ACME Solar Holdings Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/51e0egptljjeviy3x7xvcbh7.pdf

Key Takeaways


BESS: The Growth Engine

Nikhil Dhingra: "We aim to have 0 open capacity by end of this year. We don't want to operate any merchant outside of PPA."

Capital Allocation & Costs

Nikhil Dhingra: "It is prudent to plan such that you only supply where your lines are complete — all the elements of the line are ready, right? You right-size your plant."

PPA Pipeline & Bidding Environment


Demand & Market Structure

Manoj Kumar Upadhyay: "My own conclusion right now tells is around 300-gigawatt hour, but I see that it will get pushed towards — as we are adding more solar... the evening and morning peak will push towards the higher side. So I see that we will be close to 400 to 500 gigawatt hour. In the positive scenario, it may touch even 1 terawatt hour kind of a situation." [14–15]

Margins & Mix


New Ventures & Optionality

Nikhil Dhingra: "The thing — only thing right now, which we are figuring out is the profitability metrics because the profitability we are seeing, of course, in terms of the headlines, it is a good headline, but the profitability is something which we need to — I think both on the cost side and on the pricing side, we need to really work to make the right amount of profitability and using the competencies we have."

Guidance & Commitments

CommitmentSpecificsTimeline
BESS commissioningMore than 10 GWh cumulative capacity (upward bias possible)By March 2027 (pulled forward from CY27 by nearly 3 quarters)
Renewable capacity commissioning1.5 GW of contracted renewable generation capacity, subject to timely substation and transmission line availabilityFY27
BESS merchant exposureAt least 10–12 GWh of batteries available for short-term power market annually (first year merchant, then moving into PPA)Each year for next 5 years
BESS capacity contracting0 open BESS capacity (all inside PPA except one 300 MW plant yet to be contracted)By end of FY27; from a long-term perspective, BESS is not open other than that plant
CapexINR15,000–20,000 croresFY27
ACME Marigold PPAPPA signing with Northeast state"Very, very shortly" [11–12]
Balance PPA portfolio~1,200 MW of projects for which PPAs are yet to be signedExpected to be signed "soon"
Government-backed bid revivalSECI/state/CFD/peak power bids to come in stronglyNext 6–9 months and beyond
BESS pricing strengthNo slowdown expected in BESS pricingNext 3 years
BESS revenue run-rateINR1,400 cr+ annual BESS revenue assumption reasonable, subject to PPA pipeline and returnsNext 2–3 years
Target capacity beyond 10 GWContemplate increasing target beyond 10 GW, basis new growth opportunitiesBy 2030; update in coming quarters

Key Metrics

MetricQ1 FY27
Total revenue₹954 cr, up 63% YoY
EBITDA₹831 cr, up 56% YoY
Total EBITDA margin~87%
Renewable energy EBITDA margin~88%–89%
BESS business EBITDA margin~82%
Profit after tax₹235 cr, up 80% YoY
PAT margin~25%
Asset base~₹25,000 cr
Q1 capex incurred~₹3,000 cr
Full-year FY27 capex guidance~₹15,000 cr to ₹20,000 cr, upgraded
BESS power sales revenue₹226 cr, ~85% from short-term contracts, balance merchant
Short-term BESS contracts securedmore than ₹1,400 cr of revenue locked in for partial FY27 BESS commissioned capacity
BESS annual EBITDA to capex yieldmore than 20%
Cumulative commissioned BESS capacity~3.62 GWh, ~40% share of India's cumulative commissioned BESS capacity till date
BESS commissioning guidancemore than 10 GWh by fiscal year 2027, upgraded from 10 GWh by calendar year 2027
Capacity utilization factor30.9%, highest in company history, vs 28.5% in Q1 FY26
Power generation202 crore units, up 23% YoY
Total PPA signed capacity3,880 MW out of 5,080 MW under-construction capacity
FDRE and hybrid PPAs signed with SECI during quarter600 MW
Total portfolio8,070 MW, entailing ~20 GWh of battery storage
Financing secured during quarter~₹6,000 cr for 700 MW of under-construction FDRE projects
Debt tied up for PPA-signed portfolionearly 85%
BESS round-trip efficiency~89%
BESS depth of discharge~93%
BESS state of healthmore than 99.9%
BESS plant availabilitymore than 99%
BESS short-term contract realizations₹8 to ₹10 per unit, depending on month and volume
Capitalized BESS cost~₹93 lakhs per megawatt, including transformer and everything
Battery ordered from global suppliersmore than 15 GWh from CATL and Hithium, within budgeted cost
FY27 expected renewable energy generation capacity commissioning1.5 GW, subject to timely availability of substation and transmission lines
Curtailment impactless than 1% of revenue, from state-based projects only
Core EBITDA margin (ex-BESS)91% for the quarter, typical range 88% to 92%