating bids and cycle time from bid to PPA will reduce.
- CERC free exit a positive catalyst: The new free exit option allowing merchant route conversion for projects without signed PPAs will free up connectivity, enabling ACME to access high-GHI connectivity it could not have otherwise obtained and helping CTU plan future connectivity better. [9–10]
- Curtailment nearly eliminated: Curtailment was less than 1% of overall revenue, affecting only state-based projects; a new ministry circular now allows surplus solar generation to be stored in batteries, and ACME plans to add batteries to all state projects to eliminate curtailment entirely.
Demand & Market Structure
- Peak power gap is large and growing: Current peak demand gap estimated at 300 GWh, expected to push toward 400–500 GWh and potentially touch 1 TWh as more rooftop solar, KUSUM, and B2B solar deepen the duck curve and push evening and morning peaks higher. [14–15]
- Trust in battery storage is building state by state: Management noted that low trust in battery technology among suppliers and buyers is gradually being overcome as fine supply capability is demonstrated, and this trust-building is happening on a state-by-state basis.
- Sodium battery progress could reshape economics: Sodium batteries are making good progress and could increase battery life closer to pump storage timelines, positively impacting peak power profitability dynamics. [20–21]
- Q1 electricity demand up 8.8% YoY: Driven by expanding economic activity, delayed monsoons, and elevated cooling demand; peak demand hit 271 GW.
Manoj Kumar Upadhyay: "My own conclusion right now tells is around 300-gigawatt hour, but I see that it will get pushed towards — as we are adding more solar... the evening and morning peak will push towards the higher side. So I see that we will be close to 400 to 500 gigawatt hour. In the positive scenario, it may touch even 1 terawatt hour kind of a situation." [14–15]
Margins & Mix
- Consolidated margin settled at 87%: BESS EBITDA margin of ~82% dragged consolidated margins below the ~88–89% renewable-only level because the cost of power purchased for charging batteries sits inside operating expenses.
- Core renewable margin stable at 91%: Ex-BESS EBITDA margin held at 91%, consistent with the 90–91% range of recent quarters, with seasonal variation driving an 88–91% band.
- FDRE projects may lift margins: Upcoming FDRE projects carry healthier realizations than plain solar bids, which could revise core EBITDA margin upward.
- No firm full-year margin guidance: Management said Q1 is a slightly better quarter, commissioning happened in a staggered manner, and interest and depreciation need to be watched; they gave a rough range of maybe 2–5% variation but declined to provide a firm full-year number.
- Battery depreciation and interest: Q1 battery interest was around INR32 crores and depreciation around INR27 crores, using a 20-year depreciation policy for batteries.
New Ventures & Optionality
- Data center entry being built from scratch: Management is hiring and building capabilities for the data center segment, which it views as very promising; the focus is on long-term concessions where infrastructure strengths align, but profitability metrics are still being worked out on both the cost and pricing sides, and an update will come when concrete. [18–19]
- C&I and non-government use cases under exploration: ACME is actively exploring CTU-connected C&I customers and has a definite plan to enter other non-government use cases, but will not dilute mid-teen to high-teen return targets; an update will come when concrete.
- SECI data center procurement could open a path: SECI is creating a platform to work with data centers to procure power; if SECI becomes the aggregator or customer, ACME will happily participate in those bids.
Nikhil Dhingra: "The thing — only thing right now, which we are figuring out is the profitability metrics because the profitability we are seeing, of course, in terms of the headlines, it is a good headline, but the profitability is something which we need to — I think both on the cost side and on the pricing side, we need to really work to make the right amount of profitability and using the competencies we have."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| BESS commissioning | More than 10 GWh cumulative capacity (upward bias possible) | By March 2027 (pulled forward from CY27 by nearly 3 quarters) |
| Renewable capacity commissioning | 1.5 GW of contracted renewable generation capacity, subject to timely substation and transmission line availability | FY27 |
| BESS merchant exposure | At least 10–12 GWh of batteries available for short-term power market annually (first year merchant, then moving into PPA) | Each year for next 5 years |
| BESS capacity contracting | 0 open BESS capacity (all inside PPA except one 300 MW plant yet to be contracted) | By end of FY27; from a long-term perspective, BESS is not open other than that plant |
| Capex | INR15,000–20,000 crores | FY27 |
| ACME Marigold PPA | PPA signing with Northeast state | "Very, very shortly" [11–12] |
| Balance PPA portfolio | ~1,200 MW of projects for which PPAs are yet to be signed | Expected to be signed "soon" |
| Government-backed bid revival | SECI/state/CFD/peak power bids to come in strongly | Next 6–9 months and beyond |
| BESS pricing strength | No slowdown expected in BESS pricing | Next 3 years |
| BESS revenue run-rate | INR1,400 cr+ annual BESS revenue assumption reasonable, subject to PPA pipeline and returns | Next 2–3 years |
| Target capacity beyond 10 GW | Contemplate increasing target beyond 10 GW, basis new growth opportunities | By 2030; update in coming quarters |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Total revenue | ₹954 cr, up 63% YoY |
| EBITDA | ₹831 cr, up 56% YoY |
| Total EBITDA margin | ~87% |
| Renewable energy EBITDA margin | ~88%–89% |
| BESS business EBITDA margin | ~82% |
| Profit after tax | ₹235 cr, up 80% YoY |
| PAT margin | ~25% |
| Asset base | ~₹25,000 cr |
| Q1 capex incurred | ~₹3,000 cr |
| Full-year FY27 capex guidance | ~₹15,000 cr to ₹20,000 cr, upgraded |
| BESS power sales revenue | ₹226 cr, ~85% from short-term contracts, balance merchant |
| Short-term BESS contracts secured | more than ₹1,400 cr of revenue locked in for partial FY27 BESS commissioned capacity |
| BESS annual EBITDA to capex yield | more than 20% |
| Cumulative commissioned BESS capacity | ~3.62 GWh, ~40% share of India's cumulative commissioned BESS capacity till date |
| BESS commissioning guidance | more than 10 GWh by fiscal year 2027, upgraded from 10 GWh by calendar year 2027 |
| Capacity utilization factor | 30.9%, highest in company history, vs 28.5% in Q1 FY26 |
| Power generation | 202 crore units, up 23% YoY |
| Total PPA signed capacity | 3,880 MW out of 5,080 MW under-construction capacity |
| FDRE and hybrid PPAs signed with SECI during quarter | 600 MW |
| Total portfolio | 8,070 MW, entailing ~20 GWh of battery storage |
| Financing secured during quarter | ~₹6,000 cr for 700 MW of under-construction FDRE projects |
| Debt tied up for PPA-signed portfolio | nearly 85% |
| BESS round-trip efficiency | ~89% |
| BESS depth of discharge | ~93% |
| BESS state of health | more than 99.9% |
| BESS plant availability | more than 99% |
| BESS short-term contract realizations | ₹8 to ₹10 per unit, depending on month and volume |
| Capitalized BESS cost | ~₹93 lakhs per megawatt, including transformer and everything |
| Battery ordered from global suppliers | more than 15 GWh from CATL and Hithium, within budgeted cost |
| FY27 expected renewable energy generation capacity commissioning | 1.5 GW, subject to timely availability of substation and transmission lines |
| Curtailment impact | less than 1% of revenue, from state-based projects only |
| Core EBITDA margin (ex-BESS) | 91% for the quarter, typical range 88% to 92% |