Key Takeaways
- Listing quarter, operational momentum: The company listed on 13 November 2024 and simultaneously energized its 1,800 MW ISTS plant, which was already generating daily revenues of ~₹1.5 crores and operating at ~85% capacity.
- Capacity doubled, execution risk now the focus: Installed capacity jumped from ~1.3 GW to 2.5 GW AC, with another 4.2 GW under construction targeted for commissioning by FY27. The funding plan leans on IPO proceeds, operating cash flows and in-house EPC savings, with management stating no current need for an equity raise.
- Margins dipped on ramp-up costs: H1 EBITDA margin saw a marginal dip, driven by higher manpower expenses as the company staffed up to deliver its under-construction pipeline.
- Growth is being deliberately modulated: Management's bias is toward consolidation, not aggressive bidding, and it will calibrate growth to sustain mid-teen hurdle rates and a manageable debt-to-EBITDA profile.
- What to watch next quarter: The pace of PPA signings for the 680 MW NHPC and remaining SECI tranches, the capitalization and disclosed economics of the 1,200 MW plant, and any movement on the three sanctioned refinancings that are yet to be disbursed.
The 1,800 MW Plant: A Milestone with Near-Term Upside
- Early energization: The ISTS-connected SECI plant, carrying four PPAs at ₹2.44 per KWh, was scheduled for a March 2025 COD but went live starting October/November 2024. Management sees peak revenue arriving within a month of the call.
- Revenue contribution: The plant was generating ~₹1.5 crores per day as of 20 November, implying an annualized run-rate of ~₹550 crores even before reaching full output.
- Pre-commissioning accounting shift: A change in law means pre-commissioning power sales now flow through the P&L rather than being netted against project cost, making the revenue contribution visible earlier than under the old standard.
- Location advantage: The plant sits in Fatehgarh, the highest-sunlight zone in the portfolio, where management estimates revenue can be 5% to 7% better than the next-best location.
Dhingra: "We are doing daily revenues of around INR1.5 crores per day from that plant as of 20th November. And we see that in the next month or so, we will reach the peak revenue from this plant."
The Under-Construction Pipeline: Funding, Timing and Flexibility
- 4.2 GW by FY27: All under-construction capacity is expected to be charged before financial year 2027, with connectivity dates arriving before that deadline. Where connectivity is already live, the company will attempt earlier commissioning.
- Three-source funding model: The capex plan rests on IPO equity proceeds (₹1,800–₹2,000 crores earmarked for debt retirement), operating cash flows from the existing 2.5 GW portfolio, and savings captured by the in-house EPC capability. Management stated it does not think it will need to raise equity based on current estimates.
- Capex estimate caveat: The ₹40,000–₹42,000 crore total capex estimate carries an 8%–10% contingency and is based on current costs; management declined to hazard a guess for projects timed for 2027–28, noting actual costs could move in either direction.
- Project timing flexibility: Some new bids allow connectivity in 2027 or 2028, letting the company sequence execution in two blocks: 2024–26 and 2026–28. This reduces the pressure to lock in capex commitments too far ahead.
- Bikaner 2 (Sikar) merchant bridge: The plant will operate on the merchant market for six to 12 months before being placed into upcoming bids as a PPA asset; management was explicit it does not want to play the merchant market for 25 years.
PPA Signings: The Near-Term Catalyst
- What is signed: The SJVN 570 MW PPA is fully signed. Half of the SECI 380 MW and part of the SECI 350 MW are signed.
- What is pending: The NHPC 680 MW PPA awaits state government consent, expected "in a month or so." The remaining SECI tranches are held up by state-specific decision-making processes, some of which were paused during elections.
- Election-driven delays: Some PPAs expected in October were delayed because SECI must go to every state for approval, and election announcements halt that process. Management expects most PPAs to be concluded in the next few weeks or one to two months.
- Tariff context: On the ₹2.51 tariff that drew analyst attention, management pushed back, arguing that capex costs have fallen to a level where that tariff is "actually a good tariff."
Upadhyay: "To be very specific to your answer to the question, actually, INR2.51 is not a bad tariff. It is because the capex has come down to the level that it is actually a good tariff."
Balance Sheet & Refinancing: Deleveraging in Motion
- Net debt moved up: Net debt increased by ~₹1,200 crores QoQ, the bulk of it funding capex on under-construction projects.
- Three refinancings sanctioned: One disbursement has been taken; two are yet to be drawn. The objectives are to extend tenor (boosting free cash flow to equity), reduce the interest rate, and diversify the lender base. Combined, the three are expected to yield ₹400–₹500 crores.
- Rating uplift in progress: One project is targeting a AA rating, with the outcome expected imminently. Management indicated an 8.7% rate for a AA handle versus 8.9% for a single-A rated plant.
- Lender diversification: The company is working with NaBFID and MNC banks to broaden its funding sources beyond the existing lender group.
- Cost of debt outlook: Management expects under-construction borrowing costs to fall as the base rate declines; the best-case rate today is 8.5% for operational assets and 9.25%–9.3% for under-construction.
- GST search resolved: A GST team visited on listing day regarding input tax credit on services from a couple of vendors. The impact was less than half a million dollars, no notice was given post-search, and there are no financial implications.
Portfolio Performance: Seasonality, CUF and the Tariff Mix
- Q2 seasonality: Revenue dropped ~10% QoQ due to the monsoon season across India, including Punjab; the distributed portfolio is affected every year from June through September.
- CUF improved operationally: Consolidated CUF rose from 23.3% to 24.6% in H1 FY25 versus H1 FY24, driven by operational improvements such as robotic cleaning.
- Revenue growth lags generation growth: Like-to-like revenue growth was lower than generation growth because new plants come at lower tariffs. The weighted average portfolio tariff was ₹4.39, while new plants are in the ₹2–₹3 range.
- 50 MW added: The Aklera project contributed 50 MW of new capacity during the half year.
- 1,200 MW plant status: First-time charging was completed for all four plants. The plant is selling power to the PPA purchaser or on the merchant market under a NOC, but it has not yet been capitalized. Synchronization of four plants together took longer than expected, a first-of-its-kind complexity in India.
Strategy & Capital Allocation: Consolidation Over Aggression
- Bias to consolidate: Management was explicit that it has "enough on our plate" and will not be aggressive in winning new bids. It may take a small chunk if returns are good, but the priority is executing the existing pipeline.
- Hurdle rate governs growth: The company targets a mid-teen FCFE IRR over 25 years and does not bid for a specific tariff. If mid-teen returns are not available, it will slow growth and reduce debt from internal cash flows.
- No monetization planned: Management does not want to monetize assets currently and wants to consolidate. On InvITs, it stated there is "nothing on the table" and "no plan of doing as of now," with no timeline. If forced to compare, an InvIT scores better than an asset sale, but no decision has been made.
- Integrated model as the moat: The fully integrated design-construct-engineer-operate model lets the company capture the entire value chain, optimize technology, time and tariff, and remain competitive. The shift toward FDRE and hybrid solutions has captured large market share by increasing the solar component and reducing the wind component to improve predictability.
- First wind plant imminent: The company's first wind plant is expected to come up in about a month, marking a diversification milestone.
Dhingra: "If the mid-teen returns are not available, we may slow our growth, of course, and at that time, we can reduce our debt from our internal cash flows and that is how we will size up the market."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Under-construction pipeline commissioning | All 4.2 GW under construction to be charged | Before FY27 |
| NHPC 680 MW PPA signing | State consent expected | "In a month or so" |
| Most pending PPAs concluded | Bulk of remaining SECI and other PPAs signed | "Next few weeks or 1–2 months" |
| IPO proceeds deployment | Retire ~₹1,800–₹2,000 crores of debt | Not specified; proceeds received |
| Three refinancings | Two pending disbursements to be drawn; combined yield ₹400–₹500 crores | Not specified; sanctions achieved |
| Growth calibrated to hurdle rate | Slow growth and reduce debt from internal cash flows if mid-teen returns unavailable | Ongoing discipline |
| Bikaner 2 (Sikar) plant | Operate on merchant market, then place into upcoming bids as PPA | Merchant for 6–12 months |
| First wind plant | Commissioning | "In a month or so" |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Revenue | ₹295 cr, up 7.4% YoY (adjusted for monetized assets) |
| EBITDA | ₹256 cr, up 3.7% YoY |
| EBITDA margin (consolidated) | 87–88%, marginal dip due to manpower ramp-up for under-construction projects |
| EBITDA margin (project level) | 92–94% |
| Cash PAT | ₹75 cr, up 75% YoY |
| Net debt | ₹8,755 cr, comprising ~₹5,500 cr operational project debt; net debt to steady-state EBITDA 4.9x |
| Net debt movement | +₹1,200 cr QoQ, largely to fund capex of under-construction projects |
| Operational capacity | 2.5 GW AC, up from 1.3 GW after energizing 1,200 MW in October |
| Under-construction capacity | 4.2 GW, commissioning expected before FY27 |
| Total portfolio | 6.7 GW including operational and pipeline |
| CUF | 24.6% in H1 FY25, improved from 23.3% in H1 FY24 |
| Weighted average portfolio tariff | ₹4.39 |
| Greenfield debt tied up | ₹14,000 cr from PFC, REC, SBI, IREDA for under-construction projects |
| Refinancing rate achieved | 8.7% for AA-rated plant, 8.9% for single A-rated plant |
| Under-construction cost of debt | 9.4–9.5% |